Chips

Nvidia's capacitor orders go to Murata and Taiyo Yuden first; Yageo gets the overflow

A supplier hierarchy published on November 20 shows Yageo's record AI revenue arrives only after Murata, Taiyo Yuden and Samsung Electro-Mechanics take their share. Yageo is adding 2027 capacity on that rented demand while Nvidia funds the tier above it.

Vincent JiangVincent Jiangthree-minute read
Share
Macro photograph of surface-mount multilayer ceramic capacitors, small brown chips with silver terminals, soldered onto a green printed circuit board and labelled C15, C21, C22 and C69.
Multilayer ceramic capacitors on a circuit board. Nvidia's orders for the parts reach Murata and Taiyo Yuden first; Yageo and Walsin take the overflow.

On November 20, Digitimes published Nvidia's multilayer ceramic capacitor pecking order: Murata and Taiyo Yuden get priority, Samsung Electro-Mechanics−12.54% — Samsung Electro-Mechanics, down 12.54 percent today holds a long-term arrangement, and Yageo−8.22% — Yageo, down 8.22 percent today and Walsin Technology "mainly receive orders spilling over from larger suppliers" 1. Eleven days earlier, Yageo had booked the best month in its history.

The record the market read as a socket win

The record was real. AI-related applications reached nearly 20% of Yageo's revenue in the third quarter of 2026, up from 16% in the second 2. October consolidated revenue hit NT$17.597 billion, up 55% year on year, out-running the third quarter's monthly average of about NT$16.5 billion 3. Third-quarter sales rose roughly 50% to NT$49.53 billion and net income rose 88% to NT$11.98 billion 4. The stock still fell 9.13% on November 3, leaving a market cap of TWD 930.5 billion 5.

Yageo's sales rose 50% in the third quarter and 36% over nine months

The record the market read as an AI socket win

  • 2025
  • 2026
050,000100,000150,000Q3Nine months132,153.51
Data
20252026
Q333,086.7149,531.54
Nine months96,961.8132,153.51
Consolidated sales in NT$ millions, exactly as reported: third quarter and nine months ended September 30, 2026, versus the same periods of 2025. Source: MarketScreener summary of Yageo Corporation results.4

What overflow looks like at 800 volts

The overflow is not commodity scrap. As AI racks move from 48-volt distribution toward 800-volt direct current, Yageo says customers have asked for single 900-volt aluminum electrolytic capacitors to replace pairs of 450-volt units wired in series, simplifying the power shelf 6. Specialist work like that lands on the second tier only when rack volumes outgrow the first call's capacity, which makes the order stream a derivative of somebody else's shortfall.

Close-up of cylindrical surface-mounted electrolytic capacitors standing on a green circuit board beside a memory chip.
Aluminum electrolytic capacitors on a board. Yageo says AI-rack customers want one 900-volt part where they used to wire two 450-volt units in series.Mercado Viagens, CC BY 2.0

The tier above is being paid to close the gap

On November 17 Nvidia−10.86% — Nvidia, down 10.86 percent today announced multibillion-dollar funding for SPIL to raise dedicated advanced packaging capacity by mid-2029, and a Kinsus agreement to more than triple substrate capacity dedicated to Nvidia, starting in 2027 7. Samsung Electro-Mechanics said on November 18 that the Nvidia alliance now extends from substrates into MLCCs, with full-scale mass production targeted for 2029 8. Meanwhile supply-chain sources told Digitimes that HBM4 shortages and PCB yield problems could push broader Vera Rubin production into the first quarter of 2027, and component suppliers expect fourth-quarter orders below earlier estimates 1.

What could prove the bulls right

Yageo reports a strong book-to-bill and guides fourth-quarter revenue slightly above the third quarter despite the seasonal dip 3, with utilization above 95% 2. Samsung Electro-Mechanics' lines reach full production only in 2029 8, and AI chip development cycles have settled at 1.5 to 1.7 years, limiting how far upgrades can slow 1. Spillover is still money. But it is money that arrives last and leaves first, and the 10-15% capacity Yageo plans for 2027 is fixed cost against rented demand 2.

December revenue is the next test

Watch Yageo's December-quarter revenue against that guidance, and whether fourth-quarter MLCC orders land below plan as the sources expect. (Earlier on The Inference: Nvidia's substrate money went to Kinsus and Samsung Electro-Mechanics, not LG Innotek, November 19; Nvidia's agreements with both companies are on the record 7.)

Get Chips by email, free

How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.

Loading NVDA

More about NVIDIA

NVDAFiscal Q2 2027
Fiscal Q2 2027 · quarter to 26 Jul 2026 · changes vs a year earlier

Revenue rose 106% to $96.2B, 92.5% of it from Data Center, “driven by the ramp of our Blackwell Ultra infrastructure”. Gains on equity stakes of $7.8B lifted net income to $59.7B.

Revenue$96.2B▲ 106%
Gross margin75.0%▲ 2.6 pts
Operating margin66.2%▲ 5.4 pts
Net income$59.7B▲ 126%
Hyperscale$48.7B▲ 102%AI clouds & enterprise$40.3B▲ 138%Data Center$89.0B▲ 117%Edge Computing$7.2B▲ 27%Revenue$96.2B▲ 106%Gross profit$72.1B75.0% marginCost of revenue$24.1BOther income$7.8Bequity-stake gainsOperating income$63.7B66.2% marginOperating expenses$8.4BNet income$59.7B▲ 126%Tax$11.8B16.5% rateR&D$7.1BSG&A$1.4B
Show as a table
LineValue
Revenue$96.2B
Gross margin75.0%
Operating margin66.2%
Net income$59.7B
Hyperscale$48.7B
AI clouds & enterprise$40.3B
Data Center$89.0B
Edge Computing$7.2B
Gross profit$72.1B
Cost of revenue$24.1B
Other income$7.8B
Operating income$63.7B
Operating expenses$8.4B
Tax$11.8B
R&D$7.1B
SG&A$1.4B

Reader comments

0 comments

    Chips

    Micron down 13.9% at $594.51, half its June record, as TrendForce forecasts 2027 NAND declines

    A TrendForce forecast tipping NAND into decline for 2027 knocked 13.9% off Micron and 16.1% off SanDisk on Friday, leaving Micron at half its June record and roughly 3.4 times forward earnings even as customers pay deposits to lock supply. Micron's December 17 report, guiding an 86.25% gross margin, is the test.

    Chips

    Nvidia's worst week since 2008 erased $901 billion, and leveraged AI cloud Nebius fell 14%

    The S&P 500 entered a correction Friday while Nvidia lost $901 billion in a week, and the pain landed hardest on the leveraged AI cloud builders whose models assumed Nvidia would keep financing the boom. Nebius is the purest expression of that bet.

    Chips

    SEC examines Nvidia's accounting, Reuters reports, as more than $2.5 trillion has left the stock

    The SEC is examining Nvidia's accounting, Reuters reports, adding a federal securities inquiry to a week that already brought a California subpoena and congressional records demands. An inquiry into the books is about revenue already booked, not next year's orders, and the supplier chain fell 11% to 14% with it.

    Chips

    Trump publicly urges Nvidia to reinstate Jensen Huang

    The board has refused and is running a permanent CEO search while Nvidia sits under an SEC probe, a California subpoena and a $2 trillion market-cap drawdown; a president lobbying a board raises the stakes of the decision for every shareholder.

    Chips

    Google cuts 1 million Broadcom-designed TPU chips from 2027 plans, survey says

    Most of the cut lands on the higher-priced 8i Max, so the revenue hit likely exceeds the one-in-five unit cut. Broadcom fell more than 10% on the survey, and the lost volume lands on up to $114 billion of disclosed AI financing commitments.

    Chips

    Broadcom fell 11.6% and AMD 11.3% on order-cut fears; GF Securities finds Meta, Microsoft CPU orders intact

    Chip stocks fell more than 8% on cut fears, but a supply-chain check from Hong Kong brokerage GF Securities found Meta's and Microsoft's server CPU orders intact, and kept Buy ratings on the two suppliers hit hardest, AMD and Intel.

    Subscribe to TheInference for free