Power

FirstEnergy nearly doubles contracted AI load in nine months to 7.9 GW, and Ohio votes on who pays

FirstEnergy's contracted data-center load nearly doubled in nine months to 7.9 gigawatts, and management put numbers on the shareholders' share of the $36 billion buildout. Regulators in three states, starting with Tuesday's Ohio vote, decide whether the structure pays.

Vincent JiangVincent Jiang · 3 min read
Share
A high-voltage transmission tower at dusk on a FirstEnergy line in Pennsylvania
1 / 6Slide 1 of 6
A FirstEnergy transmission line at dusk in Pennsylvania. The company plans $19 billion of transmission work inside a $36 billion five-year capital program, sized in part to serve contracted data-center demand.

FirstEnergy+0.70% — FirstEnergy, up 0.70 percent today, the Akron-based utility serving about 6 million customers in six states, is building a $36 billion grid on the back of artificial intelligence demand, and the open question is who funds it 13. On the October 28 earnings call, chief executive Brian Tierney reported contracts to supply data centers through 2036 reached 7.9 gigawatts at the end of the third quarter, up 23% from 6.4 gigawatts at the end of June and 90% above the end-2025 level, with another 4 gigawatts in active negotiation and a 26-gigawatt total pipeline 123.

Contracted load rose 23% in a quarter; the 26 GW pipeline looms behind it

0102030Contracted, Q2 20266.4Contracted, Q3 20267.9Total pipeline, Q3 2026 (contracted + prospective)26
Data
Value
Contracted, Q2 20266.4
Contracted, Q3 20267.9
Total pipeline, Q3 2026 (contracted + prospective)26
Contracted data-center demand under contract through 2036, and the total pipeline including prospective load, in gigawatts, as reported for Q2 and Q3 2026. Sources: Utility Dive, Akron Beacon Journal, GuruFocus earnings-call highlights.1,2,3

Every contracted gigawatt adds a quarter-billion to the grid

The buildout carries a price tag. Each contracted gigawatt requires roughly $250 million of transmission upgrades, so FirstEnergy expects its $19 billion transmission plan to grow by at least 25%, or $4.75 billion, inside that $36 billion five-year capital program 13. Someone funds that.

Management's answer: the data centers pay. In West Virginia, where Monongahela Power and Potomac Edison want to build the $2.7 billion Maidsville gas plant, offtakers have signaled openness to fund much of it through a surcharge 13. For shareholders, the cost is quantified: up to $2 billion of new equity through 2030 and up to 35% equity funding on incremental projects 3.

The money case is priced, and regulators hold the gates

For investors, the demand fact is now priced against a payout that depends on regulators. FirstEnergy reaffirmed 2026 core earnings guidance of $2.62 to $2.82 a share and expects growth near the top of its 6% to 8% range through 2030 3. Analyst targets sit at $50, against a $46.83 close on October 29, so the stock trades on the buildout converting, not on demand appearing 35.

Three gates decide that. The West Virginia certificate for Maidsville, expected in the fourth quarter, unlocks the plant's contracts 13. Pennsylvania's commission has already rejected FirstEnergy's data-center billing plan 3-2, as reported when this covered the Q2 buildout 5. And February's updated capital plan gives the transmission uplift and equity needs their first full numbers, after New Jersey's affordability review reaches resolution expected later this year or early next 3.

The politics that sets the mood votes Tuesday

Then there is Ohio. On October 29, the Energy and Policy Institute reported that super PACs backing Senator Jon Husted received $2 million this year from two 501(c)(4) groups FirstEnergy secretly funded in 2018, years before the company agreed to pay $275 million in refunds and fines over its bribery schemes 4. A New Jersey review could reshape investment there too, with resolution expected this year or early next 3.

When this covered the Q2 buildout on October 26, banks' $50 targets were betting on 4.3 gigawatts and the politics was the caveat 5. What is new since: the contracted load nearly doubled in nine months, the transmission uplift got its first number, the shareholders' equity share was quantified, and the dark-money report landed four days before Ohio votes 134. The decision rule: 7.9 gigawatts is a demand fact, but the earnings are a regulatory variable, set in three states starting with Tuesday's ballot 134.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading FE

Reader comments

0 comments

    Power

    X-energy trades near $11 as AEP says its 12-reactor Indiana project has no final decision before 2030

    On its October 28 earnings call, AEP chairman Bill Fehrman said the Amazon-backed twelve-reactor Indiana project needs only minimal AEP money now and cannot reach a final investment decision before 2030. X-energy trades near $11 against analyst targets that run from $8 to $57.

    Power

    First Solar Cut Its Customers and Kept the Tax Credit

    Third-quarter sales dropped 23% while net income rose 25%, and the 2026 gross-profit guidance never moved because about 85% of it is one federal tax credit. The tariff regime meant to bring buyers back starts on December 4.

    Power

    NuScale jumped 7% on its first reactor hardware, while a shareholder suit called its plan a farce

    The Doosan contract turns NuScale's approved reactor design into its first piece of production steel, and the stock jumped 7%. A securities suit filed the same week calls the commercialization plan behind it a farce, and the November 5 earnings call decides whether this is a manufacturing story or a payment-flow story.

    Power

    A tariff Duke is writing in South Carolina decides who pays for AI's power plants

    Duke Energy told South Carolina regulators it will seek the large-load tariff it settled in North Carolina, while two methane plants totaling 2,720 megawatts move through permitting behind it. The rule inside that tariff, more than the turbines, decides whether the AI buildout is billed to the companies that cause it or to millions of households.

    Power

    Dominion's AI build puts the power bill on data centers, and the carbon bill on everyone else

    Dominion's third-quarter filing this morning sits under three Virginia dockets and Tuesday's election. The 14-year contracts that put the power bill on data centers leave the carbon bill on everyone else, and February's rider ruling will decide whether the AI build keeps its political license.

    Power

    AEP signs Google and SoftBank to pay for its grid, but only 35 of 84 gigawatts have firm contracts

    The utility's 84-gigawatt AI pipeline is no longer just a load forecast: SoftBank and Google are signing to pay for AEP's lines and plants at a set return, while shareholders still fund the rest. The gap between 84 GW contracted and 35 GW firm is where the next share sale lives.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.