Digital Realty says the US chip license rule barely touches it as Malaysian data center stocks fell 20%

The rule's first trading day cut Malaysian data centre builders MN Holdings and Critical Holdings nearly 20% and Nvidia partner YTL Power almost 10%. Digital Realty's Serene Nah says years of KYC and the US-headquartered carve-out leave the rule barely touching her business, and that it favors US operators.

Vincent JiangVincent Jiangfour-minute read
Share
A Digital Realty data centre in Markham, Ontario: a low building with a glass corner and corrugated metal walls under a blue sky.
A Digital Realty data centre in Markham, Ontario. The company says years of end-user due diligence and its US parentage leave it largely outside the new US licence rule for advanced AI chips shipped to Singapore, Malaysia, Thailand, Indonesia and Brazil.

The rule, and the tape it hit

The US Commerce Department's Bureau of Industry and Security published an interim final rule on November 16, "Addressing Remote Access to Advanced Semiconductors" 7. It takes effect on Federal Register publication, expected November 19, Thursday 67.

The rule requires licenses to ship advanced AI chips into Singapore, Malaysia, Thailand, Indonesia and Brazil, all named as carrying an "unacceptable" risk of diversion 467. It also bars any datacentre worldwide from giving China-headquartered customers, or those with Chinese ultimate parents, access to more than roughly 12 million aggregate TPP, about 750 Nvidia−2.79% — Nvidia, down 2.79 percent today H100-class chips 467. Datacentres already serving such customers have 90 days from the effective date to get a license, and Commerce will take comments for 60 days 67.

Megaspeed's $4.8 billion flow set the rule off

Megaspeed, a Singapore-based Nvidia partner, moved at least $4.8 billion of advanced AI equipment through Singapore in under two years, and the scandal around it took down Nvidia's CEO, Jensen Huang, who resigned November 12 6. The Financial Times reported last month that Tencent agreed to lease access to 100,000 advanced AI chips via Oracle−0.82% — Oracle, down 0.82 percent today datacentres in Southeast Asia, exactly the arrangement the rule now targets 6.

The market did not wait. On the first trading day, Malaysian datacentre builders MN Holdings and Critical Holdings each fell nearly 20%, Nvidia partner YTL Power almost 10%, and its parent YTL Corp 8% 45.

The selloff's second tier: chip suppliers down 3 to 8%, China's SMIC up 7%

China's SMIC rose while suppliers fell, as investors priced ecosystem separation

-10-50510YTL Corp-8Frencken-3.91AEM Holdings-2.9Tencent-3Alibaba-5SMIC7
Data
Value
YTL Corp-8
Frencken-3.91
AEM Holdings-2.9
Tencent-3
Alibaba-5
SMIC7
One-day share-price changes, November 17, 2026, in percent, as reported by Reuters via International Business Times. The Malaysian datacentre builders MN Holdings and Critical Holdings, reported as falling nearly 20%, and YTL Power, nearly 10%, are not drawn because those figures were reported only as approximations; see the text. Sources: 5, 7.5,7

The camp that did not sell

Into that tape walked Serene Nah, Digital Realty's+1.13% — Digital Realty, up 1.13 percent today managing director and head of Asia-Pacific, opening the company's fifth AI test lab and first in Southeast Asia at its SIN11 facility in Loyang, Singapore 13. Her verdict on the rule: "I personally don't think the new rules will have much impact on us" 13.

Three reasons from the record. First, years of KYC that already checks end users, the exact diligence the rule now expects of every operator 137. Second, exposure mismatch: its Malaysian and Indonesian sites host enterprise and connectivity customers, not China-linked compute 13. Third, the carve-out: shipments to companies headquartered in the US, or with a US ultimate parent, are exempt from the five-country licenses provided the exporter files monthly reports, and Digital Realty is a US operator. "I think gives us a better operating advantage," Nah said 137.

Read the caveat before the prize

The bull case rests on numbers the company gave the same day: about 84MW live across three Singapore datacentres, a provisional 50MW award on Jurong Island (SIN13, due 2029), all inside a nearly S$7 billion Singapore commitment, of which more than S$4.3 billion is for new datacentres 13. But the 50MW site carries Nah's own warning: "we may have to be very selective with what customers we are placing in there" 13.

The rule licenses chips, not demand, yet it narrows the customer pool for new capacity in the very week the build is designed. Enterprise asks in APAC now run 1 to 3MW per customer, up from about 300kW two years ago, and US-headquartered customers are queuing for Jurong Island 13. If the selective question resolves, it likely resolves toward Digital Realty, because its largest prospective tenants sit on the exempt side of the rule; that is an inference from Nah's comments, not a stated fact 13.

Capex reached $1.38B in Q3 as operating cash fell to $0.38B

  • Capex
  • Operating cash flow
$0B$0.5B$1B$1.5BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26Capex doubled, operating cash down41%
Data
CapexOperating cash flow
Q4 '24$0.22B$0.77B
Q1 '25$0.73B$0.4B
Q2 '25$0.77B$0.64B
Q3 '25$0.69B$0.65B
Q4 '25$0.54B$0.72B
Q1 '26$0.86B$0.53B
Q2 '26$0.92B$1.06B
Q3 '26$1.38B$0.38B
Digital Realty's quarterly capital spending and operating cash flow, USD billions, Q4 2024 to Q3 2026, with capex shown as positive spending. The Singapore build sits inside this programme. Source: 8, Digital Realty quarterly figures from its SEC filings.8

Malaysia will not negotiate, Singapore is studying it

Kenanga Investment Bank, a Malaysian brokerage, said in a Tuesday research note that Malaysian datacentre construction firms with mostly US-based customers face limited direct exposure 5. Malaysian Trade Minister Johari Abdul Ghani said the country would not negotiate with Washington and companies would comply 5. Singapore's government is studying the rule and "exploring how to facilitate trusted access for Singapore companies" 46.

This column has followed Digital Realty's regional push before: the 9.9% stake it took with Goodman in NextDC after that operator's 42% crash, and the Evergy+0.24% — Evergy, up 0.24 percent today power deal it has not yet signed 13456. What is new since those pieces is the rule itself, the November 17 selloff, and Nah's on-record positioning the same day 13456.

The 90-day clock starts Thursday

Watch the next readings: the Federal Register publication on November 19, which starts the 90-day license clock and the 60-day comment window in which the rule can be reshaped 7, whether SIN13's "more selective" language turns into customer names on the wrong side of the license line, and whether the beaten Malaysian names confirm Chinese-linked lease books 46. The evidence so far favors the US operator's side of the argument, and the clock starts Thursday 467.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading DLR

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    TE Connectivity's AI wiring unit passed $3 billion with orders up 70%

    The Digital Data Networks unit doubled in two years to a little more than $3 billion and should add over $1 billion of revenue next year, the largest single slice of TE's guided growth. The same hyperscaler capex compounds faster at Amphenol, and neither stock trades like it.

    Data Center

    nVent claims a megawatt of AI data center carries $2 million of its cooling and power gear

    The claim arrived at the show with "significant pre-orders" and no customer, price or count, and the next day 86% of nVent's option premium sat in puts, options that pay if the stock falls. The fourth-quarter report decides whose number survives.

    Data Center

    The world's largest laptop maker shipped 9.6 million notebooks in Q3, down 24% in peak season

    Quanta's AI rack boom is crowding out the memory and processors its own notebooks need, and management's guidance takes servers to 85–90% of revenue next year. The bill lands on Quanta's balance sheet, Intel's forecast and the price of the next laptop.

    Data Center

    MARA sold $3 billion of bitcoin this year for an AI pivot that still has no tenant

    Trading a shrinking mining business for AI data centers is the right bet, but with its first AI leases at risk of slipping past December 31 and a treasury down to about 20,000 coins, shareholders now carry the risk its lenders once did.

    Data Center

    Eoptolink sees orders growing into next year as its stock falls a fifth day, more than 70% below its peak

    The upbeat guide landed on a fifth straight day of losses, with the stock more than 70% below its peak, hours after Washington signaled it will press ahead with curbs on Chinese data-center gear. Most of Eoptolink's revenue comes from the US cloud builders those curbs aim to cut off.

    Data Center

    Wagga Wagga council demands 1.5% of IREN's Redbank capital costs for community funds

    Wagga Wagga wants 1.5% of IREN's Redbank capital costs for community funds, a levy that lands while $18.9 billion of commitments sit against $3.5 billion of cash and $6 billion of the build's financing is not yet secured.