Microsoft supplier IREN tripled AI cloud revenue to $200 million; its $4 billion target slips to January

AI Cloud revenue tripled sequentially to $200 million and the backlog stands at $20.3 billion, yet the $4 billion run-rate target slipped to January or February. The build converts on schedule; the calendar and the uncommitted $6 billion are the open questions.

Richard TangRichard Tang · 2 min read
Share
Aerial view of an IREN data center campus under construction, with a large crane and rows of data halls
1 / 7Slide 1 of 7
IREN posted this drone footage of its campuses under construction on 5 November, the day before its results, with the line "this is what execution at scale looks like."

IREN+18.69% — IREN, up 18.69 percent today filed its first quarter as a Microsoft supplier tonight, and the document answers both camps at once. The bears who spent two days reading satellite imagery of an unfinished Texas data hall got their confirmation: the company's more-than-$4 billion run-rate target, promised for year-end, has moved to January 2027 and may stretch to February, after a customer-requested design change and supplier timing 1.

The bulls got something bigger: AI Cloud revenue of $200 million for the quarter ended September 30, nearly triple the prior quarter's $71 million, with an 86 percent segment gross margin 1.

Revenue dipped as mining faded, then the AI quarter pushed it past its 2025 peak

$0M$100M$200M$300MQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$228M
Data
Total revenue
Q3 '24$36M
Q4 '24$116M
Q1 '25$145M
Q2 '25$187M
Q3 '25$240M
Q4 '25$185M
Q1 '26$145M
Q2 '26$137M
Q3 '26$228M
Total revenue by calendar quarter, in US dollars; the September 2026 quarter is IREN's fiscal first quarter of 2027. Sources: IREN quarterly figures from SEC filings; IREN Q1 FY27 press release.3,1

From a construction story to a billing story

The revenue line matters because it is the first hop of the chain proven in cash, not in renderings. Contracted compute actually went into service: Horizon 1 was delivered to Microsoft−0.78% — Microsoft, down 0.78 percent today during the quarter and earned NVIDIA+4.05% — NVIDIA, up 4.05 percent today Exemplar status on its GB300 systems 1. What was a construction story three months ago is now a billing story. Total revenue reached $228 million, up two-thirds sequentially, while bitcoin mining shrank to $28 million; this is now an AI infrastructure company that happens to own a shrinking mining tail 1.

AI Cloud revenue tripled in a quarter while bitcoin mining halved

AI Cloud revenue tripled in one quarter as mining shrank

  • AI Cloud revenue
  • Bitcoin mining revenue
0M50M100M150M200MQ4 FY26Q1 FY27200M28M
Data
AI Cloud revenueBitcoin mining revenue
Q4 FY2671M67M
Q1 FY27200M28M
Segment revenue for the June 2026 quarter (Q4 FY26) and the September 2026 quarter (Q1 FY27), in US dollars. Source: IREN, Q1 FY27 press release, Form 8-K Exhibit 99.1, 5 November 2026.1

Demand is not the bottleneck; the calendar and the money are

The backlog grew to $20.3 billion, two-thirds of it owed by investment-grade counterparties, and pricing on new deals keeps rising 1. Post-quarter, IREN signed a five-year contract at about $22 million per megawatt with 90 percent of the GPU capex prepaid by the customer, and a short-term deal at $40 million per megawatt 1.

When a customer prepays the hardware, it is telling you it fears scarcity, not oversupply.

The bottleneck is the one the audit flagged: converting construction into accepted capacity, and paying for it. Horizon 2 through 4 are in late-stage construction 1, and the remaining fiscal-2027 capex is $15 billion, of which $9 billion is covered by cash and committed financing 1.

Cash and debt both multiplied more than tenfold in seven quarters to fund the build

  • Cash
  • Debt
$0B$2B$4B$6B$8BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$7.84B
Data
CashDebt
Q4 '24$0.43B$0.32B
Q1 '25$0.18B$0.32B
Q2 '25$0.57B$0.96B
Q3 '25$1.03B$0.97B
Q4 '25$3.26B$3.84B
Q1 '26$2.21B$3.97B
Q2 '26$7.57B$7.84B
Cash and total debt at each calendar quarter-end, in US dollars, shown from Q4 2024 onward because earlier debt disclosures are not comparable. Source: IREN quarterly figures from SEC filings.3

January is the verdict

The other $6 billion depends on market conditions 1, and the 10-Q filed the same night carries a new note purchase agreement and a guaranty 2, evidence the company is raising that money while lenders repriced exactly such paper this week. Watch whether the January delivery holds. If it does, the bears' timeline argument dies; if it slips again, the financing gap, not the contracts, becomes the story. The builder who gets these halls accepted on schedule is the one earning the value here, and tonight's filing says IREN is closer to being that builder than the satellite photos suggested.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading IREN

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Nebius has 5 GW of power signed and about 200 MW billing: the ladder that sets its ARR guide

    Nebius's capacity is counted in gigawatts while its revenue arrives in megawatts. Working the ladder from contracted to connected to billing power shows what the December guide really assumes, what a customer prepayment is, and why the debt market already ranks the neoclouds.

    Data Center

    Microsoft tightens oversight of IREN, Nebius and Nscale; lenders hold the bill on their unfinished halls

    Microsoft, the biggest tenant in AI computing, has started auditing its outside builders: a report on tightened oversight of IREN, Nebius and Nscale, plus a lapsed Nscale expansion option, sent the GPU-cloud suppliers down 9 to 21 percent ahead of IREN's earnings tonight. The borrowed money behind their unfinished halls is what the audit really tests.

    Data Center

    Crusoe says it cut switchgear lead time 40% and borrowed $700 million against turbines

    Crusoe, the company behind OpenAI's Abilene data center, now builds the electrical gear that decides when a hall can be energized, and has drawn $700 million of debt secured by power equipment. What gets tested next is the lead-time premium of ABB, GE Vernova, Eaton and Vertiv.

    Data Center

    Voters restricted data centers in 37 of 38 ballot measures; AI buildouts now need consent

    Voters restricted data centers in 37 of 38 decided local ballot measures on November 3. The capital for the AI buildout is still there; the consent is not, and that reprices every site in the pipeline.

    Data Center

    Backblaze's B2 grew 47%, but CoreWeave's deal is paid in $21.94 converts, triple the $7.40 share price

    B2 storage grew 47% while CoreWeave barely contributed; the same night's 10-Q prices the anchor deal in customer warrants, zero-coupon debt and a conversion strike about triple the share price.

    Data Center

    DigitalOcean raises its 2027 growth target to 60% and files to sell $1 billion of new shares the same day

    DigitalOcean raised its 2027 growth target to 60%+ the same morning it opened a $1 billion share program, and its 10-Q shows leases, not debt, now fund the AI build. Analysts cut five price targets into the beat, yet the Street average still sits near double the market price.