Crusoe files a $4.8bn Jayton campus and Project Hyper hits $12bn with no tenant named

Two filings published today add a $4.8 billion Jayton campus to Crusoe's Project Hyper, taking the complex to $12 billion. The Jayton half names no tenant and delivers in 2029, against a ledger of six gigawatts sold and one standing.

Vincent JiangVincent Jiangthree-minute read
Share
Aerial view of a large single-story data center campus on open rural land at sunset
1 / 6Slide 1 of 6
A hyperscale data center campus on open rural land, the form of build-out Crusoe's filings describe. Crusoe's Jayton campus is not yet built; no licensed photo of the site exists.

Two filings on a county road

Two Texas filings published today put Crusoe$26.61B — Crusoe, private, latest valuation $26.61B on Country Road 233 in Jayton, Kent County: two data center buildings of 759,260 sq ft each, $4.8 billion of site investment, construction from the end of January 2027, and go-live dates of May and July 2029 1. Both are listed as "spur buildings" of Project Hyper, Crusoe's complex to the north in Childress 1.

Twelve billion dollars, fifteen days after the raise

Project Hyper's Childress half was filed in September: three buildings of 806,360 sq ft at $2.4 billion each, two already under construction, the third expected to start this month, all targeting completion in the first half of 2028 1. Together the two sites reach $12 billion, $7.2 billion in Childress and $4.8 billion in Jayton, committed by a company that fifteen days earlier initially closed a $3.9 billion Series F at a $30.9 billion post-money valuation 12.

The blank tenant line

Crusoe's ledger reads more than 6 GW of gross contracted capacity, about 1 GW delivered and operational, and over $140 billion of total contracted value on terms the release does not disclose 2, the gap Crusoe sold six gigawatts and built one mapped on 28 September. That leaves roughly five gigawatts to finance and build, and the Jayton filings add $4.8 billion to that side with no tenant named anywhere in them 1. Half of Project Hyper is now a $4.8 billion bet on a customer Crusoe has not named. The holders at the $30.9 billion mark include ARK Invest, Fundrise and Robinhood−1.43% — Robinhood, down 1.43 percent today Ventures Fund I 2.

The neighbors are pre-sold

Every Crusoe campus around Jayton carries a name. Lancium and Crusoe announced Childress in July as a 1 GW grid-connected campus on 270 acres, purpose-built for a hyperscaler the release left unnamed, and reports put Meta−4.64% — Meta, down 4.64 percent today in that space 13. IREN's−8.08% — IREN, down 8.08 percent today adjacent Childress site is committed to Microsoft−2.50% — Microsoft, down 2.50 percent today, four 50 MW phases under a five-year $9.7 billion contract with the first accepted in August 14. Abilene, where OpenAI$1.18T — OpenAI, private, latest valuation $1.18T trained Astra, has grown to 1.2 GW with a second 900 MW site underway, and Armstrong County is filed for Google 123. Jayton is the blank.

Crusoe's announced Texas campuses reach 3.1 GW; Jayton filed no megawatts at all

  • Estimate
0GW0.5GW1GW1.5GWAbilene campus1.2GWAbilene second site0.9GWChildress, Project Hyper1GWJayton spurs: sq ft and dollars, no MW
Data
Value
Abilene campus1.2GW
Abilene second site (estimate)0.9GW
Childress, Project Hyper (estimate)1GW
Gigawatts at full scale, per Crusoe and Lancium's 15 July 2026 Childress announcement; the 2 October Jayton filings state square feet and dollars, and no capacity.1,3

Signed demand is not poured concrete

The bull case is real and on paper: cloud bookings up more than 20-fold year to date, Managed Inference past $100 million in contracted annual recurring revenue, Meta, Microsoft and OpenAI all customers 25. None of it names a Jayton tenant or moves a 2029 delivery date. Contracts hedge demand falling; they do not hedge schedules slipping.

Watch January

The third Childress building starts this month; Jayton breaks ground at the end of January 2027 1. The tell stays operational gigawatts per quarter, where each one delivered converts backlog into asset and each slip converts it into carrying cost. January's groundbreaking is on a schedule. The tenant line is not.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HOOD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Riot Platforms must refinance $20.8 million drawn on a $573 million Rockdale bridge by December 31

    The Rockdale bridge, and the Corsicana project-debt raise behind it, are the first market-priced test of Anthropic's $37 billion of rent, the worry behind Keefe, Bruyette & Woods' November 11 downgrade.

    Data Center

    Ford won't force AI data centers on Ontario cities that say no, stranding Prologis's 40-megawatt project

    Ontario's premier said he would rather respect a city's freeze than override it, a day after Prologis and Montcrest appealed Mississauga's ban to the Ontario Land Tribunal. The stance strands a 40-megawatt project in a year-long tribunal queue and lands on Prologis shareholders, who own a 5.8-gigawatt data center pipeline.

    Data Center

    Fastly jumps 12.6% on a Comcast deal built for GTA VI's 212 GB launch-day download

    Shares closed up 12.6 percent at $17.90 on a launch-day partnership that names no price. The quarter underneath leans on download traffic Fastly itself calls one-off, and February's report separates the game from the business.

    Data Center

    Arista Networks launches edge routers using up to 60% less power as supplier commitments hit $11.4 billion

    At SC26, Arista pushed its routers out of the data center toward users, promising up to 60% lower power than rival edge platforms by building on 5-nanometer Broadcom silicon. The bet lands on a balance sheet carrying $11.4 billion of supplier commitments and a gross margin already sliding, so the edge must arrive before the parts bill does.

    Data Center

    Lenovo posts record $30.2 billion revenue and a $640 million loss on Alat warrants

    The record quarter is real, and so is the loss: a $1.9 billion non-cash mark on the warrants Lenovo sold with its $2 billion Saudi convertible bond deal. Shareholders now price one number the release does not settle, whether a record 9.6% server margin survives the cycle.

    Data Center

    Akamai says it is turning away 2027 cloud business for lack of power

    Akamai's cloud unit is turning away 2027 customers because it cannot power the machines, while the line renting compute to Anthropic runs at $109 million a quarter against a 2027 guide of up to $1.3 billion. Anthropic, the anchor tenant on the backlog, begins trading on Nasdaq today.

    Subscribe to TheInference for free