Harris County targets CenterPoint's $66.7 billion capital plan over data center grid surge

Harris County is fighting for authority to slow 8 gigawatts of data center load that underpins CenterPoint's $66.7 billion capital plan, just days ahead of its third-quarter print.

Vincent JiangVincent Jiang · 3 min read
Share
Jason Wells, chief executive of CenterPoint Energy
1 / 6Slide 1 of 6
CenterPoint Energy chief executive Jason Wells, whose $66.7 billion capital plan is the target of Harris County's push for data center siting authority.

On October 15, 2026, Harris County Attorney Abbie Kamin stood on the courthouse steps alongside county commissioners Lesley Briones and Adrian Garcia and did something unusual for a local official: she read a regulated utility’s investor presentation back at it as an indictment 17. The numbers belonged to Houston wires-and-pipes operator CenterPoint Energy−0.32% — CenterPoint Energy, down 0.32 percent today 1.

Management had told Wall Street that 8 gigawatts of data center load would be energized across the Houston area by 2029, swelling system demand roughly 50 percent 17. Kamin's complaint was not that the utility's forecast was inaccurate, but that Harris County had zero legal authority to decide what plugs into its dirt 18.

The rate base stakes

For CenterPoint, that load projection is the economic engine of its corporate equity 19. Because investor-owned utilities earn state-sanctioned returns on approved physical capital rather than commodity power, data center queues directly dictate rate-base growth 1.

On July 28, 2026, CenterPoint raised its 10-year capital expenditure plan for 2026 through 2035 by $1.2 billion to $66.7 billion, marking its second capex hike of the year 19. Management tied the spending directly to Houston's accelerating queue, estimating that absorbing the massive volume would dilute fixed network expenses and trim local residential and commercial delivery charges by at least $5 billion over a decade 19.

CenterPoint has deployed over $10 billion in capital across eight quarters

$0B$1B$2B$3BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '2610-year capex plan raised to$66.7B
Data
Capital Expenditure
Q3 '24$0.84B
Q4 '24$2.01B
Q1 '25$1.04B
Q2 '25$1.13B
Q3 '25$1.22B
Q4 '25$1.48B
Q1 '26$1.2B
Q2 '26$1.37B
Quarterly capital expenditure in billions of dollars. Sources: CenterPoint Energy Form 10-Q SEC filings.11

Wall Street embraced the arithmetic 3456. TD Cowen initiated coverage at Buy on October 22, 2026, with a $47 target and upgraded the stock to Strong-Buy on October 23, 2026 34. HSBC initiated at Buy with a $44 target 5. Scotiabank named CenterPoint a top utility pick on October 22, 2026, noting an internal transmission study could add another $10 billion of capex into guidance while acknowledging political pushback 6.

The jurisdictional clash

Yet the foundation of that $66.7 billion capital plan faces multiple political collisions 1. Texas counties hold no zoning powers, leaving Harris County unable to impose development moratoria or steer substation locations 17.

In response, the Commissioners Court voted on October 15, 2026, to order emergency service and flood control agencies to flag every major permit application, while petitioning Texas lawmakers for siting jurisdiction ahead of the January 2027 legislative session 18. The county also awaits an opinion from Texas Attorney General Ken Paxton on whether local governments possess any statutory authority to pause data center builds 17.

Paxton has separately targeted the sector, opening a statewide investigation on October 15, 2026, into water compliance across 156 data center projects spanning 32 counties, including Harris County 110. Above both sits Governor Greg Abbott's September 21, 2026, directive halting Texas Commission on Environmental Quality data center permits pending an Electric Reliability Council of Texas (ERCOT) audit of 474 gigawatts of large-load requests 18. The compliance deadline for that environmental halt passed on October 19, 2026, and ERCOT must publish its audit by December 10, 2026 1.

The earnings test

CenterPoint management argues the backlog is durable, noting with its second-quarter print that it filed more than 17 gigawatts into ERCOT's Batch Zero study, where it expects 14 gigawatts to qualify against a current system peak of 21 gigawatts 19. When the utility reports third-quarter earnings on October 27, 2026, analysts will look for whether executive leadership formally folds Scotiabank's anticipated $10 billion transmission expansion into the base plan 26.

Our previous reporting on Entergy's transparency dispute highlighted how rapidly utility agreements can collide with regulatory oversight 1. If Austin or county officials restrict interconnections, the promised $5 billion ratepayer relief and the capital spending that justifies CenterPoint's valuation will evaporate together 1. Deep dive into the filings below as regulatory friction reshapes the Texas grid.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading CNP…

Reader comments

0 comments

    Power

    PPL's 31.8 GW pipeline in advanced planning waits on a transmission tariff; plan update November 6

    PPL Electric proposed 16 miles of line for a data center near Mount Carmel and picked its Allenwood route, while Governor Shapiro's PUC petition challenges exactly the layer of the grid those projects occupy. The annual business plan update on November 6 is the first hard number on the buildout, and the stock's premium to every utility peer has to be earned by it.

    Power

    Fluence's AI power bet faces a securities-fraud suit after three guidance breaks and a 73% fall

    A securities-fraud class action alleges Fluence's fiscal 2026 guidance rested on contract factories that were never ready, and the company's own disclosures back the timeline: three guidance breaks in eight months took the stock down about 73%.

    Power

    Amazon bought 690 megawatts from Constellation's Calvert Cliffs; Calvert County's zoning gates the next deal

    Constellation's 20-year contract with Amazon funds a $3 billion upgrade and relicensing at Calvert Cliffs, but the county that hosts Maryland's only nuclear plant says it was never consulted, and it controls the zoning that gates the site's next options. The decision now sits with a November 3 election and a December moratorium vote.

    Power

    GE Vernova's gas customers put 25% down, so its October 28 order line, not Meta's financing, is the test

    The market read Meta's financing strains as a threat to GE Vernova's order book. It missed that customers bank a 25% deposit when they reserve a turbine slot, so October 28's order line, not the deposit, is the only number that matters.

    Power

    Siemens Energy fell 2.9% Friday on CoreWeave's 15% bond yield; its backlog is EUR 162 billion

    A 2.9% Friday drop with no company news behind it, a tripled nuclear training program, a EUR 162 billion backlog, and one November date that forces both camps to argue with numbers.

    Power

    WEC Energy Group seeks to buy $2 billion of Invenergy gas plants no regulator tested for need

    Wisconsin's Public Service Commission cleared 1.5 gigawatts of merchant gas on October 15 through a review its chair said state law confined, and We Energies has applied to buy the pair for more than $2 billion just as analysts cut the stock's targets toward the market price.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.