Power

National Grid quoted £1.1 billion for Sea Link to planners while asking its regulator for £2.567 billion

Two days before the Energy Secretary rules on National Grid's £3 billion Kent-to-Suffolk cable, the regulator's own chair says the builder is gaming the system. Roughly £70 billion of grid buildout earns only what Ofgem allows, and the allowance rests on credible cost figures.

Richard TangRichard Tangthree-minute read
Share
Zoë Yujnovich, chief executive of National Grid, in a corporate portrait outdoors
1 / 6Slide 1 of 6
Zoë Yujnovich, National Grid's chief executive, whose company quoted planners £1.1 billion for Sea Link while asking Ofgem for £2.567 billion on like-for-like terms.

Two days before the government rules on Sea Link, National Grid−3.22% — National Grid, down 3.22 percent today has a trust problem, and for anyone holding NG.L, National Grid's London-listed shares, it is the money question behind the entire AI-era grid buildout. During the planning examination for the proposed 138km electricity cable between Kent and Suffolk, National Grid Electricity Transmission kept quoting a cost of about £1.1 billion 1. Documents published by Ofgem, the energy regulator for Great Britain, show the same company asked the regulator for £3.197 billion in January 2026, while the examination was still running 1. On like-for-like figures in 2018/19 prices, that is £1.1 billion against £2.567 billion, more than double. 1

What National Grid says, and what it does not explain away

National Grid says the lower figure was an early, high-level assessment, not an estimate based on the project's detailed design, and puts the current estimate near £3 billion 1. It notes Ofgem's minded-to position, the regulator's provisional view ahead of a final funding decision, supports funding for the main delivery contracts. 1

That may be true. What is harder to explain away is the February funding statement to planning inspectors, still describing £1.1 billion as the estimated cost, submitted a month after the £3.197 billion request. 1 Campaign group Suffolk Energy Action Solutions wants the October 30 decision paused for an independent cost review; it cites an alternative it estimates at under £300 million. 1

The same project, two cost stories: £1.1 billion quoted, £2.567 billion like-for-like, £3.197 billion requested

  • Estimate
£0bn£1bn£2bn£3bn£4bnQuoted to planning inspectors£1.1bnLike-for-like, 2018/19 prices£2.57bnRequested from Ofgem£3.2bnCurrent estimate (National Grid)£3bn
Data
Value
Quoted to planning inspectors£1.1bn
Like-for-like, 2018/19 prices£2.57bn
Requested from Ofgem£3.2bn
Current estimate (National Grid) (estimate)£3bn
Sea Link cost figures in £ billions. The first three are from Energy Live News reporting of Ofgem-published documents; the fourth is National Grid's current estimate, marked as the company's own figure. Like-for-like comparison is on a 2018/19 price basis.1

The sharpest charge comes from the regulator itself

Ofgem's own chair, Mark McAllister, is quoted in a book published this month: "National Grid is gaming the system." 1 The National Audit Office separately warned in September that major grid upgrades proceed without full business cases, and that constraint costs, the price of a network that cannot carry all the power generated, land on consumers. 1

The £70 billion buildout earns nothing without an Ofgem allowance

Here is the chain that matters: AI demand needs data centers, data centers need grid connections, grid connections need projects like Sea Link, and those projects only get built at scale if the regulated funding settlement holds.

Roughly £70 billion of new pylons and cables by 2031 earns nothing unless Ofgem allows the costs, and scrutiny this public makes tougher allowances likelier. 1 I am firmly pro-AI and this buildout has to happen. But grid money flows through regulated monopolies, and a builder that cannot keep its cost story straight between its regulator and its planning inspectors invites the scrutiny that slows everyone down.

The market has not re-priced this yet

The stock slipped to about GBX1,220 on October 28, a fraction of a percent, and Traders Union's analyst calls the cost discrepancy a material concern "until National Grid restores trust on project costing." 2

We reported on October 22 that National Grid's half-year results land on November 5, after the Microsoft/Nscale UK AI campus pullout sharpened questions about its delivery record 3. What to watch now: the funding allowance Ofgem grants, the Energy Secretary's Sea Link ruling on October 30 1, and whether those two events, not the day's price move, change what investors will pay for regulated growth.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NGG

Reader comments

0 comments

    Power

    First Solar's CEO put $150 million into India, toward $1 billion, as capex fell for eight straight quarters

    Investors bid up First Solar on a friendlier Washington the same week its chief executive put another $150 million into India and said policy certainty is "absolutely critical". The capital is speaking louder than the stock.

    Power

    Vistra guided 2027 EBITDA to $7.7 to $8.5 billion with 98% of output hedged before the Texas vote

    Vistra's first 2027 outlook landed with about 98% of next year's output already hedged before the Texas election, and the market that had marked the stock down 16% on the governor's race paid up for a year a January inauguration cannot touch. The open fight starts in 2028, where the hedges run out.

    Power

    Kinder Morgan's Southeast Connector just got bigger: 20 shippers, 48-inch pipe, 3.7 Bcf/d in sight

    Two weeks after a $3.1 billion FID sized the pipe at 2.6 Bcf/d, Kinder's bulletin board shows another 1.1 Bcf/d of shipper awards and 20 takers. The land fight along the 150-mile Tennessee route has not started yet; the commercial demand already beat the plan.

    Power

    Walmart invested in Base Power, which claims 100 megawatts a month on a $13 billion valuation

    Base Power announced backup batteries for nearly 6,500 North Texas homes, a Walmart investment, and a 100 MW-a-month install pace, all on a $13 billion valuation. Homeowners fund the fleet; Base pools it and sells it back to the grid.

    Power

    Oklo raised $2.25 billion selling stock at $70.19; the market values everything it builds at $700 million

    The Q3 filing holds Oklo's build guidance and posts record construction spending; at a $3.8 billion market value against $3.13 billion banked, the market carries everything the company does beyond holding cash at roughly $700 million.

    Power

    MARA moved 1,650 bitcoin worth $132.8 million as its $1.5 billion gas plant deal finds no AI tenant

    The bitcoin miner moved 1,650 coins to institutional venues the same day FERC cleared its $1.5 billion gas plant deal, and the stock sank 14% anyway. Its AI pivot runs on bitcoin-backed debt, and the promised AI lease still has no tenant.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.