Hut 8 shareholders carry River Bend's interest and tax bill until the first hall opens in 2027

The Louisiana campus's tax terms went public this week: a $7 billion Google-backstopped lease funds the build, while note interest and a smaller tax break than Meta received sit on Hut 8 shareholders until the first hall delivers in mid-2027.

Richard TangRichard Tang · 3 min read
Share
Aerial photograph of rows of bitcoin mining sheds at Hut 8's facility in Medicine Hat, Alberta
1 / 6Slide 1 of 6
Hut 8's bitcoin mining facility in Medicine Hat, Alberta, in 2018. The company is converting its mining power portfolio into AI infrastructure, with River Bend in Louisiana its largest campus yet.

The full cost stack of River Bend, Hut 8's−13.13% — Hut 8, down 13.13 percent today $10 billion AI data center campus in West Feliciana Parish, Louisiana, went public this week, and it reads as the price of building the part of the AI boom that models alone cannot build: land, power and halls. Hut 8, the Miami company converting a bitcoin-mining power portfolio into AI infrastructure, now has a deal with public numbers on both sides.

Parish President Kenny Havard told WWL Louisiana the parish settled on payments of $90 million a year from Hut 8 on land that would otherwise owe about $120 million in property taxes 1. The company has already paid $10 million of those taxes in advance and $16 million for the parish's water system 1.

On top of the tax discount sits debt service: the campus was financed with $3.25 billion of senior secured notes sold in April, and at their stated coupon the annual interest runs near $200 million 2. None of it earns revenue until the first hall opens, which Hut 8 targets for the second quarter of 2027 3.

The Google backstop is what made the financing possible

The revenue side is contracted before a hall opens. Fluidstack, a GPU-cloud intermediary whose expected end tenant is Anthropic$350B — Anthropic, private, latest valuation $350B, signed a 15-year, $7 billion lease for River Bend's first 245 megawatts, with Google financially backstopping the payments 3.

Anthropic has confirmed it is the expected tenant 4. That backstop is what let the project subsidiary reach the investment-grade bond market, a first for a single-sponsor data center, with the debt non-recourse to Hut 8's parent 2.

Hut 8 has since repeated the structure at Beacon Point in Texas and holds $26.6 billion of contracted lease value across the two campuses 2. Analysts at Maxim project those leases to average more than $1.75 billion a year in operating income once all halls deliver in late 2028 7.

The parish kept more tax than Meta, and negotiated it in public

West Feliciana's terms look generous to the taxpayer by Louisiana standards, where the data-center boom has run on giveaways. Meta's−1.52% — Meta, down 1.52 percent today Richland Parish deal offered property-tax reductions as steep as 80% 1. Havard negotiated without nondisclosure agreements, posted the tax deal online, and held hearings in the open while the state's economic development agency signed its own NDA with Anthropic 4.

The politics sit close to the deal: a wholly owned Hut 8 subsidiary gave $25,000 to Gov 4. Jeff Landry's PAC in June, months before the October 5 groundbreaking, where Donald Trump Jr., the company's partner in a bitcoin venture, appeared with Landry 4. Hut 8 says contributions are separate from commercial decisions, and the terms make the same case in numbers: the parish kept more tax than Meta did 14.

The delivery date, not the groundbreaking, is the investment case

Hut 8 reports third-quarter results on November 4, with consensus expecting a loss of about $0.75 a share on revenue of $76.5 million, after last quarter's miss 5. The revenue line is still a bitcoin-mining baseline and will stay that way for several quarters.

Hut 8 reports mining-era revenue and losses while River Bend contributes nothing

  • Revenue
  • Net income
-$0.4B-$0.2B$0B$0.2BQ1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$0.08B-$0.15B
Data
RevenueNet income
Q1 '25$0.02B-$0.13B
Q2 '25$0.04B$0.14B
Q3 '25$0.08B$0.05B
Q4 '25$0.09B-$0.28B
Q1 '26$0.07B-$0.22B
Q2 '26$0.08B-$0.15B
Hut 8 Corp quarterly revenue and net income, USD billions, from SEC filings; calendar labels mark quarters ended March, June, September and December. Source: Hut 8 SEC filings, retrieved October 30, 2026.6

What investors are actually pricing is execution: the first hall in the second quarter of 2027, run-rate income by late 2028 37. River Bend's model, contracted cash from creditworthy counterparties funding the power and buildings between AI models and the people who use them, is the most defensible part of the AI buildout, and the builder who executes it deserves the reward. The risk is a construction slip, and the test date is already on the calendar.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Delta Electronics set a record NT$197.1 billion quarter; Vicor's ITC case targets the same AI server modules

    Delta Electronics printed a second straight record quarter on AI server power, yet profit grew slower than sales, four banks cut its Thai unit's targets and the shares fell 9.8%. On the same modules, Vicor's royalty take is built to rise as its US trade case advances: the question for AI-power investors is no longer demand, it is who keeps the margin.

    Data Center

    Furukawa Bets 100 Billion Yen on Fiber While Corning's Customers Lock Supply Through 2032

    TrendForce counts a 180 million fiber-kilometer global shortfall for 2026 and data-center fiber prices above five times their 2025 levels. Furukawa Electric's 100 billion yen four-country expansion answers it, but the new lines ship from late fiscal 2028, after Corning's customers have already locked supply through 2032.

    Data Center

    Fermi's $6.5 billion lease comes due Friday, and the only news this week was a rerun

    The TensorWave lease closes, extends or dies on October 31. One day out there is no closing, no financing, and the one company story circulating this week was a year-old gas press release.

    Data Center

    A short seller says Iron Mountain's data center bet barely covers its interest bill. The stock rose.

    JCapital Research shorted Iron Mountain on October 28, arguing 81% of capex buys 13% of revenue at 1.7x interest cover. The filings agree with the arithmetic; the stock rose anyway.

    Data Center

    CoreWeave's stock has halved since Core Scientific shareholders refused its $9 billion bid

    A year after voting down the $9 billion all-stock sale, Core Scientific's holders hold a refused bid worth about $7.90 a share against a $14.42 stock. The standalone bet's first public test arrives on November 5.

    Data Center

    Nebius reports November 12. Its $3.5 billion Citi loan comes due October 2027.