IREN's 3-year-old Nvidia H100s re-rented at double the price; $6 billion of its $15 billion build unfunded

The doubled rent on three-year-old H100s is IREN's proof that GPU collateral holds value. It lands in front of lenders just as $6 billion of the company's $15 billion build still needs raising, and the form of that money decides who carries the risk.

Vincent JiangVincent Jiangthree-minute read
Share
IREN's Q1 FY27 earnings highlights slide: $200 million AI Cloud revenue, $20 billion backlog and capacity expansion targets
1 / 6Slide 1 of 6
IREN's own summary of the November 5 quarter that set off the argument: $200 million of AI Cloud revenue, $20 billion of backlog and a capacity path to 2028.

Three-year-old chips, doubled rents

Chips do not usually appreciate. On IREN's+1.22% — IREN, up 1.22 percent today Nov. 5 earnings call, co-CEO Daniel Roberts said these just did: "Older generation H100s, we just recontracted at double the original contract price." 1 IREN, a former bitcoin miner now renting out AI data centers, wrote its $9.7 billion Microsoft−2.43% — Microsoft, down 2.43 percent today contract as if the GPUs inside were worth nothing after five years. 12

The rest of the call ran the same direction: a five-year deal at about $22 million per megawatt with the customer prepaying about 90% of the GPU bill, a short-term deal above $40 million per megawatt, and contracted pricing up 11% to 12%. 2

A $6 billion hole in a $15 billion plan

The September quarter alone consumed $4.77 billion of capital spending, against $281 million a year earlier. 3 IREN still plans $15 billion this fiscal year, to June 2027; about $9 billion is covered by cash, committed GPU financing and prepayments, and $6 billion is "target" financing, subject to market conditions. 24 Short seller Jim Chanos counts about $20 billion of average capital employed by the time IREN reaches $4 billion of revenue and calls the resulting 5x ratio "not viable long-term." 1 The doubled H100 rent is IREN's answer: collateral that earns more at three years than it did new 1.

IREN's quarterly capex rose 17-fold in the year to September 2026

The September quarter alone spent 17x the year-ago quarter

$0B$2B$4B$6BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26Dell GPU deliveries for Microsoftland
Data
Quarterly capex
Q4 '24$0.18B
Q1 '25$0.44B
Q2 '25$0.36B
Q3 '25$0.28B
Q4 '25$0.73B
Q1 '26$1.33B
Q2 '26$1.98B
Q3 '26$4.77B
Capital expenditure by calendar quarter, USD billions, from IREN's SEC filings.3

The banks priced the hole, not the chips

Goldman Sachs+1.63% — Goldman Sachs, up 1.63 percent today cut its target to $30 from $50 and kept Neutral; JPMorgan went to $55 from $65, Cantor Fitzgerald to $47 from $99. 56 Net debt reached $4.43 billion, from $216 million, and the stock fell 45% in a month. 5 The other side of the ledger: June's $3.65 billion GPU financing, rated A, covered about 96% of the $5.8 billion Microsoft GPU bill at a 3.31% average cost, and backlog stands at $20.3 billion, two-thirds with investment-grade counterparties. 2 Roberts, on the same call: "Capital markets have become more selective in the last few weeks." 4

Three banks cut their IREN targets by 40 to 52 points

  • Target before
  • Target after
$0$20$40$60$80$100Goldman Sachs$30$50-40%JPMorgan$55$65-15%Cantor Fitzgerald$47$99-53%
Data
Target beforeTarget afterChange
Goldman Sachs$50$30-40.0%
JPMorgan$65$55-15.4%
Cantor Fitzgerald$99$47-52.5%
Price targets on IREN before and after the November 5 earnings call and Microsoft delay, per reports compiled by Yahoo Finance and Crypto Briefing.5,6

The form of the money decides it

If lenders accept the doubled mark, the $6 billion arrives as debt against GPUs and data centers IREN values at $6 billion. 2 If not, it arrives as stock, and shareholders have seen that bill: shares outstanding rose 48% in fiscal 2026. 1

Timing has already slipped once. Microsoft asked IREN to reconfigure network gear to ready 200 megawatts for frontier models, pushing the $4 billion annualized revenue milestone to January, possibly February 4, and Microsoft itself spent $5 billion less than expected on AI infrastructure after delays at third-party providers. 7 Research firm Currence expects 30% to 50% of capacity due this year to slip into 2027 or later. 8

The January print and the terms on the first slice of the $6 billion settle the argument. Debt priced like June's deal says Chanos is wrong; new shares say he is early.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading IREN

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Nvidia's $6.3 billion CoreWeave order survives a Huang exit, but the next financing does not

    A day after CoreWeave beat guidance and swore off bond markets, D.A. Davidson told investors to stay away because Jensen Huang was the real backstop. The filings say the order outlasts him; the next financing round is what would miss him.

    Data Center

    Johnson Controls and Armada ship first modular AI data center from Dublin to Norway on just 9 MW of orders

    A Johnson Controls plant in Dublin is now continuously building modular AI data centers, and the first unit has left for Fossefall in Norway. One buyer stands behind the firm orders, and the same morning JPMorgan turned wary on AI-linked industrials.

    Data Center

    Keefe Bruyette downgrades Riot Platforms on Anthropic tenant risk, $23 target vs Jefferies' $28

    A day after Jefferies more than doubled its target to $28 on the Corsicana lease, Keefe, Bruyette & Woods cut Riot to Market Perform at $23 over tenant credit. The 10-Q names the tenant Anthropic PBC, and Anthropic prices its IPO on November 18.

    Data Center

    CoreWeave named VAST Data a partner, then agreed to buy SSDs directly from Solidigm; backlog $132.5 billion

    CoreWeave's Q3 filing names VAST Data a partner and, in the same document, commits to buying SSDs directly from Solidigm, against a $132.5 billion backlog and $37-39 billion of capex. The question is what a storage software layer is worth when its biggest customer class buys the hardware itself.

    Data Center

    Oracle spent its $20 billion funding cap in five days, then lost Tencent and Microsoft

    Washington killed a $7 billion Tencent chip lease and Microsoft switched off its rented Oracle servers, days after Oracle spent the entire $20 billion it promised not to exceed through fiscal 2030. Bernstein says no more funding is needed; the mid-December quarter report now carries that whole argument.

    Data Center

    CoreWeave raised prices twice in a quarter; Hippocratic AI charges a fixed $2.50 an hour for admin calls

    CoreWeave's filed customer list quietly names Hippocratic AI, whose published prices of $15 and $2.50 an hour are fixed while the capacity behind them just repriced twice in a quarter. The margin squeeze shows up first in the application company's gross line, and in a listed name near you.