FERC rejects PJM's data-center shortcut, and capacity prices pinned at $325 a megawatt-day carry the bill

FERC killed most of PJM's plan to let data centers connect without paying for new generation. What is left is prepaying for the grid at the state level or paying through a capacity auction pinned at its cap, and either way the money lands with the owners of existing power plants.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
Aerial view of rooftop chillers, cooling towers and backup generators covering a large data-center campus under construction
1 / 6Slide 1 of 6
Backup generators and cooling plant cover the roofs of a data-center campus under construction. PJM expects data-center demand on its system to triple by 2030, to about 29 GW, and FERC has just decided who pays to connect it.

On October 9 the Federal Energy Regulatory Commission rejected the core of PJM Interconnection's plan for connecting data centers and other large loads to the largest U.S. power grid, a network spanning 13 Mid-Atlantic and Midwest states plus Washington, D.C. 12 The rejection decides who pays for AI's grid access: the cheapest route in is closed, and the bill lands on state-approved prepayments and on PJM capacity prices, which investment bank Jefferies+1.04% — Jefferies, up 1.04 percent today expects to stay higher for longer 3.

The plan, called Interim Resource Adequacy Service, would have let big new loads connect without matching new generation if they accepted being switched off ahead of grid emergencies, through interim service and "bring your own new capacity" rules 1. FERC kept only a definition of large loads and a registry listing who they are 1. PJM expects data-center demand on its system to triple by 2030, to about 29 GW 3.

The regulator called it a state matter

The tariff appears "to place obligations directly on eligible new large loads," mostly retail customers, and its compensation framework "appears to establish a retail rate," FERC said 1. States should decide which customers are cut first when the system is stressed, and PJM must justify switching data centers off before other large users 3.

Commissioner David Rosner warned the plan could make the capacity market signal a surplus while the region sheds thousands of megawatts on an involuntary basis 1. FERC rejected not the data centers but the terms that would have let them connect ahead of other users without paying for new supply 1.

Two doors remain: prepay, or the cap

One door is bilateral. On October 7, Duke Energy's two North Carolina utilities settled with the state's consumer advocate, joined by Amazon+4.20% — Amazon, up 4.20 percent today, Google, Meta+3.06% — Meta, up 3.06 percent today, Microsoft+1.03% — Microsoft, up 1.03 percent today and the U.S. Department of Defense: loads of 50 MW and up pay nonrefundable, upfront costs for facilities serving only them, and a state commission ruling is expected by mid-November 4.

The other door is the auction, where generators are paid per megawatt-day to promise power when the grid is stressed, and it is already rationed by cap. PJM's 2028/29 capacity auction cleared at $325 per megawatt-day, the third straight at the ceiling; uncapped bidding would have settled above $500 5.

6.8 gigawatts short, through a backstop FERC half-rejected

PJM still needs 6.8 GW for that year through a backstop purchase, an emergency buy outside the auction 2. FERC partly rejected it on September 29; its offer cap stands at $555, and PJM aims to refile by October 29 26.

PJM's capped auction hides a market willing to pay $500 and up

  • Estimate
$0/MW-day$200/MW-day$400/MW-day$600/MW-dayAuction cap, last three auctions$325/MW-dayUncapped clearing level$500/MW-dayWhat demand would pay with no capBackstop auction offer cap$555/MW-day
Data
Value
Auction cap, last three auctions$325/MW-day
Uncapped clearing level (estimate)$500/MW-day
Backstop auction offer cap$555/MW-day
PJM capacity price signals, dollars per megawatt-day. The Base Residual Auction price cap, where the last three auctions cleared; the level uncapped bidding would have exceeded (estimated); and the offer cap for the backstop procurement FERC partly rejected on September 29. Sources: 24/7 Wall St. via AOL; Utility Dive.2,5

Existing generators collect either way

The ruling could mean capacity prices higher for longer in PJM, favorable to the independent power producers Constellation Energy, NRG Energy+1.84% — NRG Energy, up 1.84 percent today, Talen Energy and Vistra+0.81% — Vistra, up 0.81 percent today, Jefferies analysts told clients 3. Vistra chief executive Jim Burke says large-load customers are "interested in contracting at a premium with existing because it's still a discount to what new build costs" 5.

NRG is the sharpest expression: a fleet roughly doubled to 25 GW with 13 GW bought from LS Power, more than 6 GW of gas-build potential for data centers, and a 1.2-GW Texas plant under a 15-year hyperscaler contract 78. Analyst price targets run from $157 at Morgan Stanley+2.36% — Morgan Stanley, up 2.36 percent today to $197 at Goldman Sachs+1.49% — Goldman Sachs, up 1.49 percent today, averaging $202.1, with 11 of 17 analysts at Buy 8.

The curtailable lane likely returns, led by states

The caveat comes from Jefferies itself: the curtailable lane likely returns, "minimally revived," and led by states, with Ohio and Pennsylvania first 1. Watch North Carolina's ruling by mid-November 4, PJM's refiled curtailment plan 3, and the 2029/30 auction in early December 2.

Sources

  1. 1Utility Dive, "FERC rejects most of PJM's large load interconnection plan," October 12, 2026
  2. 2Utility Dive, "FERC chair slams PJM 'mess' as country's largest grid operator delays power auction," September 30, 2026
  3. 3Seeking Alpha via TradingView, "FERC rejects most of PJM's temporary curtailment plan to manage data centers," October 12, 2026
  4. 4Daily Energy Insider, "Duke Energy utilities reach large-load payment settlement with North Carolina staff," October 9, 2026
  5. 524/7 Wall St. via AOL, "The AI Boom Has a Power Problem. These 3 Utilities Are Getting Paid to Solve It," September 17, 2026
  6. 6Utility Dive, "DOE presses PJM on ratepayer protections from large load costs," October 8, 2026
  7. 7POWER Magazine, "The POWER Interview: NRG's Case for Bring Your Own Power and the Labor to Build It," August 5, 2026
  8. 8Stocktwits, "NRG Energy Stock Heads For Best Week In A Month: CEO Flags Early Stages Of 'Demand Supercycle'," March 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading JEF

Reader comments

0 comments

    Power

    Baker Hughes counts 607 US rigs, the most since April 2024, as banks cut price targets on rates, not demand

    The oilfield engine behind the stock is running at 2024 levels just as the sell side cuts price targets on the cost of capital rather than demand. The rigs are what service the $18.3 billion of debt raised to buy Chart Industries.

    Power

    PECO, Exelon's Pennsylvania unit, raises bills about $9 a month Dec. 1; a sixth traces to data centers

    The typical Pennsylvania household pays about $9 more a month from Tuesday, and roughly a sixth of that increase traces to capacity prices bid up by data-center demand. Exelon has asked FERC to scrap the auction system behind them, but its own complaint leaves this December's auction untouched.

    Power

    Taiwan's binding nuclear referendum passed with 62% of votes, and TSMC's Taiwan risk waits for 2028

    Taiwan's nine-in-one elections ended in a split: the KMT held Greater Taipei, the DPP took Taichung and the nuclear referendum passed as binding. For AI and chip investors the status quo holds, and the real decision waits for the early-2028 presidential vote.

    Power

    Taiwan votes 7 million to 4 million to end its nuclear-free policy as TSMC pledges $265 billion in the US

    The yes count cleared the turnout rule on Saturday night, but the first restarted reactor is years away, and TSMC's answer to Taiwan's power ceiling is already rising in Arizona and sitting in a Texas filing.

    Power

    Generac's $4.5 billion data center backlog earns about half the margin of its home business

    The data center order book tripled to $4.5 billion and the sell side says $295 a share; the fine print in the same outlook says each AI dollar converts at about half the profit of the home business. February's report settles which one the stock has been priced on.

    Power

    Virginia's commission rules by Jan. 11 on NextEra's $67 billion Dominion deal with the Robo Memo sealed