Power

FirstEnergy nearly doubles contracted AI load in nine months to 7.9 GW, and Ohio votes on who pays

FirstEnergy's contracted data-center load nearly doubled in nine months to 7.9 gigawatts, and management put numbers on the shareholders' share of the $36 billion buildout. Regulators in three states, starting with Tuesday's Ohio vote, decide whether the structure pays.

Vincent JiangVincent Jiangthree-minute read
Share
A high-voltage transmission tower at dusk on a FirstEnergy line in Pennsylvania
1 / 6Slide 1 of 6
A FirstEnergy transmission line at dusk in Pennsylvania. The company plans $19 billion of transmission work inside a $36 billion five-year capital program, sized in part to serve contracted data-center demand.

FirstEnergy+1.17% — FirstEnergy, up 1.17 percent today, the Akron-based utility serving about 6 million customers in six states, is building a $36 billion grid on the back of artificial intelligence demand, and the open question is who funds it 13. On the October 28 earnings call, chief executive Brian Tierney reported contracts to supply data centers through 2036 reached 7.9 gigawatts at the end of the third quarter, up 23% from 6.4 gigawatts at the end of June and 90% above the end-2025 level, with another 4 gigawatts in active negotiation and a 26-gigawatt total pipeline 123.

Contracted load rose 23% in a quarter; the 26 GW pipeline looms behind it

0102030Contracted, Q2 20266.4Contracted, Q3 20267.9Total pipeline, Q3 2026 (contracted + prospective)26
Data
Value
Contracted, Q2 20266.4
Contracted, Q3 20267.9
Total pipeline, Q3 2026 (contracted + prospective)26
Contracted data-center demand under contract through 2036, and the total pipeline including prospective load, in gigawatts, as reported for Q2 and Q3 2026. Sources: Utility Dive, Akron Beacon Journal, GuruFocus earnings-call highlights.1,2,3

Every contracted gigawatt adds a quarter-billion to the grid

The buildout carries a price tag. Each contracted gigawatt requires roughly $250 million of transmission upgrades, so FirstEnergy expects its $19 billion transmission plan to grow by at least 25%, or $4.75 billion, inside that $36 billion five-year capital program 13. Someone funds that.

Management's answer: the data centers pay. In West Virginia, where Monongahela Power and Potomac Edison want to build the $2.7 billion Maidsville gas plant, offtakers have signaled openness to fund much of it through a surcharge 13. For shareholders, the cost is quantified: up to $2 billion of new equity through 2030 and up to 35% equity funding on incremental projects 3.

The money case is priced, and regulators hold the gates

For investors, the demand fact is now priced against a payout that depends on regulators. FirstEnergy reaffirmed 2026 core earnings guidance of $2.62 to $2.82 a share and expects growth near the top of its 6% to 8% range through 2030 3. Analyst targets sit at $50, against a $46.83 close on October 29, so the stock trades on the buildout converting, not on demand appearing 35.

Three gates decide that. The West Virginia certificate for Maidsville, expected in the fourth quarter, unlocks the plant's contracts 13. Pennsylvania's commission has already rejected FirstEnergy's data-center billing plan 3-2, as reported when this covered the Q2 buildout 5. And February's updated capital plan gives the transmission uplift and equity needs their first full numbers, after New Jersey's affordability review reaches resolution expected later this year or early next 3.

The politics that sets the mood votes Tuesday

Then there is Ohio. On October 29, the Energy and Policy Institute reported that super PACs backing Senator Jon Husted received $2 million this year from two 501(c)(4) groups FirstEnergy secretly funded in 2018, years before the company agreed to pay $275 million in refunds and fines over its bribery schemes 4. A New Jersey review could reshape investment there too, with resolution expected this year or early next 3.

When this covered the Q2 buildout on October 26, banks' $50 targets were betting on 4.3 gigawatts and the politics was the caveat 5. What is new since: the contracted load nearly doubled in nine months, the transmission uplift got its first number, the shareholders' equity share was quantified, and the dark-money report landed four days before Ohio votes 134. The decision rule: 7.9 gigawatts is a demand fact, but the earnings are a regulatory variable, set in three states starting with Tuesday's ballot 134.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading FE

Reader comments

0 comments

    Power

    Bloom Energy's newest billion-dollar NTT DATA and Google power deals ship nothing until 2027

    The stock trades at 39.2x forward earnings, above GE Vernova and Enphase, yet the NTT DATA 900 MW order and the AEP plant for Google ship nothing until 2027 and 2028 while Q3 cash flow ran negative. The de-rating is a bet on when signed megawatts become invoiced ones.

    Power

    Pinnacle West files 25-year deal making TSMC fund its own power ahead of a December rate decision

    The 25-year contract is the template for every data-center deal that follows it, and it lands before two Arizona regulators elected three days earlier on bill anger. Pinnacle West's growth story now rides on convincing them.

    Power

    Energy Department paid BWXT $68 million for uranium work as its first US new-build order slips to 2027

    The payment has sat unremarked in federal data for eleven days, and the one tracker that noticed coded the award to L3Harris. It is the funded half of BWXT's growth paying out in cash, while the commercial half, the AI-power half, waits on an order that slipped to 2027.

    Power

    CPUC proposal would cut PG&E's 5,000-mile undergrounding plan to about 1,100 miles

    A judge has moved $1.7 billion of wildfire costs onto California ratepayers, and on November 19 the commission votes on a cost test PG&E says would strike 3,900 miles from the capital it earns on. The utility has already cut $2 billion from its own 2027 plan.

    Power

    AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize

    AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.

    Power

    Southern Company prices $1.75B of equity units at 8.625%, forcing stock buys by 2029

    The units pay 8.625% a year and force buyers to take Southern stock by December 2029, funding a data-center build that Georgia's newly Democratic regulators were elected to police.

    Subscribe to TheInference for free