Applied Digital's interest bill passed its rent for the first time: $77.4 million vs $65.8 million

Applied Digital's quarterly interest expense passed its base rent for the first time, and its CEO says 800 megawatts of the buildout still needs financing. The AI buildout's bottleneck has moved from demand to the price of borrowed money, and shareholders are absorbing the difference.

Richard TangRichard Tang · 3 min read
Share
Wes Cummins, chief executive of Applied Digital, appearing on Bloomberg's The Close
1 / 7Slide 1 of 7
Wes Cummins, chief executive of Applied Digital, on Bloomberg's The Close on October 13, 2026, where he said financing has become more difficult.

For the first time, Applied Digital's+0.99% — Applied Digital, up 0.99 percent today quarterly interest bill has passed its rent. In the quarter ended August 31, the AI data-center landlord booked $77.4 million of interest expense 1. Its base rent came to $65.8 million, less than the interest for the first time since the leasing business began 12. That arithmetic, not any wobble in demand, took the stock to a 52-week low of $17.16 on November 2 and pulled Nebius+3.97% — Nebius, up 3.97 percent today, CoreWeave+2.00% — CoreWeave, up 2.00 percent today and IREN+2.36% — IREN, up 2.36 percent today down about 6% with it 23.

Lenders now collect more than the tenants pay

The mechanism matters more than the headline. Applied Digital builds powered campuses and leases them on take-or-pay contracts of 15 years or more to investment-grade hyperscalers 5. It holds roughly $36 billion of contracted revenue across five campuses 1.

It has leased 1.41 gigawatts of capacity and switched on 250 megawatts, so most of the rent is still to come while the debt is drawing now 1. Fit-out fees and interest on its $3.7 billion cash pile narrow this quarter's gap 18, but fit-out is pass-through construction work; the recurring rent is what has to carry the debt.

Capex has outrun revenue for nine straight quarters, on borrowed money

  • Revenue
  • Capex
  • Total debt, quarter-end
$0B$2B$4B$6B$8BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26capex hit $2.1B while rent wasstill ramping
Data
RevenueCapexTotal debt, quarter-end
Q2 '24$0.04B$0.04B$0.14B
Q3 '24$0.04B$0.06B$0.43B
Q4 '24$0.04B$0.17B$0.8B
Q1 '25$0.05B$0.26B$0.99B
Q2 '25$0.05B$0.17B$0.91B
Q3 '25$0.08B$0.25B$0.7B
Q4 '25$0.13B$0.55B$2.61B
Q1 '26$0.13B$0.78B$2.83B
Q2 '26$0.26B$1.29B$5.1B
Q3 '26$0.34B$2.08B$6.48B
Quarterly revenue and capital expenditure, with quarter-end total debt, in billions of US dollars; fiscal quarters labeled by calendar quarter. Source: Applied Digital SEC filings.9

The bottleneck moved from demand to the price of money

On November 2, chief executive Wes Cummins told CNBC that about 800 megawatts still need financing over the next 12 months, and he rejected the compute-seller label: "We're effectively a highly technical real estate business 45. Long-term leases, high-quality tenants." 45 The unfinanced capacity is leased to tenants rated AA or better, he said, and the bond market stays open at a price 5.

The price is the story. Macquarie's preferred equity in the campuses earns 12.75%, a rate we mapped in October when the lender side drew its line; the newest secured notes were sold at 7% 124.

Elon Musk, having borrowed $40 billion for SpaceX's+0.74% — SpaceX, up 0.74 percent today own chips, says debt markets have "almost entirely shut off" for anyone without revenue independent of data centers, promising "guppy-level death" for the 200-plus neoclouds 67. Nvidia's+2.91% — Nvidia, up 2.91 percent today Jensen Huang names the same constraint from the other end: demand is "off the charts", capital is what is scarce 6.

Shareholders hold the gap; the tenant's credit is the collateral

Who pays is the equity, down 51% in a year 2, with fiscal-2028 consensus swinging in three months from a small profit to a projected loss of 78 cents a share 24. Who benefits is the tenants. CoreWeave, about 30% of contracted revenue, rents campuses financed on someone else's balance sheet, and its own customer at the site is Meta+0.45% — Meta, up 0.45 percent today, which Cummins says improves the credit 245.

Revenue is running four times last year's level; the net loss widened anyway

  • Revenue
  • Net income (loss)
-$0.4B-$0.2B$0B$0.2B$0.4BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$0.34B-$0.24B
Data
RevenueNet income (loss)
Q4 '24$0.04B-$0.14B
Q1 '25$0.05B-$0.04B
Q2 '25$0.05B-$0.05B
Q3 '25$0.08B-$0.02B
Q4 '25$0.13B-$0.02B
Q1 '26$0.13B-$0.1B
Q2 '26$0.26B-$0.11B
Q3 '26$0.34B-$0.24B
Quarterly revenue and net income (loss), in billions of US dollars; fiscal quarters labeled by calendar quarter, most recent the quarter ended August 31, 2026. Source: Applied Digital SEC filings.9

CoreWeave itself owes $51.6 billion against $5.5 billion of cash, and its interest bill already runs at about a quarter of its revenue 7. The demand for AI compute is signed; the debt that houses it is not. January's fiscal Q2 report prices the next tranche, and whoever can fund the gap cheapest captures this stretch of the buildout 7. None of this argues against AI adoption; it argues for reading the financing hop as closely as the model releases.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading APLD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Super Micro pre-announced up to $19.5 billion in sales; tonight's report must show neocloud customers can pay

    The AI server builder's October 20 preview lifted September-quarter revenue to $18.5–19.5 billion and gross margin to 12.0–12.5%, and the stock has since handed the rally back. After the close tonight, the report has to show the margin holds and that its neocloud customers can still fund the racks.

    Data Center

    Meta's Ohio data center faces Tuesday's vote with 90.5% of 10,202 hearing comments against

    A database logged one day before the midterms counts 10,202 public comments at US local hearings: 90.5% negative, water the top complaint, AI mentioned in a fifth. More than 40 ballot measures on Tuesday put the bill on builders' permits, pipes and wires.

    Data Center

    Nidec's 3.2MW AI cooler is on schedule; its audit is not

    Nidec announced a 3.2MW in-row cooler for 800-volt AI racks the same week its auditor declined to sign its accounts and Tokyo's exchange began a listing review. The product ramp and the accounting clearance now run on different clocks, and the second one prices the stock.

    Data Center

    Hedge funds sold IREN as AI exposure; $4 billion of contracts must convert on November 5

    The funds that bought bitcoin miners as AI exposure sold them as AI exposure in October, Goldman Sachs prime-brokerage data show. IREN reports fiscal first-quarter results on November 5, with consensus at $221.71 million of revenue and a $0.76 loss per share, and the print decides whether $4 billion of contracted capacity is converting or stalling.

    Data Center

    American Tower owns Dish's abandoned 5G radios; SpaceX may be the buyer as US property revenue falls 3%

    A bankruptcy abandonment order gave the tower operator its dead customer's radios the same week it guided US property revenue down 3%. About 400 basis points of that hole is one company, and the likeliest buyer of the gear is the company building a network to replace its remaining tenants.

    Data Center

    Equinix's record quarter ran on $3.8 billion of new debt and a $2 billion stock shelf

    Record bookings and a third guidance raise, but the build ran on $3.8 billion of new debt and a $2 billion share-sale shelf filed an hour after results. Who pays if the build outruns the bookings.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.