A bitcoin miner just priced $2.28B of bonds on Meta's guaranteed rent

SEC offering papers name Meta's subsidiary Anviran as the tenant behind the $6.6B, 20-year Sandersville lease, with Meta guaranteeing the rent. The notes priced on 18 September at 7.875%, one day after the Fed's first hike in three years, against a build CleanSpark had modeled at 7.5%.

Vincent JiangVincent Jiangthree-minute read
Share
Aerial view of a bitcoin mining campus: rows of blue-roofed mining containers arranged in a grid on bare ground, each with a small transformer station.
A bitcoin miner's campus from above: Hut 8's Medicine Hat, Alberta site. CleanSpark's Sandersville, Georgia campus is the same kind of rural mining build, now leased to Meta for AI compute.

For two months CleanSpark hid its tenant behind the phrase "high investment grade leading global technology company" 1. The offering papers filed 17 September ended the guessing: the tenant is Meta+2.23% — Meta, up 2.23 percent today, through wholly owned subsidiary Anviran LLC, which signed a 20-year, roughly $6.6B lease on the 175 MW Sandersville, Georgia campus with 3% annual rent increases 23.

Bond buyers own Meta's rent, not the miner's balance sheet

Subsidiary CSDC Finance I issued the notes; project entity CSRE Properties Sandersville guarantees them, secured by first-priority liens on substantially all project assets 45. CleanSpark the parent signs only a customary completion guarantee, funding the build if note proceeds run short 45. Meta separately guarantees Anviran's rent and operating expenses 12. Bond buyers are not lending to a bitcoin miner; they are buying two decades of Meta-guaranteed rent with the miner as general contractor.

Meta's name was worth 7.875% one day after the Fed hiked

The filing modeled the $2.08B build at an illustrative 7.5%, with first rent in November 2027 and full build-out in March 2028 12. Market talk for CleanSpark's first junk-bond offering ran near 8.5%, about two points above the BB-rated average 6.

The deal priced anyway on 18 September: $2.276B of senior secured notes due 2031, a 7.875% coupon at 98.5 cents on the dollar, Morgan Stanley+0.55% — Morgan Stanley, up 0.55 percent today leading with Goldman Sachs−0.23% — Goldman Sachs, down 0.23 percent today and Wells Fargo 56. The pricing landed one day after the Fed's 25-basis-point hike on 17 September, its first in three years 2. Closing is set for 25 September 5.

0%2%4%6%8%10%Modeled in the filing7.5%Priced 18 September7.88%Market talk before pricing8.5%
Data
Value
Modeled in the filing7.5%
Priced 18 September7.88%
Market talk before pricing8.5%
Meta's guarantee pulled the coupon in below the 8.5% talk and within half a point of the 7.5% the filing had modeled, even with a Fed hike the day before.1,2,5,6

300 of 885 Texas megawatts are still a study away

Meta's exclusivity agreement reaches past Georgia: an LOI for up to 885 MW at CleanSpark's Sealy and Brazoria sites 12. ERCOT has locked in 585 MW of base load; the remaining 300 MW is "studied load," waiting on the Batch Zero allocation study due next April, which can return fewer megawatts than requested 12.

0 MW200 MW400 MW600 MWSandersville, leased175 MWTexas base load, secured585 MWTexas studied load, pending Batch Zero300 MW
Data
Value
Sandersville, leased175 MW
Texas base load, secured585 MW
Texas studied load, pending Batch Zero300 MW
Meta's Texas option runs several times its Georgia lease, and the highlighted slice is the part still waiting on an ERCOT study that can come back short.1,2

Two camps now: miners with a Mag 7 tenant, and miners without

The analysts who revealed the tenant called the split plainly: an investment-grade counterparty is "more important than ever" after the hike, while smaller operators who cannot land one face "less favorable" terms and "eye-watering rates" on any project financing 1. The same 25-basis-point move is expected to tighten credit for non-investment-grade companies across the board 2.

The 2031 maturity leaves the refinancing to CleanSpark

The market's first verdict favored the miner: CLSK up 8.39% on the day, META down 2.43% 12. But the notes come due in 2031, years before the 20-year lease runs out, and that refinancing belongs to CleanSpark, not Meta 45. Watch the closing on 25 September, the Batch Zero study in April, and first rent in November 2027 15. Meta has rented its megawatts; the megawatt lottery is still CleanSpark's to lose.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading META

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Akamai's founder-CEO bought $2.6 million of its stock at $85.08, no trading plan

    F. Thomson Leighton paid $85.08 a share in cash on the open market, with no trading plan, a day after Akamai closed $2.5 billion of 1% convertible debt. Every other claim on the company's upside starts above $102; his entry marks where the man running the AI build-out values the equity.

    Data Center

    Legrand raises 2026 outlook again to 11-13% organic growth as data centers grow near 40%

    Legrand lifted its 2026 organic growth target to 11-13% after nine-month sales of €8.33 billion, and UBS turned buyer with a €170 target. Investors are now paid an 8% discount to Schneider Electric and ABB to hold a group whose growth sits in one product line.

    Data Center

    Cipher Digital fell 20% in a week on a Texas data-center moratorium aimed at campuses it has not leased

    A fifth of Cipher's value vanished in a week on a risk aimed at campuses it has not leased, while rent on the ones it has is now being booked. The exposure that reaches shareholders is funding the next build, behind $6.7 billion of debt and a spent-down bitcoin treasury.

    Data Center

    Fujikura banked ¥235 billion, mostly from AI fiber, then guided to ¥194 billion in the second half

    The AI data-center fiber supplier banked ¥235 billion of operating profit by September, raised its full-year revenue outlook and doubled the dividend, yet its own ¥429 billion guide plans a smaller, lower-margin second half. Investors deciding whether that is prudence or slowdown are the ones whose money moves.

    Data Center

    Accelevation's owners took $318.4 million in nine months and left $4.5 million of equity behind

    The AI data center builder's first public balance sheet shows $318.4 million taken out by its owners in nine months, $648.8 million of debt, $4.5 million of equity left behind, and 66% revenue growth that produced a 77% profit decline.

    Data Center

    Akamai paid $284 million to keep $2.5 billion of new debt at 1%

    The closing terms itemize the cost of Akamai's cheap money: $284.4 million for the hedge, warrants on 23.3 million shares struck up to 40% above the market, and a race between an Anthropic-backed build-out and a $1.15 billion maturity next September.

    Subscribe to TheInference for free