CleanSpark's $2.276 billion notes are built to survive losing Meta; shareholders hold $4.1 billion of debt

The Sandersville indenture, read line by line on November 16, hands bondholders a $327 million reserve, rent-shaped repayment and a named list of fallback tenants. Shareholders hold about $4.1 billion of debt, a building that opens in late 2027, and 885 megawatts with no lease.

Vincent JiangVincent Jiangthree-minute read
Share
S. Matthew Schultz, chief executive of CleanSpark, in a blue plaid blazer and glasses against a dark background
S. Matthew Schultz, CleanSpark's chief executive, calls the Sandersville project "fully funded through completion."

One sentence of news, 1.65 megabytes of small print

On November 16, Randeep Bubbra, an infrastructure-finance lawyer, published a clause-by-clause read of the indenture behind CleanSpark's−2.54% — CleanSpark, down 2.54 percent today September 25 bond: $2,276.0 million of 7.875% senior secured notes due October 1, 2031, sold at 98.5% of face by CSDC Finance I, a CleanSpark subsidiary 12. The closing press release carried a single sentence of terms 6. The indenture exhibit behind it runs 1.65 megabytes 7. The same day, the shares closed at $6.25, down 5.74% 3, and D. E. Shaw's funds filed a passive stake of 17,286,575 shares, 6.7% of the class, as of September 30 4.

The bond follows one lease, and survives losing it

Every clause points at one building. Sandersville, Georgia sits under a 20-year triple-net lease, dated July 9, 2026, with Anviran, LLC, described in the company's October update as a Meta−0.93% — Meta, down 0.93 percent today subsidiary and guaranteed by Meta Platforms itself, worth about $6.6 billion of contracted revenue over the initial term and scalable to $11.6 billion with extensions 159.

Interest pays from issue; principal waits until every phase reaches full rent, then amortizes in instalments sized so rent covers each payment 1.275 times over, behind a $327.0 million reserve funded at closing 18. Lose the lease or the guarantee and the issuer has six months, extendable to twelve, to re-let from a pre-approved list: Amazon−0.34% — Amazon, down 0.34 percent today, Apple−0.52% — Apple, down 0.52 percent today, Microsoft−3.42% — Microsoft, down 3.42 percent today, Alphabet−0.64% — Alphabet, down 0.64 percent today, Nvidia−1.64% — Nvidia, down 1.64 percent today, or any listed hyperscaler above $100 billion of market value 1.

Termination money above $15.0 million must be offered to noteholders at par 1. The bond was built to survive losing Meta; nothing in the indenture protects the share price.

The equity holds everything the indenture leaves

A market note on November 17 put CleanSpark's debt since September at roughly $4.1 billion 8. The last filed balance sheet, for the June quarter, showed $1.782 billion, and the new notes alone add $2.276 billion, which lands within rounding of that figure 13.

In Texas, up to 885 megawatts sit under exclusivity with no signed lease, an ERCOT review is expected in mid-December, and Sandersville opens at the end of 2027 8. Chief executive Matt Schultz calls the project "fully funded through completion" 5.

Retail posters on Stocktwits expect a Meta lease for Texas to arrive with the November 24 earnings print 1112; exclusivity is a negotiating position, not a contract 8. Bernstein's Chad Dillard still rates the stock a Buy at $11, against a consensus average target of $17.92 10.

The September notes more than doubled CleanSpark's debt

Filed debt was $1.78 billion in June; the notes take it near $4.1 billion

  • Total debt
  • Estimate
$0bn$2bn$4bn$6bnQ1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26After Sept '26 (est.)$1.78bn$2.276 billion notes closed 25Sept
Data
Total debt
Q1 '25$0.65bn
Q2 '25$0.82bn
Q3 '25$0.82bn
Q4 '25$1.79bn
Q1 '26$1.79bn
Q2 '26$1.78bn
After Sept '26 (est.) (estimate)$4.1bn
Total debt at fiscal quarter ends from SEC filings; the last bar is a market-note estimate for after the September issues, not a filed balance sheet.13,8

Three dates decide it

The November 24 print, the mid-December ERCOT review, and the Final Commencement Date, the day every phase of Sandersville pays full rent and the notes start to amortize, settle whose claim is real. The Inference sized this lease in October and found the same megawatt-versus-lease gap at Cipher Digital−2.45% — Cipher Digital, down 2.45 percent today last week. Any Texas deal will surface as an SEC filing before it surfaces anywhere else.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading CLSK

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Morgan Stanley starts Comfort Systems at $1,410, lowest target on the street

    Comfort Systems just printed record revenue, EPS and a $17.81 billion backlog, and its stock has still lost about half its value since June. Morgan Stanley's initiation is a bet that the order book turns into 2027 profit.

    Data Center

    Equinix plans a $500 million Dallas data center; Blackstone pays a 7% yield for Amazon-leased buildings

    A Texas permit for DA13 landed the same week Equinix closed its largest-ever green bond and Blackstone's new trust paid a 7% cap rate for Amazon-leased data centers. The AI buildout is not the risk; the cost of the capital funding it is, and the bill lands on Equinix's bondholders and shareholders.

    Data Center

    Zhongji Innolight fell 8% to a year low on quant selling, not a US transceiver ban that only bites in 2028

    The FCC draft bars only new transceiver models, a rule that bites with the 3.2T generation in 2028, while October's forced quant selling set this week's price. Innolight's owners are paying for a rout, not for a policy that has not taken effect.

    Data Center

    Trane Technologies' $12.5 billion backlog waits on suppliers; CEO sees margin relief in six to nine months

    At the Baird conference on November 12, Dave Regnery put the constraint on Trane's $12.5 billion backlog in its suppliers' plants rather than its own, with relief expected in six to nine months. With detailed 2027 guidance deferred to fourth-quarter results, that timeline is the only forward margin guide investors hold.

    Data Center

    Legrand puts data centers at 32% of revenue just as Thailand asks 49 data-center builds to pause

    The French group's Southeast Asia chief put numbers on its AI exposure: data centers are about a third of revenue and close to €3 billion a year, just as Thailand and Singapore start rationing the power and water new builds need.

    Data Center

    MARA sold 13,597 bitcoin for $1.1 billion, cut debt 37%; two AI leases by Dec. 31 decide the stock