Hut 8's $27 billion of AI leases cover 949 megawatts; the other 6,910 need about $73 billion to build
The Bitcoin miner's November 4 call put 949 megawatts under AI leases worth about $27 billion, against quarterly revenue of $71.1 million. Most of the 7,859-megawatt pipeline behind them has neither a tenant nor construction underway.
Richard Tangthree-minute read
The miner-to-AI conversion got its first public price tag this week, and Hut 8's−8.83% — Hut 8, down 8.83 percent today shares spent two days paying for it: down 7.21% on November 13 and 3.82% on November 14 12. On November 14, Coinpaper tallied Core Scientific's April 2026 financing disclosure and put the cost of turning a Bitcoin mine into an AI data center at about $9.3 million a megawatt 3. Laid against Hut 8's pipeline, that arithmetic splits the company in two 3.
The November 4 third-quarter call had described the signed half: 949 megawatts of IT capacity contracted under AI leases running 15 to 17 years, worth about $27 billion in base-term revenue 4. The quarter's receipts ran the other way. Revenue was $71.1 million, against $83.5 million a year earlier, and most of the quarter's $189.5 million of net income was an unrealized mark on bitcoin 5.
The distance between those numbers is a construction project. Construction gets paid now.
Revenue has sat near $70 million a quarter while the AI rent waits for 2027
The business that exists today is flat; the AI rent starts in 2027
Data
| Revenue | |
|---|---|
| Q4 '24 | $0.03B |
| Q1 '25 | $0.02B |
| Q2 '25 | $0.04B |
| Q3 '25 | $0.08B |
| Q4 '25 | $0.09B |
| Q1 '26 | $0.07B |
| Q2 '26 | $0.08B |
| Q3 '26 | $0.07B |
The leases are signed; the buildings are not
Nothing hands over before the second quarter of 2027, when the first data hall at River Bend, Louisiana is due; Beacon Point in Texas follows in the third quarter of 2027 and into 2028 5. Chief executive Asher Genoot says each campus will be "funded entirely at the project level, without requiring equity issuance or recourse debt at the parent" 5.
So far that funding means $7.5 billion of bonds tied to River Bend and Beacon Point's first phase, non-recourse in that lenders can claim only the individual project, not the parent company 4. Hut 8 also closed a $1.07 billion revolving credit facility, undrawn, and holds about $6.6 billion of cash 5. The bill has started regardless: quarterly interest expense of $105 million now outruns revenue 5.
Only 1,330 of Hut 8's 7,859 pipeline megawatts are under construction
Most of the pipeline is land options and power studies, not building sites
- Under diligence3,300 MW42%
- Under exclusivity3,180 MW40.5%
- Under development49 MW0.6%
- Under construction1,330 MW16.9%949 MW of IT capacity leased
Data
| Part | Utility capacity | Share |
|---|---|---|
| Under diligence | 3,300 MW | 42% |
| Under exclusivity | 3,180 MW | 40.5% |
| Under development | 49 MW | 0.6% |
| Under construction | 1,330 MW | 16.9% |
The rest of the pipeline is a $73 billion bill
Core Scientific−0.70% — Core Scientific, down 0.70 percent today, the first miner to make this pivot, disclosed $5.5 billion of construction spend for 590 contracted megawatts in its April financing documents, tallied by Coinpaper on November 14 3. That is about $9.3 million a megawatt, because an AI hall needs liquid cooling, dense electrical distribution and fiber that a shed of Bitcoin mining chips never had 3.
At that rate, Hut 8's 7,859-megawatt pipeline implies roughly $73 billion of building, close to ten times the bonds raised so far 34. Financing for Beacon Point's second phase is still being "evaluated" 5.
The market started charging for the gap this week
Keel, the former Bitfarms and a fellow convert, fell about 20% when its chief executive said no AI leases would be signed this year 6. Hut 8 itself jumped 16% on the day it reported 7.
The bitcoin that bridges the build slid toward $60,000 as exchange-traded-fund outflows hit a seventh straight day 8. Hut 8 has already funded about $250 million of buybacks by selling roughly 3,100 coins 4.
None of this doubts the demand. OpenAI$1.18T — OpenAI, private, latest valuation $1.18T chief executive Sam Altman's line is that the bottleneck for AI "isn't code, it's electrons," and River Bend sits on a $7 billion contract with Google and Anthropic 6. Power is the scarce asset; on this arithmetic, the constraint has moved from holding it to financing the buildings on it.
The marker is the River Bend handover in the second quarter of 2027 5. Until a tenant switches on, the $27 billion headline covers only the 949 leased megawatts, and the other 6,910 earn nothing until the pipeline's roughly $73 billion bill is raised and spent 5. Anyone buying the headline is paying for megawatts with no tenant.