Doosan gets paid to build the reactor NuScale still has to sell

The only NRC-approved small modular reactor just moved a step closer to hardware, but the money in this deal flows to the Korean factory, not to the American designer still waiting for a single binding customer.

Richard TangRichard Tangthree-minute read
Share
Artist's rendering of a NuScale Power small modular reactor plant
1 / 6Slide 1 of 6
An artist's rendering of the NuScale small modular reactor plant, whose upper reactor pressure vessel module Doosan Enerbility signed on October 29 to fabricate.

Doosan Enerbility signed a contract on October 29 to build the core reactor vessel module for NuScale Power's−8.80% — NuScale Power, down 8.80 percent today small modular reactor 1, and that is the one link in this chain that already works. The factory is ready, the design is approved, and the manufacturer gets paid. The missing link is a customer: NuScale has no binding power purchase agreement, the contract under which a buyer commits to purchase the plant's electricity, and its shareholders pay to keep the pipeline warm.

The factory link just moved

Doosan, the Korean heavy-equipment maker, will fabricate the upper reactor pressure vessel, the component capping the vessel that holds high-temperature, high-pressure coolant, at its Changwon plant. The deal expands a partnership dating to 2019 and a 2023 materials contract into full-scale commercial manufacturing 1. NuScale chief executive John Hopkins called it an approved design becoming "a module ready for actual delivery" 1; COO Carl Fisher and Doosan president Kim Jong-du signed at the ceremony 1.

Full-scale mockup of the upper section of the NuScale Power Module, the component Doosan Enerbility will fabricate
A full-scale mockup of the upper section of the NuScale Power Module, the component Doosan Enerbility signed on October 29 to fabricate at its Changwon plant.Oregon State University, photo courtesy of NuScale Power

NuScale remains the only small modular reactor developer with design approval from the US Nuclear Regulatory Commission 3.

The demand link is empty, and the revenue shows it

Every disclosed arrangement on the customer side is non-binding: up to 6 gigawatts with the Tennessee Valley Authority, carried with no financial guarantee, and the RoPower venture in Romania, not yet at a binding stage 3.

The revenue line confirms the gap. Second-quarter revenue was $75,000 4, down from $8.1 million a year earlier, most of which came from a single related-party project 5, against a quarterly net loss that widened from $37.6 million to $50.1 million 4.

NuScale's revenue is collapsing toward zero

0$M5$M10$M15$MQ1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '260.08$M
Data
Revenue ($M)
Q1 '2513.38$M
Q2 '258.05$M
Q3 '258.24$M
Q4 '251.81$M
Q1 '260.56$M
Q2 '260.08$M
Quarterly revenue in millions of dollars, from NuScale Power's SEC filings. Second-quarter 2026 revenue was $75,000, against a $50.1 million net loss.6

The structure behind the pipeline matters more than its size. The TVA agreement was signed by ENTRA1 Energy, NuScale's exclusive commercialization partner; NuScale was not a party 5.

The pipeline runs through ENTRA1, and NuScale pays for it

Under a milestones agreement, NuScale has already recorded a $507.4 million expense for the first payment to ENTRA1, and a binding power purchase agreement triggers a second payment worth 35% of the total, near $1.2 billion if the 72-module scope holds 5. ENTRA1 also holds sole discretion over whether to buy from NuScale at all, at a capped module price 5. A securities class action alleges NuScale misled investors about ENTRA1's operational capabilities; the company denies wrongdoing 3.

Who carries the risk

Doosan collects fabrication revenue whether or not a plant is ever financed; NuScale's shareholders need a signed buyer, and the stock trades below $6 34. The value in this chain sits at the binding contract, not the factory. The event to watch is a signed power purchase agreement between TVA and ENTRA1, and note what it costs: it would hand ENTRA1 a payment near $1.2 billion, with module revenue arriving years later at a price ceiling set before any order exists 5.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading SMR

Reader comments

0 comments

    Power

    Bloom Energy's newest billion-dollar NTT DATA and Google power deals ship nothing until 2027

    The stock trades at 39.2x forward earnings, above GE Vernova and Enphase, yet the NTT DATA 900 MW order and the AEP plant for Google ship nothing until 2027 and 2028 while Q3 cash flow ran negative. The de-rating is a bet on when signed megawatts become invoiced ones.

    Power

    Pinnacle West files 25-year deal making TSMC fund its own power ahead of a December rate decision

    The 25-year contract is the template for every data-center deal that follows it, and it lands before two Arizona regulators elected three days earlier on bill anger. Pinnacle West's growth story now rides on convincing them.

    Power

    Energy Department paid BWXT $68 million for uranium work as its first US new-build order slips to 2027

    The payment has sat unremarked in federal data for eleven days, and the one tracker that noticed coded the award to L3Harris. It is the funded half of BWXT's growth paying out in cash, while the commercial half, the AI-power half, waits on an order that slipped to 2027.

    Power

    CPUC proposal would cut PG&E's 5,000-mile undergrounding plan to about 1,100 miles

    A judge has moved $1.7 billion of wildfire costs onto California ratepayers, and on November 19 the commission votes on a cost test PG&E says would strike 3,900 miles from the capital it earns on. The utility has already cut $2 billion from its own 2027 plan.

    Power

    AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize

    AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.

    Power

    Southern Company prices $1.75B of equity units at 8.625%, forcing stock buys by 2029

    The units pay 8.625% a year and force buyers to take Southern stock by December 2029, funding a data-center build that Georgia's newly Democratic regulators were elected to police.

    Subscribe to TheInference for free