Backblaze's $437 million market cap rests on a $400 million order book

CoreWeave beat third-quarter estimates and raised 2026 guidance, yet its 2031 notes still yield 15.5%. Backblaze, spending ahead of the customer's monthly minimums, now trades below where it sat before its own report.

Vincent JiangVincent Jiangthree-minute read
Share
Michael Intrator, CoreWeave's co-founder and chief executive, gesturing while speaking on a panel against a blue backdrop at the World Economic Forum in Davos
CoreWeave chief executive Michael Intrator at the World Economic Forum's annual meeting in Davos in January 2026. The company beat third-quarter estimates and raised 2026 guidance, while its 2031 notes still yield 15.5%.

CoreWeave rallied on the beat; Backblaze slipped

On November 2, 2026, Backblaze−2.25% — Backblaze, down 2.25 percent today (BLZE), the cloud-storage small cap, said the signed order book in its filings, remaining performance obligations, jumped from $70 million to $400 million in a single quarter, chiefly on the CoreWeave−1.24% — CoreWeave, down 1.24 percent today order forms signed June 16, a deal The Inference covered in October as a credit bet 1.

Eight days later the customer reported: CoreWeave (CRWV), the GPU cloud renting out AI computing, posted third-quarter revenue of $3.66 billion, up 168% and ahead of the $3.55 billion consensus, lost $709 million, raised 2026 guidance to $13.0-13.3 billion, and closed up 24% the next day 23. Backblaze slipped the other way: $6.91 on November 17, under the $7.40 it closed at before its own report, a market capitalization near $437 million, barely more than the order book itself 41.

The beat did not reach the bonds

CoreWeave raised about $4.2 billion of convertible notes during the quarter 3; on report day its 9.75% notes due 2031 still yielded 15.5%, five-year credit-default swaps, the price of default insurance, stood near 1,152 basis points, and roughly $15 billion of principal is due through 2028 per its second-quarter statement 5. Debt reached $46.8 billion at September 30, from $21.4 billion at year-end, and net interest of $846 million in the quarter is guided to $1.05-1.15 billion in the fourth 6.

CoreWeave tripled quarterly revenue in a year; its 2031 notes still yield 15.5%

Revenue tripled in a year while the 2031 notes still yield 15.5%

$0B$1B$2B$3B$4BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '262031 notes still yield 15.5%
Data
Revenue
Q2 '24$0.4B
Q3 '24$0.58B
Q4 '24$0.75B
Q1 '25$0.98B
Q2 '25$1.21B
Q3 '25$1.37B
Q4 '25$1.57B
Q1 '26$2.08B
Q2 '26$2.58B
Q3 '26$3.66B
Quarterly revenue from CoreWeave's SEC filings, Q2 2024 through Q3 2026, in USD billions; the 2031-note yield is CNBC's November 10 reading.8,5

Backblaze pays before the minimums arrive

None of the 47% growth in Backblaze's B2 storage came meaningfully from CoreWeave 17. Chief financial officer Marc Suidan says the customer ramps "all the way through middle of next year," with full ramp by Q3 2027 7. The costs front-run that: fourth-quarter equipment spend of $65-83 million, capex at 55-65% of revenue, and depreciation that lands before the revenue it serves, cutting gross margin by 3-6 points 7. The money is $201 million of zero-coupon converts due 2031 converting at $21.94, triple the share price, with capped calls shielding old holders only up to $33.76 17.

A red Backblaze Storage Pod chassis, opened to show rows of hard drives and cooling fans, standing among server racks in a data center aisle
A Backblaze Storage Pod, the dense hard-drive design the company uses to hold its multi-exabyte B2 cloud. Backblaze's B2 storage grew 47% while it spent ahead of CoreWeave's contract minimums.ChrisDag via Wikimedia Commons

Backblaze's $6.91 share price sits at a third of its converts' $21.94 conversion price

$0$10$20$30$40Share price, Nov 17$6.91Close before Nov 2 report$7.4Convert conversion price$21.94Capped-call ceiling$33.76
Data
Value
Share price, Nov 17$6.91
Close before Nov 2 report$7.4
Convert conversion price$21.94
Capped-call ceiling$33.76
Backblaze's closing share price on November 17, 2026 and before its November 2 report (Yahoo Finance), against the $21.94 conversion price and $33.76 capped-call ceiling on its $201 million of zero-coupon 2031 notes. USD per share.4,1

Prepayments, not parent debt, carry the build

The bull case carries numbers too. Chief executive Michael Intrator counts on roughly $9 billion of customer prepayments and deposits within three months plus hardware-partner financing, and finance chief Nitin Agrawal says CoreWeave will not issue parent-level unsecured debt through 2027 because its secured loans trade near par 26.

Asked why not retire bonds yielding about 15%, Intrator said he can "deploy the capital at a higher rate of return" 3. Backblaze chief executive Gleb Budman, asked about the market's concern, answered: "We don't see any signs of any risk or any concern. It's a committed contract with committed minimum ramps" 7.

CoreWeave's capex has outrun operating cash in every quarter of the last two years

  • Capex
  • Operating cash flow
-$5B$0B$5B$10BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26Capex $9.4B vs operating cash$2.0B
Data
CapexOperating cash flow
Q2 '24$2.25B-$0.12B
Q3 '24$1.22B$0.64B
Q4 '24$3.5B$0.19B
Q1 '25$1.41B$0.06B
Q2 '25$2.45B-$0.25B
Q3 '25$2.39B$1.69B
Q4 '25$4.06B$1.56B
Q1 '26$7.7B$2.98B
Q2 '26$6.42B$0.68B
Q3 '26$9.44B$1.98B
CoreWeave quarterly capital spending and operating cash flow from its SEC filings, Q2 2024 through Q3 2026, in USD billions. Capex is capital spending shown as a positive number.9

Watch Backblaze's fourth-quarter gross margin, where the build's depreciation first shows, and the 2031 yield as CoreWeave's minimums step up monthly through July 2027 75. The order book is a promise from a company whose creditors charge 15.5% to wait 75.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading BLZE

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CleanSpark's $2.276 billion notes are built to survive losing Meta; shareholders hold $4.1 billion of debt

    The Sandersville indenture, read line by line on November 16, hands bondholders a $327 million reserve, rent-shaped repayment and a named list of fallback tenants. Shareholders hold about $4.1 billion of debt, a building that opens in late 2027, and 885 megawatts with no lease.

    Data Center

    Morgan Stanley starts Comfort Systems at $1,410, lowest target on the street

    Comfort Systems just printed record revenue, EPS and a $17.81 billion backlog, and its stock has still lost about half its value since June. Morgan Stanley's initiation is a bet that the order book turns into 2027 profit.

    Data Center

    Equinix plans a $500 million Dallas data center; Blackstone pays a 7% yield for Amazon-leased buildings

    A Texas permit for DA13 landed the same week Equinix closed its largest-ever green bond and Blackstone's new trust paid a 7% cap rate for Amazon-leased data centers. The AI buildout is not the risk; the cost of the capital funding it is, and the bill lands on Equinix's bondholders and shareholders.

    Data Center

    Zhongji Innolight fell 8% to a year low on quant selling, not a US transceiver ban that only bites in 2028

    The FCC draft bars only new transceiver models, a rule that bites with the 3.2T generation in 2028, while October's forced quant selling set this week's price. Innolight's owners are paying for a rout, not for a policy that has not taken effect.

    Data Center

    Trane Technologies' $12.5 billion backlog waits on suppliers; CEO sees margin relief in six to nine months

    At the Baird conference on November 12, Dave Regnery put the constraint on Trane's $12.5 billion backlog in its suppliers' plants rather than its own, with relief expected in six to nine months. With detailed 2027 guidance deferred to fourth-quarter results, that timeline is the only forward margin guide investors hold.

    Data Center

    Legrand puts data centers at 32% of revenue just as Thailand asks 49 data-center builds to pause

    The French group's Southeast Asia chief put numbers on its AI exposure: data centers are about a third of revenue and close to €3 billion a year, just as Thailand and Singapore start rationing the power and water new builds need.

    Subscribe to TheInference for free