MARA sold $3 billion of bitcoin this year for an AI pivot that still has no tenant

Trading a shrinking mining business for AI data centers is the right bet, but with its first AI leases at risk of slipping past December 31 and a treasury down to about 20,000 coins, shareholders now carry the risk its lenders once did.

Richard TangRichard Tangthree-minute read
Share
MARA chairman and chief executive Fred Thiel speaking into a microphone on stage at Bitcoin Investor Week in New York
Fred Thiel, MARA's chairman and chief executive, at Bitcoin Investor Week in New York in March 2026. He has said the two AI leases targeted for December 31 "could move into next year."

MARA Holdings+3.82% — MARA Holdings, up 3.82 percent today has sold about $3 billion of bitcoin this year, and onchain trackers watched another 366 coins leave its wallets on Wednesday 1. Trading a shrinking mining business for AI data centers is the right bet: the chain runs power, land, then a paying tenant, and MARA is buying the first two links with the proceeds. The problem is the clock. On the third-quarter call, chief executive Fred Thiel said the two AI leases targeted for December 31 "could move into next year" 2.

The coins are bridge financing, and the bridge is shortening

Bitcoin trades near $64,186 and MARA's stock is down 13% in a week 14. The selling has been well timed: MARA's average sale price this year, $74,446, sits well above today's coin 1. After the quarter closed, the miner sold about $1.1 billion more of bitcoin and used most of the proceeds to repay every loan backed by its coins 3. Under 5% of its holdings are now pledged or lent, down from more than half, so a falling coin can no longer set off margin calls 2.

That deleveraging is real, and it spends the collateral: roughly 20,000 coins are left, about $1.3 billion at this week's price 1. Standing against them are the Long Ridge gas plant in Ohio, whose purchase MARA expects to close on November 27 4, noteholders who can demand repayment starting next year, and a $500 million share buyback the board authorized alongside the pivot 3.

The missing link is a signature, not power

No tenant has signed, and that is the break in the chain. Long Ridge, bought from FTAI Infrastructure for about $1.5 billion and financed in part with senior secured notes priced on November 17 at 8.75% 5, gives MARA power and land. Power plus land makes a campus, and a campus makes a business only when a tenant signs.

The Long Ridge Energy & Power gas plant in Ohio, with a combustion tower and turbine buildings, under a graphic reading Long Ridge Acquisition Approved
The Long Ridge Energy & Power plant in Ohio, which MARA expects to buy for about $1.5 billion and close on November 27. MARA said on November 5 that FERC had authorized the acquisition.MARA Holdings via X

Riot Platforms+8.48% — Riot Platforms, up 8.48 percent today, a rival miner, has already signed a lease worth roughly $28 billion with a frontier AI lab, while at Kearney, the data-center site Thiel expects among the first in MARA's portfolio to be contracted, the remaining issues sit on the customer's side 52. Thiel's stated strategy is patience: "waiting has improved the terms available to us" 5.

Mining still pays the bills, and mining is shrinking

What pays the bills while he waits is still mining, and mining is shrinking 4. Revenue sits well below its 2025 peak and fell again last quarter 6, and the quarter's reported profit was an accounting gain on coins the company has since been selling 1.

Mining revenue has slid 35% from its Q3 2025 peak

Mining, which pays the bills, is a third smaller than it was a year ago

$100$150$200$250$300Q3 2024Q1 2025Q3 2025Q1 2026Q3 2026$164.2Down 35% from a year earlier
Data
Revenue
Q2 2024$145.1
Q3 2024$131.7
Q4 2024$214.4
Q1 2025$213.9
Q2 2025$238.5
Q3 2025$252.4
Q4 2025$202.3
Q1 2026$174.6
Q2 2026$174.9
Q3 2026$164.2
Reported quarterly revenue, $ millions, from MARA's SEC filings, Q2 2024 to Q3 2026. Revenue peaked at $252.4M in Q3 2025 and was $164.2M in Q3 2026, 35% lower.6

The risk moved from lenders to shareholders

That is the trade underneath this week's headlines. Long Ridge's bondholders earn the 8.75% coupon, with interest of about $69 million a year sitting comfortably inside the plant's $144 million of annualized earnings 5. Shareholders hold everything else: a shrinking mining business, a buyback competing with the buildout for the same coins 3, and a lease test the market prices as conditional. Two signed leases by December 31 would give investors a reason to pay more than a miner's multiple; MARA trades at about 3.3 times forward sales against a five-year average of 5.1 4.

The wait is paid for in coins that are running out

Patience may improve the terms, as Thiel argues, but here it is financed out of a thinning stack of coins 5. Thiel has six weeks to the lease deadline, and the coins funding the wait are the ones still unsold. The reward belongs to whoever turns these megawatts into a signed lease. Until someone signs, the equity carries a bet the lenders no longer have to.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading MARA

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    TE Connectivity's AI wiring unit passed $3 billion with orders up 70%

    The Digital Data Networks unit doubled in two years to a little more than $3 billion and should add over $1 billion of revenue next year, the largest single slice of TE's guided growth. The same hyperscaler capex compounds faster at Amphenol, and neither stock trades like it.

    Data Center

    Digital Realty says the US chip license rule barely touches it as Malaysian data center stocks fell 20%

    The rule's first trading day cut Malaysian data centre builders MN Holdings and Critical Holdings nearly 20% and Nvidia partner YTL Power almost 10%. Digital Realty's Serene Nah says years of KYC and the US-headquartered carve-out leave the rule barely touching her business, and that it favors US operators.

    Data Center

    nVent claims a megawatt of AI data center carries $2 million of its cooling and power gear

    The claim arrived at the show with "significant pre-orders" and no customer, price or count, and the next day 86% of nVent's option premium sat in puts, options that pay if the stock falls. The fourth-quarter report decides whose number survives.

    Data Center

    The world's largest laptop maker shipped 9.6 million notebooks in Q3, down 24% in peak season

    Quanta's AI rack boom is crowding out the memory and processors its own notebooks need, and management's guidance takes servers to 85–90% of revenue next year. The bill lands on Quanta's balance sheet, Intel's forecast and the price of the next laptop.

    Data Center

    Eoptolink sees orders growing into next year as its stock falls a fifth day, more than 70% below its peak

    The upbeat guide landed on a fifth straight day of losses, with the stock more than 70% below its peak, hours after Washington signaled it will press ahead with curbs on Chinese data-center gear. Most of Eoptolink's revenue comes from the US cloud builders those curbs aim to cut off.

    Data Center

    Wagga Wagga council demands 1.5% of IREN's Redbank capital costs for community funds

    Wagga Wagga wants 1.5% of IREN's Redbank capital costs for community funds, a levy that lands while $18.9 billion of commitments sit against $3.5 billion of cash and $6 billion of the build's financing is not yet secured.

    Subscribe to TheInference for free