Core Scientific's $1.2 billion profit is mostly a warrant gain, not rent

The miner turned landlord booked $215.4 million of colocation rent, then reported a $1.18 billion profit that was mostly a warrant gain, while its anchor tenant's bonds trade near distressed levels and its own buildout leans on that tenant's cash.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
Adam Sullivan, chief executive of Core Scientific, seated at a microphone in a grey interview set
Adam Sullivan, chief executive of Core Scientific, in a November 2026 sit-down. His company's $1.18 billion third-quarter profit was mostly a non-cash warrant gain.

The mining is gone; the rent is real

Core Scientific's−0.64% — Core Scientific, down 0.64 percent today third quarter ended the argument about what the company is. Colocation, renting powered data center halls to AI computing firms, brought in $215.4 million of $232.9 million total revenue, up from $15.0 million a year earlier 93. Self-mining produced $12.3 million and stops by December 31, 2026, when the company becomes a landlord full time 93. Billing capacity reached 485 megawatts, worth over $700 million in annualized colocation revenue 9.

Colocation replaced mining as Core Scientific's revenue in four quarters

Colocation went from about a fifth of mining-era revenue to 92 percent in a year

  • Colocation
  • Self-mining
$0M$100M$200M$300MQ3 2025Q3 2026$215.43M
Data
ColocationSelf-mining
Q3 2025$14.95M$57.44M
Q3 2026$215.43M$12.26M
Revenue by segment, in millions of dollars, for the quarters ended Sept. 30, 2025 and Sept. 30, 2026. Colocation is 92 percent of third-quarter 2026 revenue; self-mining stops by December 31, 2026. Sources: Core Scientific's third-quarter 2026 results, Form 8-K (Nov. 5, 2026), and Texas Technology News on bitcoin miners turned AI landlords.9,2

The profit is paper, the bill is cash

Net income of $1.18 billion carried a $1.03 billion non-cash gain on the fair value of warrants; operating income was $72.4 million 9. The quarter cost $985.1 million of capital spending, long-term debt stands at $4.30 billion, and book equity is negative $1.09 billion 9.

Net income swings on warrant marks while free cash flow stays negative

  • Net income
  • Free cash flow
-$2B-$1B$0B$1B$2BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26
Data
Net incomeFree cash flow
Q3 '24-$0.46B-$0.03B
Q4 '24-$0.29B-$0.02B
Q1 '25$0.58B-$0.13B
Q2 '25-$0.94B-$0.09B
Q3 '25-$0.14B-$0.11B
Q4 '25$0.22B-$0.12B
Q1 '26-$0.35B-$0.14B
Q2 '26-$1.16B-$0.82B
Q3 '26$1.18B-$0.24B
Net income and free cash flow, $ billions, for the quarters ended Sept. 30, 2024 through Sept. 30, 2026. Free cash flow is operating cash flow less capital spending. Source: Core Scientific's quarterly SEC filings.13

The tenant is paying the building bill. CoreWeave−4.22% — CoreWeave, down 4.22 percent today funded $180.9 million of Core Scientific's capital spending in the first nine months of 2026, with $202.2 million more of pass-through spending expected, and Core Scientific carried a $282.7 million customer funding receivable at September 30 19. A review of the results found the roughly $6 billion project-bond financing for the AMD−4.85% — AMD, down 4.85 percent today buildout still unsecured 2.

Aerial view of Core Scientific's Pecos, Texas data center campus under construction, with finished data halls and crane work on the next buildings
Core Scientific's Pecos, Texas campus in a November 2026 flyover. The company says the first tranche of capacity there is due in early 2027, funded in part by its tenant's cash.Core Scientific via X

The tenant's credit is the landlord's risk

CoreWeave is the anchor tenant under a 500-megawatt hosting agreement worth about $8.7 billion over 12 years 7. Its 9.625 percent note due 2032 fell to 74.9 cents on the dollar on November 24, the lowest since issuance 10. Its 2031 bond traded at 74.23 cents on November 25 for a 17.91 percent yield 4, and five-year credit default swaps, insurance against a missed payment, imply a 68 percent chance of default within five years 5. The stock halved after Core Scientific shareholders refused CoreWeave's $9 billion takeover bid; the rent ledger that survived is now priced against the would-be buyer's own bonds 11.

CoreWeave credit markerLevelDate
9.625% note due 203274.9 cents on the dollar, lowest since issuanceNov. 24, 2026
2031 bond74.23 cents on the dollar, 17.91% yieldNov. 25, 2026
Five-year credit default swaps68% implied chance of default within five yearsNov. 25, 2026
CoreWeave's debt and default insurance, as reported by GuruFocus, Investing.com and StockTwits on November 24 and 25, 2026.

The bull case has a second tenant

AMD has leased about 110 megawatts at the Hunt County, Texas site, a $1.3 billion project listed in the state's construction records, with first deliveries in the first half of 2028 3. Bernstein and B. Riley kept Buy ratings on the stock, at $19 and $27 price targets 1. Sellers did not care: the stock fell 10.8 percent on November 24 and sits below every major moving average 8.

The gate is ERCOT on December 10

December 10 6. ERCOT, the Texas grid operator, rules that day on 6.5 gigawatts of large-load designations under its Batch Zero review, Core Scientific among the applicants, and power approvals are the gate for everything above 6. For readers who want the same AI power demand without the tenant's credit risk, the same trade exists one step upstream as a power seller: Constellation Energy−2.93% — Constellation Energy, down 2.93 percent today, the nation's largest producer of clean energy, counts data centers among its customers 12.

Sources

  1. 1Poisar (fiscal.ai), Core Scientific Discloses Financial Details of CoreWeave Colocation Agreement, 19 November 2026
  2. 2Texas Technology News, Texas bitcoin miners become AI landlords: Riot's $28 billion Corsicana lease, 25 November 2026
  3. 3TokenPost, Texas Record Lists $1.3 Billion Data Center Project at Core Scientific Site, 25 November 2026
  4. 4Yahoo Finance (Investing.com), CoreWeave bonds plunge as 2031 yield surges to 17.91%; Shares drop 10%, 25 November 2026
  5. 5Yahoo Finance (StockTwits), ORCL, GOOGL, SPCX, CRWV Credit Default Swap Spreads Hit Records, 25 November 2026
  6. 6Yahoo Finance (Blockspace), 6.5 GW of Texas data center load faces December 10 ERCOT Batch Zero decision: Needham, 23 November 2026
  7. 7Construction Review Online, Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal, 19 November 2026
  8. 8Traders Union, Core scientific slides 10.82% today, 25 November 2026
  9. 9SEC Form 8-K, Core Scientific Announces Third Quarter 2026 Results, 5 November 2026
  10. 10Yahoo Finance (GuruFocus), CoreWeave's Debt Trades Near 75 Cents on the Dollar, 25 November 2026
  11. 11The Inference, CoreWeave owes $10.6 billion by 2027; its landlord Core Scientific just hit a 52-week low of $12.79, 16 October 2026
  12. 12Constellation, Electricity Provider and Gas Supplier, company website, retrieved 25 November 2026
  13. 13Core Scientific, quarterly figures from its SEC filings, retrieved 25 November 2026

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading CORZ

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Backblaze's new privacy notice says it sold user data to ad networks

    The revised notice, effective December 1, says the storage company sold identifiers, browsing activity and geolocation to ad networks, walking back an April promise. Its most loyal B2 customers noticed; the stock rally did not price them in.

    Data Center

    Digital Realty's 156MW Chicago-area data center wins a 4-2 council vote and a tax break

    Four days after President Trump threatened a "tremendous tax" on US companies building data centers abroad, the Austin landlord's domestic land bank cleared its first zoning test. Its October filing shows the record leasing quarter was led by Asia-Pacific, exactly the half of the pipeline the threat targets.

    Data Center

    IREN bought a $410,000 school to house builders for a $10 billion campus it has not funded

    IREN signed on November 23 for the former St John's Lutheran School in Eudunda to house workers for its 800MW Bundey campus, while $6 billion of its fiscal-year spending has no financing. GPU lenders now advance 50 to 60 cents on the dollar, so the gap closes with stock, not debt.

    Data Center

    Nebius has $6 billion to $11 billion left to raise for 2027, on top of $14.2 billion of debt

    Hewlett Packard Enterprise said on November 23 its finance arm has never lent to a neocloud, and Nebius's own guidance leaves roughly a fifth of next year's $40-45 billion build-out to outside capital, on top of $14.2 billion of debt. Whose money pays for the rest decides the stock.

    Data Center

    FCC approves SpaceX request for up to 1 million satellites for orbital data centers

    The first US authorization for a space-based AI compute constellation turns a contested proposal into an approved system with spectrum rights, and sets the template for rival orbital data-center filings.

    Data Center

    Databricks co-founder says one GPU cloud passed his security test; Nebius claims the spot

    A Databricks co-founder says just one neocloud passed his isolation bar, and Nebius claims the spot, while GPU lenders cut loan-to-value to 50-60%. The enterprise buyer and the creditor are asking the same question about the same companies.

    Subscribe to TheInference for free