Power

A tariff Duke is writing in South Carolina decides who pays for AI's power plants

Duke Energy told South Carolina regulators it will seek the large-load tariff it settled in North Carolina, while two methane plants totaling 2,720 megawatts move through permitting behind it. The rule inside that tariff, more than the turbines, decides whether the AI buildout is billed to the companies that cause it or to millions of households.

Richard TangRichard Tang · 3 min read
Share
North Carolina Governor Josh Stein speaking at a campaign rally in Durham, North Carolina, in April 2026
1 / 6Slide 1 of 6
Josh Stein, North Carolina's governor, has pushed for data centers to pay for power plants, not just grid wires. Photo from a rally in Durham, April 2026.

Duke Energy+1.53% — Duke Energy, up 1.53 percent today told South Carolina regulators this week it will seek a large-load tariff: a standard published rate for very large customers, set by regulators, that any data center can take rather than a contract negotiated one customer at a time.

It is a reversal after years of individual contracts, with "broad agreement" on key principles even as details remain in dispute, while Dominion Energy+2.46% — Dominion Energy, up 2.46 percent today, which also serves the state, plans to keep signing bespoke deals 1. One utility is now writing the rule that decides who pays for the AI buildout, across two states at once.

The tariff covers wires, and nobody has settled the plants

A data center is a customer no rate class was built for: it arrives huge, and it can leave. The North Carolina settlement, signed by Amazon−2.01% — Amazon, down 2.01 percent today, Google, Meta−0.53% — Meta, down 0.53 percent today and Microsoft−1.62% — Microsoft, down 1.62 percent today, makes large loads pay upfront for their own substations and post security for shared transmission; we reported the terms on October 15 2.

Governor Josh Stein describes the rest of the deal: contracts on a public template, minimum-purchase guarantees, and a duty to cut use when the grid is strained, which lasts only the first five years 3. The Federal Energy Regulatory Commission approved the federal transmission layer on October 9, one commissioner calling the protections "meaningful, if imperfect" 4.

Stein and Jackson want data centers to pay for the plants

Generation is the open link. Stein and Attorney General Jeff Jackson want the loads that force new plants onto the system to pay for them, pointing to what other states extracted from the same companies 3. "North Carolina should be receiving these same kinds of commitments, but right now we're getting none of them," Stein said 3. Jackson's objection is narrower: the settlement has large users covering transmission lines, but who pays for power plants is left unclear 3.

Other states won clean-energy megawatts from data-center developers; North Carolina won none

0 MW500 MW1,000 MW1,500 MW2,000 MWGoogle, Minnesota2,000 MWMeta, Ohio1,200 MWAmazon, Indiana960 MWNorth Carolina's haul0 MWStein: 'right now we're getting none'
Data
Value
Google, Minnesota2,000 MW
Meta, Ohio1,200 MW
Amazon, Indiana960 MW
North Carolina's haul0 MW
Megawatts each state won from data-center developers, as cited by Governor Josh Stein on October 28, 2026. Source: WRAL.3

The gas is already in permitting

The bill being written is concrete: Duke filed its pre-construction notice this month, an initial regulatory step, for two methane plants of 1,360 megawatts each on the Yadkin River in Davie County, North Carolina, with gas storage across the river in Davidson County 5 6. The Southern Environmental Law Center has appealed Davie County's view that the plants are permitted "by right" in a residential-agricultural zone with no public hearing; the hearing is due by November 23 5. Davidson County's commissioners vote on their rezoning on November 9 6.

If the tariff stops at the wires, households are the backstop

If the tariff stops at wires, the cost of those plants lands on Duke's 8.7 million customers through their rates 7, including the North Carolina households whose rate case we reported on October 23. Duke's construction spending already runs well ahead of the cash its operations generate 8. In Lexington, the Davidson County seat, residents wore "No Gas Plants, No Data Centers" shirts to the planning hearing; Duke says demand is driven mostly by manufacturing and migration, not data centers 6.

Duke's construction spending now outruns the cash its operations generate

  • Capex
  • Operating cash flow
$1B$2B$3B$4B$5BQ4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '26$4.15Bspending steps up as cash flowflattens
Data
CapexOperating cash flow
Q3 '23$3.05B$3.52B
Q4 '23$3.29B$2.57B
Q1 '24$3.21B$2.47B
Q2 '24$3B$2.95B
Q3 '24$2.99B$3.52B
Q4 '24$3.09B$3.38B
Q1 '25$3.15B$2.18B
Q2 '25$3.28B$2.86B
Q3 '25$3.45B$3.63B
Q4 '25$4.14B$3.66B
Q1 '26$4.09B$1.51B
Q2 '26$4.15B$2.76B
Quarterly capital expenditure and operating cash flow, US$ billions, from Duke Energy's SEC filings.8

The dates that decide it land within weeks

Duke reports third-quarter results on November 5 9, two days after midterms in which voters decide 34 data-center ballot measures across 30 counties 10. North Carolina's Utilities Commission is expected to rule on the settlement by mid-November 2; the plants' full certificate application follows early next year, after the state's resource-plan order due by year-end 5. The settlement covers the wires; extending it to generation is the fight now before the commission.

The South Carolina filing will show which principles Duke treats as settled; the mid-November order will show whether the tariff reaches power plants; the November 23 hearing will show whether the 2,720 megawatts stay on schedule. The buildout should proceed, priced to the customer who causes the cost: that is the counterweight that keeps AI off the backs of households least able to pay.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading DUK

Reader comments

0 comments

    Power

    WEC Energy's $47.5 billion grid plan bets on AI data centers, and Wisconsin's regulator holds the key

    A record $47.5 billion five-year plan, nearly half for data centers, puts Wisconsin's ratepayer protection regime and its regulators in the path of the AI buildout.

    Power

    Missouri votes Tuesday on half of Ameren's power buildout

    MISO just awarded an Ameren and NextEra consortium a $1.23 billion Iowa transmission line that no Missouri regulator votes on. The generation half of Ameren's buildout still runs through Jefferson City, where utilities are giving to campaigns five to one ahead of the November 3 midterms.

    Power

    X-energy trades near $11 as AEP says its 12-reactor Indiana project has no final decision before 2030

    On its October 28 earnings call, AEP chairman Bill Fehrman said the Amazon-backed twelve-reactor Indiana project needs only minimal AEP money now and cannot reach a final investment decision before 2030. X-energy trades near $11 against analyst targets that run from $8 to $57.

    Power

    First Solar Cut Its Customers and Kept the Tax Credit

    Third-quarter sales dropped 23% while net income rose 25%, and the 2026 gross-profit guidance never moved because about 85% of it is one federal tax credit. The tariff regime meant to bring buyers back starts on December 4.

    Power

    NuScale jumped 7% on its first reactor hardware, while a shareholder suit called its plan a farce

    The Doosan contract turns NuScale's approved reactor design into its first piece of production steel, and the stock jumped 7%. A securities suit filed the same week calls the commercialization plan behind it a farce, and the November 5 earnings call decides whether this is a manufacturing story or a payment-flow story.

    Power

    FirstEnergy nearly doubles contracted AI load in nine months to 7.9 GW, and Ohio votes on who pays

    FirstEnergy's contracted data-center load nearly doubled in nine months to 7.9 gigawatts, and management put numbers on the shareholders' share of the $36 billion buildout. Regulators in three states, starting with Tuesday's Ohio vote, decide whether the structure pays.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.