Evergy Sees $4 Billion of Generation Behind a Deal Digital Realty Has Not Signed
A 1.4-gigawatt letter of intent at a former Kansas ammunition plant is the durable news in a weather-inflated quarter. The funding decisions that come first are a Missouri rate order in December and a new capital plan in February; the contract is not expected until the first half of 2027.
Richard Tangthree-minute read
Shares of Evergy+0.57% — Evergy, up 0.57 percent today, the electric utility for Kansas and Missouri, touched an all-time high of $88.65 on November 5, 2026, on a quarter that, by the company's own arithmetic, leaned on the weather 1. Adjusted earnings were $2.58 a share against $2.03 a year earlier, and chief financial officer Bryan Buckler put $0.46 of the increase down to weather, demand and large-customer revenue 23. The durable news is a letter of intent with Digital Realty−0.23% — Digital Realty, down 0.23 percent today, the data-center developer, for 1.4 gigawatts at the former Sunflower Army Ammunition Plant in Kansas, beside the customer's existing project 2.
The letter is the headline; the contracts are smaller
The electric service agreement behind the letter is not expected until the first half of 2027, and the roughly $4 billion of generation Evergy anticipates for it, most of it utility-owned, sits outside the five-year capital plan 23. What Evergy signed this quarter was amendments adding about 110 megawatts to existing agreements, with 140 more contingent on a transmission study due by year-end 23.
A minimum bill pays for capacity before it is drawn
Five executed agreements carry about 2.6 gigawatts of eventual peak load on 15-to-17-year terms with binding minimum bills: a customer pays for reserved capacity whether or not it draws it 23. Those customers draw 350 to 400 megawatts today; the first bar below is power actually flowing, and the rest is ramp still to come 23. That minimum bill is what lets a regulated utility finance plants for load that does not yet exist, and management says the Digital Realty expansion alone could add about two percentage points to long-term rate-base growth 4.
Evergy's signed load grows about sixfold by 2030
The 1.4 GW Digital Realty letter is not in these bars
- Signed large-customer peak load
- Estimate
Data
| Signed large-customer peak load | |
|---|---|
| Today | 375 MW (350–400 MW) |
| 2030 (estimate) | 2,250 MW |
| After 2030 (estimate) | 3,100 MW |
The funding decisions come before the contract
Evergy is already selling at-the-market equity, shares issued gradually into the market, with about $700 million priced this year against $700 million to $900 million a year through 2029 3. Evergy Missouri West, one of its two Missouri utilities, asked the Missouri Public Service Commission on November 3 for about $182.6 million more a year, roughly $17.25 a month on a typical residential bill; interventions close on November 25 5.
Expected revenue from two data-center customers trims that request by about $61 million, the same ratepayer-protection fight we watched Florida's regulators force on Duke Energy 6. Missouri Metro, the other Missouri utility, expects its rate order in December, and Kansas regulators rule by mid-2027 on a tariff rewrite adding non-refundable advance payments from large customers 23. Public hearings before the Missouri Public Service Commission on a new gas plant near St. Joseph, which our earlier piece tied to this build, open on November 16 7.
Evergy's capital spending has outrun operating cash in six of the last eight quarters
- Capital spending
- Operating cash flow
Data
| Capital spending | Operating cash flow | |
|---|---|---|
| Q4 '24 | $0.51B | $0.4B |
| Q1 '25 | $0.59B | $0.45B |
| Q2 '25 | $0.63B | $0.32B |
| Q3 '25 | $0.71B | $0.94B |
| Q4 '25 | $0.87B | $0.33B |
| Q1 '26 | $0.85B | $0.36B |
| Q2 '26 | $0.96B | $0.35B |
| Q3 '26 | $0.9B | $0.99B |
Digital Realty has promised that ratepayers will not pay
Digital Realty's chief executive, Andrew Power, told his own October call that the company is developing the Sunflower site in De Soto, Kansas, and landed one of the largest leases in its history in Kansas City this year 8. His company has signed the Ratepayer Protection Pledge, whose commitment is that the cost of infrastructure for new data-center demand "should not be borne by residential customers and small businesses" 8.
If Digital Realty signs next year, Evergy collects on those minimum bills for power it finances now; if it walks, the growth case rests on a pipeline that is still letters, and the equity is already sold. The next marker is the February capital-plan update, when the $4 billion either enters the numbers or does not 23.