Power

A tariff Duke is writing in South Carolina decides who pays for AI's power plants

Duke Energy told South Carolina regulators it will seek the large-load tariff it settled in North Carolina, while two methane plants totaling 2,720 megawatts move through permitting behind it. The rule inside that tariff, more than the turbines, decides whether the AI buildout is billed to the companies that cause it or to millions of households.

Richard TangRichard Tangthree-minute read
Share
North Carolina Governor Josh Stein speaking at a campaign rally in Durham, North Carolina, in April 2026
1 / 6Slide 1 of 6
Josh Stein, North Carolina's governor, has pushed for data centers to pay for power plants, not just grid wires. Photo from a rally in Durham, April 2026.

Duke Energy+0.20% — Duke Energy, up 0.20 percent today told South Carolina regulators this week it will seek a large-load tariff: a standard published rate for very large customers, set by regulators, that any data center can take rather than a contract negotiated one customer at a time.

It is a reversal after years of individual contracts, with "broad agreement" on key principles even as details remain in dispute, while Dominion Energy−0.19% — Dominion Energy, down 0.19 percent today, which also serves the state, plans to keep signing bespoke deals 1. One utility is now writing the rule that decides who pays for the AI buildout, across two states at once.

The tariff covers wires, and nobody has settled the plants

A data center is a customer no rate class was built for: it arrives huge, and it can leave. The North Carolina settlement, signed by Amazon−1.20% — Amazon, down 1.20 percent today, Google, Meta−2.63% — Meta, down 2.63 percent today and Microsoft−2.43% — Microsoft, down 2.43 percent today, makes large loads pay upfront for their own substations and post security for shared transmission; we reported the terms on October 15 2.

Governor Josh Stein describes the rest of the deal: contracts on a public template, minimum-purchase guarantees, and a duty to cut use when the grid is strained, which lasts only the first five years 3. The Federal Energy Regulatory Commission approved the federal transmission layer on October 9, one commissioner calling the protections "meaningful, if imperfect" 4.

Stein and Jackson want data centers to pay for the plants

Generation is the open link. Stein and Attorney General Jeff Jackson want the loads that force new plants onto the system to pay for them, pointing to what other states extracted from the same companies 3. "North Carolina should be receiving these same kinds of commitments, but right now we're getting none of them," Stein said 3. Jackson's objection is narrower: the settlement has large users covering transmission lines, but who pays for power plants is left unclear 3.

Other states won clean-energy megawatts from data-center developers; North Carolina won none

0 MW500 MW1,000 MW1,500 MW2,000 MWGoogle, Minnesota2,000 MWMeta, Ohio1,200 MWAmazon, Indiana960 MWNorth Carolina's haul0 MWStein: 'right now we're getting none'
Data
Value
Google, Minnesota2,000 MW
Meta, Ohio1,200 MW
Amazon, Indiana960 MW
North Carolina's haul0 MW
Megawatts each state won from data-center developers, as cited by Governor Josh Stein on October 28, 2026. Source: WRAL.3

The gas is already in permitting

The bill being written is concrete: Duke filed its pre-construction notice this month, an initial regulatory step, for two methane plants of 1,360 megawatts each on the Yadkin River in Davie County, North Carolina, with gas storage across the river in Davidson County 5 6. The Southern Environmental Law Center has appealed Davie County's view that the plants are permitted "by right" in a residential-agricultural zone with no public hearing; the hearing is due by November 23 5. Davidson County's commissioners vote on their rezoning on November 9 6.

If the tariff stops at the wires, households are the backstop

If the tariff stops at wires, the cost of those plants lands on Duke's 8.7 million customers through their rates 7, including the North Carolina households whose rate case we reported on October 23. Duke's construction spending already runs well ahead of the cash its operations generate 8. In Lexington, the Davidson County seat, residents wore "No Gas Plants, No Data Centers" shirts to the planning hearing; Duke says demand is driven mostly by manufacturing and migration, not data centers 6.

Duke's construction spending now outruns the cash its operations generate

  • Capex
  • Operating cash flow
$1B$2B$3B$4B$5BQ4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '26$4.15Bspending steps up as cash flowflattens
Data
CapexOperating cash flow
Q3 '23$3.05B$3.52B
Q4 '23$3.29B$2.57B
Q1 '24$3.21B$2.47B
Q2 '24$3B$2.95B
Q3 '24$2.99B$3.52B
Q4 '24$3.09B$3.38B
Q1 '25$3.15B$2.18B
Q2 '25$3.28B$2.86B
Q3 '25$3.45B$3.63B
Q4 '25$4.14B$3.66B
Q1 '26$4.09B$1.51B
Q2 '26$4.15B$2.76B
Quarterly capital expenditure and operating cash flow, US$ billions, from Duke Energy's SEC filings.8

The dates that decide it land within weeks

Duke reports third-quarter results on November 5 9, two days after midterms in which voters decide 34 data-center ballot measures across 30 counties 10. North Carolina's Utilities Commission is expected to rule on the settlement by mid-November 2; the plants' full certificate application follows early next year, after the state's resource-plan order due by year-end 5. The settlement covers the wires; extending it to generation is the fight now before the commission.

The South Carolina filing will show which principles Duke treats as settled; the mid-November order will show whether the tariff reaches power plants; the November 23 hearing will show whether the 2,720 megawatts stay on schedule. The buildout should proceed, priced to the customer who causes the cost: that is the counterweight that keeps AI off the backs of households least able to pay.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading DUK

Reader comments

0 comments

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.

    Power

    Southern Company can sell 12 million shares at any moment as its capital plan could reach $100 billion

    Southern Company, Georgia Power's parent, can now sell stock the moment it chooses after filing an automatic shelf on November 10. The capital plan behind the filing could approach $100 billion, its remaining equity is unpriced, and in January a new Democratic majority arrives on Georgia's utility commission with authority over who pays.

    Power

    Duke Energy asks Florida for 300 MW of solar and a $1 billion savings claim, six days after a data-center loss

    The filing claims $1 billion of lifetime customer savings, but that number is avoided fuel cost, not a bill credit, and it lands six days after the same commission unanimously rejected Duke's data-center cost plan. For Duke shareholders, commissions reading this arithmetic decide whether the $103 billion build gets paid.

    Power

    Talen Energy sells 750 MW of capacity for $100 million a year, keeps the power merchant

    The seven-year Guernsey deal locks in the leg of the business Talen can price and leaves the electricity merchant, in a zone its own 10-Q shows trading far below the PJM market. It de-risks the leveraged AI-power trade that TLN holders own.

    Power

    Gov. Spanberger moves to force NextEra's sealed fitness memo into the $67 billion Dominion merger hearing

    The State Corporation Commission's evidentiary hearing starts November 17 with a ruling due by January 11, while traders who bet on deal spreads treat approval as near-certain. A rate freeze, a rate cap or a fitness finding would reprice both stocks.

    Power

    PG&E freezes $2 billion of grid spending as California's wildfire liability law stalls

    California's utility regulator now calls the liability rule underneath PG&E's hardening boom unsustainable, and a November 19 vote could cut its 5,000-mile burial plan to about 1,100 miles. PCG shareholders are forgoing rate-base growth to protect the balance sheet; ratepayers may pay either way.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.