Hut 8's $27 billion of AI leases cover 949 megawatts; the other 6,910 need about $73 billion to build

The Bitcoin miner's November 4 call put 949 megawatts under AI leases worth about $27 billion, against quarterly revenue of $71.1 million. Most of the 7,859-megawatt pipeline behind them has neither a tenant nor construction underway.

Richard TangRichard Tangthree-minute read
Share
Aerial view of Hut 8's River Bend data center campus under construction, a wide flat roof surrounded by earthworks and a crane
1 / 6Slide 1 of 6
Hut 8's River Bend campus in Louisiana under construction. The first data hall there is due to hand over in the second quarter of 2027.

The miner-to-AI conversion got its first public price tag this week, and Hut 8's−8.83% — Hut 8, down 8.83 percent today shares spent two days paying for it: down 7.21% on November 13 and 3.82% on November 14 12. On November 14, Coinpaper tallied Core Scientific's April 2026 financing disclosure and put the cost of turning a Bitcoin mine into an AI data center at about $9.3 million a megawatt 3. Laid against Hut 8's pipeline, that arithmetic splits the company in two 3.

The November 4 third-quarter call had described the signed half: 949 megawatts of IT capacity contracted under AI leases running 15 to 17 years, worth about $27 billion in base-term revenue 4. The quarter's receipts ran the other way. Revenue was $71.1 million, against $83.5 million a year earlier, and most of the quarter's $189.5 million of net income was an unrealized mark on bitcoin 5.

The distance between those numbers is a construction project. Construction gets paid now.

Revenue has sat near $70 million a quarter while the AI rent waits for 2027

The business that exists today is flat; the AI rent starts in 2027

$0.02B$0.04B$0.06B$0.08B$0.1BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$0.07B
Data
Revenue
Q4 '24$0.03B
Q1 '25$0.02B
Q2 '25$0.04B
Q3 '25$0.08B
Q4 '25$0.09B
Q1 '26$0.07B
Q2 '26$0.08B
Q3 '26$0.07B
Quarterly revenue in US dollars, calendar quarters. The 949 contracted megawatts hand over from the second quarter of 2027. Source: Hut 8 SEC filings.9

The leases are signed; the buildings are not

Nothing hands over before the second quarter of 2027, when the first data hall at River Bend, Louisiana is due; Beacon Point in Texas follows in the third quarter of 2027 and into 2028 5. Chief executive Asher Genoot says each campus will be "funded entirely at the project level, without requiring equity issuance or recourse debt at the parent" 5.

So far that funding means $7.5 billion of bonds tied to River Bend and Beacon Point's first phase, non-recourse in that lenders can claim only the individual project, not the parent company 4. Hut 8 also closed a $1.07 billion revolving credit facility, undrawn, and holds about $6.6 billion of cash 5. The bill has started regardless: quarterly interest expense of $105 million now outruns revenue 5.

Only 1,330 of Hut 8's 7,859 pipeline megawatts are under construction

Most of the pipeline is land options and power studies, not building sites

  • Under diligence3,300 MW42%
  • Under exclusivity3,180 MW40.5%
  • Under development49 MW0.6%
  • Under construction1,330 MW16.9%949 MW of IT capacity leased
Data
PartUtility capacityShare
Under diligence3,300 MW42%
Under exclusivity3,180 MW40.5%
Under development49 MW0.6%
Under construction1,330 MW16.9%
Utility capacity in megawatts by development stage, September 30, 2026; the annotation marks IT capacity under lease, a different basis. Sources: Hut 8 Q3 2026 results release and Q3 call.4,5

The rest of the pipeline is a $73 billion bill

Core Scientific−0.70% — Core Scientific, down 0.70 percent today, the first miner to make this pivot, disclosed $5.5 billion of construction spend for 590 contracted megawatts in its April financing documents, tallied by Coinpaper on November 14 3. That is about $9.3 million a megawatt, because an AI hall needs liquid cooling, dense electrical distribution and fiber that a shed of Bitcoin mining chips never had 3.

At that rate, Hut 8's 7,859-megawatt pipeline implies roughly $73 billion of building, close to ten times the bonds raised so far 34. Financing for Beacon Point's second phase is still being "evaluated" 5.

The market started charging for the gap this week

Keel, the former Bitfarms and a fellow convert, fell about 20% when its chief executive said no AI leases would be signed this year 6. Hut 8 itself jumped 16% on the day it reported 7.

The bitcoin that bridges the build slid toward $60,000 as exchange-traded-fund outflows hit a seventh straight day 8. Hut 8 has already funded about $250 million of buybacks by selling roughly 3,100 coins 4.

None of this doubts the demand. OpenAI$1.18T — OpenAI, private, latest valuation $1.18T chief executive Sam Altman's line is that the bottleneck for AI "isn't code, it's electrons," and River Bend sits on a $7 billion contract with Google and Anthropic 6. Power is the scarce asset; on this arithmetic, the constraint has moved from holding it to financing the buildings on it.

The marker is the River Bend handover in the second quarter of 2027 5. Until a tenant switches on, the $27 billion headline covers only the 949 leased megawatts, and the other 6,910 earn nothing until the pipeline's roughly $73 billion bill is raised and spent 5. Anyone buying the headline is paying for megawatts with no tenant.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    WhiteFiber's cloud revenue grew 0.4% because a departing customer paid $3.4 million to leave

    The Q3 10-Q shows the growth was a $3.4 million exit fee from a customer who left, while lease liabilities rose 6.6 times in nine months. Whose money moves: anyone holding WYFI, which opened Friday at $10.34 against a $34.33 analyst target.

    Data Center

    Prologis sues Trenton in federal court nine days after voters banned its data center

    Nine days after Trenton voters banned large data centers, Prologis is testing in federal court whether permits issued before a vote can override it, and the answer prices political risk for every data-center landlord.

    Data Center

    S&P warns data-center cyber risk is growing against $2 trillion of assets and $10 billion of premium

    S&P Global Ratings counts insurable data-center assets passing $2 trillion by 2027 against about $10 billion of new premium in 2026, and warns one attack could hit many tenants at once. Landlords and regulators are already rationing tenants by credit rating, and the Fed is set to keep raising the cost of the debt that funds the build-out.

    Data Center

    Wistron posts a record NT$1.15 trillion AI-server quarter funded by a $1.47 billion share sale

    Wistron posted a record NT$1.149 trillion quarter and is spending NT$12.87 billion for demand expected in 2028, but the growth burns cash, a $1.47 billion September share sale funds it, and the US states that buy the racks just elected governors who ran against data centers.

    Data Center

    Nvidia's interim CEO balked at a $250 billion OpenAI backstop, moving the bill onto Oracle's $70 billion

    The refusal moves the risk from Nvidia's balance sheet onto Oracle's own $70 billion of capital and the holders of its 7%-plus notes, the money building data centers behind a backlog that S&P puts half with OpenAI. Nvidia reports on November 17; Oracle's quarter lands in mid-December.

    Data Center

    Eoptolink's profit rose 80% while its operating cash flow fell 68%

    Shares in the Chinese optical-module maker fell 8.76% on November 13 on US chip-curb talk, but the import ban being drafted targets the generation after the parts it sells today. Its own nine-month report is the real repricing: profit converted into prepaid inventory for a buildout Washington is learning to ration.

    Subscribe to TheInference for free