Hut 8 fell 15% the day after Anthropic's $119.5 billion IPO; $10.7 billion of River Bend rent is unsigned

Anthropic closed its second session at $88.30, near its $83 IPO price, and the listing pitched as fresh money for Hut 8's expansion gave back its debut gain within a day. Of River Bend's potential $17.7 billion in lease value, $10.7 billion is renewals that Google does not guarantee and Anthropic has not signed.

Vincent JiangVincent Jiangthree-minute read
Share
Aerial dusk view of Hut 8's River Bend data center campus under construction in Louisiana: a large roofed hall, a red construction crane and earthworks.
Hut 8's River Bend campus in Louisiana under construction. The first data hall there is due in the second quarter of 2027; $10.7 billion of the campus's potential rent is unsigned renewals.

Anthropic$350B — Anthropic, private, latest valuation $350B, the company behind the Claude chatbot, gave back most of its debut pop on Friday. Shares that opened Thursday at $111.50, 34% above the $83 IPO price, closed Friday at $88.30, down 9.1% from Thursday's close 12. The Nasdaq 100 index fell 5.6% the same day 1. Hut 8−13.98% — Hut 8, down 13.98 percent today, the bitcoin miner turned data-center landlord whose River Bend campus in Louisiana runs clusters for Anthropic, fell harder: just over 15%, to $46.96 3.

Hut 8 fell harder on Friday than Anthropic or the Nasdaq 100

The landlord fell harder than the tenant and the market

-15%-10%-5%0%Hut 8-15%Anthropic-9.1%Nasdaq 100-5.6%S&P 500-3.7%
Data
Value
Hut 8-15%
Anthropic-9.1%
Nasdaq 100-5.6%
S&P 500-3.7%
Moves on November 20, 2026. Anthropic, Nasdaq 100 and S&P 500 are closing changes per Bloomberg; Hut 8 is an afternoon reading per Seeking Alpha.1,3

Google guarantees $7 billion of the rent; $10.7 billion has no signature

The over-allotment, the underwriting banks' option to sell extra shares, was exercised Friday and lifted the total raised by Anthropic and its selling co-founders to $119.5 billion, $93.5 billion of it in the IPO itself 1. Thursday's read was that this cash now stands behind Hut 8's upside 4. Part of it does. River Bend's 15-year lease with Fluidstack, the operator that runs the campus for Anthropic, is worth $7.0 billion in base rent, about $454 million of net operating income a year against $235 million of Hut 8's 2025 revenue, and Google backstops every base year 4.

The backstop stops there. Three five-year renewals would lift the contract to about $17.7 billion, leaving roughly $10.7 billion that rests on Anthropic's own balance sheet, plus Fluidstack's right of first offer, the right to bid first on up to 1,000 megawatts more at River Bend 4. None of it is signed 4.

Hut 8 is building as if the renewals were signed

Hut 8's debt hit $7.66 billion on September 30, from $423 million at the end of March, and capital spending ran $581 million and $481 million in the past two quarters against $53 million in the first 7. The first River Bend data hall is due in the second quarter of 2027 56; until it opens, shareholders carry the campus's interest and tax bill.

Capex went from $53 million in the first quarter to $581 million in the second

$0M$200M$400M$600MQ1 2026Q2 2026Q3 2026$481M$581M
Data
Capital spending
Q1 2026$53M
Q2 2026$581M
Q3 2026$481M
Hut 8's capital spending by quarter, $ millions, as reported in its quarterly SEC filings. Quarters ended March 31, June 30 and September 30, 2026. Over the same three quarters its debt went from $423 million to $7.66 billion.7

The cash arrived; the signature did not

The bull case is real on paper: Anthropic's run-rate revenue, annualized from a shorter period, reached $81 billion as of October 31, up $10 billion in a month 1, and analysts expect AI leases to lift Hut 8's revenue more than fivefold between 2025 and 2028 4. Thursday's rotation drained the market around the listing, with investors selling other assets to fund their Anthropic purchases 2. The bear case predates the IPO: 949 megawatts contracted, nothing operating yet, equity as a leveraged claim on unbuilt halls 6.

Most of the $119.5 billion was already spoken for

Anthropic's prospectus sets the clock: about $895 billion of computing and infrastructure commitments, only $70 billion of it due before September 2027, so most of what the IPO cash could buy was already ordered, leased or reserved 5. Google−1.04% — Google, down 1.04 percent today backstops River Bend's base rent, and Fluidstack, the tenant, pays it 4. The renewals carry no such guarantee. The tell: any signed piece of that 1,000 megawatts while Anthropic's IPO cash is fresh 4.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Mutual funds hold Equinix 7 basis points light as Blackstone pays a 7% yield

    Large-cap mutual funds now hold Equinix seven basis points below its benchmark weight, three days after Blackstone's new trust paid a 7.0% cap rate for Amazon-leased data centers. Two prices for the same AI real estate, and the public REITs sit between them.

    Data Center

    Arizona's attorney general asks Cochise County to delay vote on SpaceX's $50 billion data center

    Kris Mayes wants the December 9 zoning vote held until state and federal reviews are done, three days after a Texas county rejected SpaceX's Starbase tax break. The spending those campuses must justify is already committed: $48.1 billion out the door and $44 billion of chip debt borrowed at up to 8.36%.

    Data Center

    Ulanqab's AI compute doubled in a year to 190,000 petaflops, official count shows

    The first official tally of China's fastest-growing AI hub lands days after Washington restricted remote access to US chips, one of two back doors behind nearly half the country's AI compute. Seven million contracted racks in one Inner Mongolia city now wait on a single bottleneck: Huawei's Ascend supply.

    Data Center

    SpaceX's 10-Q shows $48.1 billion of capex against $13.1 billion of cash before its December 8 lock-up

    SpaceX's Q3 10-Q puts the build at $48.1 billion of nine-month capex against $13.1 billion of operating cash, with the gap filled by $43 billion of chip-lease debt near 8.3%. That is the case against the equity 17 days before its lock-up expires, with Anthropic holding a 90-day exit.

    Data Center

    Applied Digital put $97 million into ChronoScale on a note that matures December 31

    The Schedule 13D/A filed November 20 shows the funding behind ChronoScale's $200 million Super Micro GPU order: a $97 million no-interest note from majority owner Applied Digital, fully funded and maturing December 31. Conversion needs a stockholder consent still in the mail, so one balance sheet carries the timing risk.

    Data Center

    Trump threatens 'tremendous tax' on US companies that build data centers abroad

    No rate, timetable or legal authority accompanied the threat, which landed on Alphabet, Amazon, Microsoft, Meta and Oracle, the companies already building abroad, on a day the Nasdaq 100 fell 5.7%.

    Subscribe to TheInference for free