Power

PG&E wants cheap permits and expensive grids: Proposition 45 is where the two meet

PG&E's October quarter, its $22.5 billion San Francisco grid claim and its $2.3 million Proposition 45 check are one fight over who pays for California's AI infrastructure, and two dated votes set the outcome.

Richard TangRichard Tang · 2 min read
Share
Patti Poppe, chief executive of PG&E Corporation
1 / 6Slide 1 of 6
Patti Poppe, chief executive of PG&E Corporation, whose October quarter, $22.5 billion San Francisco grid valuation and $2.3 million Proposition 45 contribution put the company on all sides of California's AI infrastructure fight.

PG&E reported a weaker quarter on October 22 2, filed a 5,000-mile undergrounding plan it says cuts wildfire risk by 98% and is worth $117 billion in long-term benefits 24, and told California regulators a San Francisco grid takeover would cost $22.5 billion against the city's $3.4 billion estimate, including $7.6 billion in business severance damages 3, all while $2.3 million of its money sits behind the November 3 ballot measure that would speed environmental review for projects its opponents say include data centers 1. One company, three levers over who pays for California's AI grid. Read together, PG&E+1.09% — PG&E, up 1.09 percent today is payer, beneficiary and lobbyist in the same fight.

The commission, not the market, is the customer

The quarter was mixed: core earnings fell to $0.41 a share from $0.50, Wildfire Fund expense rose to $141 million from $86 million, and PG&E cut $2 billion from its 2027 capital plan 2. The company is capital-hungry and needs returns approved, which makes the Public Utilities Commission, not the market, the customer that matters 2.

PG&E's quarterly capex has climbed toward $3.3 billion even as it trims the 2027 plan

$0B$1B$2B$3B$4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$3.3B
Data
Capital expenditures
Q1 '24$2.64B
Q2 '24$2.3B
Q3 '24$2.61B
Q4 '24$2.83B
Q1 '25$2.64B
Q2 '25$3.07B
Q3 '25$2.93B
Q4 '25$3.16B
Q1 '26$3.36B
Q2 '26$2.97B
Q3 '26$3.3B
Quarterly capital expenditures in billions of US dollars, from PG&E Corporation's SEC filings, Q1 2024 through Q3 2026. Source: PG&E Corporation quarterly filings, retrieved 27 October 2026.6

PG&E is a mid-tier funder of Yes on 45 behind Brin's $10 million

$0M$2M$4M$6M$8M$10MBrin committee$10MPG&E$2.3MEdison (direct)$2MSempra$1MCal. Resources$1MPrologis$0.5M
Data
Value
Brin committee$10M
PG&E$2.3M
Edison (direct)$2M
Sempra$1M
Cal. Resources$1M
Prologis$0.5M
Disclosed giving to Yes on Proposition 45 committees, in millions of dollars, per Capital & Main campaign-records review, October 2026. Shows Edison International's $2 million direct gift; its utility affiliate separately sent $2 million to CalChamber's Business PAC.1

That is where Proposition 45 enters 1. The measure would clip review under the California Environmental Quality Act, the state's permitting law, and its funders map onto the AI buildout: Sergey Brin's committee gave $10 million, PG&E $2.3 million, Edison International+0.83% — Edison International, up 0.83 percent today $2 million directly plus $2 million from its utility affiliate to the Chamber of Commerce's PAC, California Resources Corp. $1 million while it builds a 275-megawatt data-center campus, and Prologis+0.54% — Prologis, up 0.54 percent today $500,000 for its five planned San Jose data centers 1. Faster approvals raise the value of projects PG&E and its partners already hold.

Cheap permits for itself, expensive grids for others

The bottleneck PG&E wants unlocked on one side, it wants priced high on the other. In October 20 testimony it valued a San Francisco municipal takeover at $22.5 billion, against the city's $3.4 billion estimate, including $7.6 billion in business severance damages 3. Same commission, same logic: capex PG&E controls is valuable; review of it is friction.

Whether data centers actually qualify under the measure is unsettled: the Yes campaign says they are excluded, independent legal experts are divided, and UC Berkeley's Eric Biber calls the measure's pro-approval language a thumb on the scale 5. For investors, that uncertainty is the point: a Yes vote is a cheap option on faster data-center permitting in a state PG&E serves. Watch November 3 and the CPUC docket, then judge whether PCG's regulator-dependent growth is cheap 2.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading EIX

Reader comments

0 comments

    Power

    Elementl signs Korean funding deal for Ohio reactors as GE Vernova counts on a 116GW gas backlog

    Korean private capital has signed a preliminary deal worth up to $750 million to fund Elementl Power's reactors in Ohio and beyond before any customer signs. GE Vernova reports Q3 on October 28, and its gas backlog, not nuclear, is what pays.

    Power

    CMS Energy earns $1.44 adjusted while funding the fight against Michigan's utility money ban

    Michigan votes on November 3 on Proposition 2, which would bar utilities from giving to the officials and commissioners who set their rates. CMS Energy, which needs more than $24 billion of supply-plan spending approved, put $50,000 into defeating it the same quarter it wrote off $456 million.

    Power

    Amazon agrees to fund and buy power from 12 small reactors at AEP's retired Indiana coal plant

    AEP, X-energy and Amazon signed agreements on October 19 to study twelve small reactors at a retired Indiana coal plant, with Amazon paying the development bills and, if it is built, buying the output under a contract meant to cover the plant's full costs. AEP reports the morning of October 28; the thing to listen for on the call is how much of the build customers like Amazon are paying for.

    Power

    LG Energy Solution's storage bet: 50 GWh of supply waits on 2 GWh of announced demand

    The Korean battery maker's marquee European demand news is a non-binding MOU worth about 4% of the 50 GWh North American capacity it is building, while lithium contracts and a 140 GWh backlog show where the real commitments sit. Q3 earnings on November 3 test whether the announced orders convert.

    Power

    CenterPoint's answer to Harris County: a $70.7 billion grid and a $5 billion promise

    The Houston utility's third-quarter filing raises its 10-year capital plan by $4.0 billion, lifts 2026 guidance, initiates 2027 and repeats a $5 billion savings promise, the company's first on-record answer to the county's fight over who pays for AI-driven grid growth. The demand is verifiable; the savings are a forecast that three dates will test.

    Power

    Banks' $50 targets bet on FirstEnergy's 4.3 GW AI load; Pennsylvania and Ohio decide who pays

    HSBC and BMO just re-rated FirstEnergy on AI data-center load, but Pennsylvania regulators rejected its billing plan 3-2 and Ohio's Senate race has turned its money into a campaign weapon. The demand is observable; who keeps the margin is not.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.