Power

Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

Vincent JiangVincent Jiangthree-minute read
Share
Rex Geveden speaking at a podium at NASA's Goddard Space Flight Center in 2006
1 / 6Slide 1 of 6
Rex Geveden, photographed in June 2006 at NASA's Goddard Space Flight Center, when he was NASA's associate administrator. He is now chief executive of BWX Technologies.

On Friday, November 6, Tennessee's Department of Economic and Community Development signed the grant agreement behind BWX Technologies'−0.77% — BWX Technologies, down 0.77 percent today $714.5 million expansion of its Jonesborough plant, which makes high-purity depleted uranium metal for the National Nuclear Security Administration 1 2 3. The project adds 181 jobs, more than doubling the company's Washington County workforce, and construction has already begun on the 325,000-square-foot facility 1 2 3.

One payer is named, one is not

Here is what the agreement settles and what it does not. The federal side has a paying customer: a 10-year, $1.6 billion NNSA contract awarded in September 2025 to design, license, build and operate the plant, which is expected to turn out up to 300 metric tons of the material a year and to become the federal government's only active HPDU site 1 2.

A one-gram sample of depleted uranium metal sealed in an ampoule
A one-gram sample of depleted uranium metal. The Jonesborough plant is designed to turn out up to 300 metric tons of the material a year.范皓程 via Wikimedia Commons

The state's share is unpriced. The grant comes from Tennessee's Nuclear Energy Fund, $95 million in total, and TNECD says the exact dollar value will be posted on the fund's transparency site within 30 days 1 3.

The other half has no customer yet

BWXT runs two capital programs with different payers. The quarter just reported shows the difference. Q3 bookings fell to $538 million from $2.25 billion a year earlier, with government bookings of $323 million against $2.09 billion last year; backlog still sits at $8.56 billion, of which $6.48 billion is government 4.

Four days before Tennessee signed, BWXT launched a $500 million offering of senior unsecured notes due 2034, alongside cash tender offers for its 4.125% notes due 2028 and 2029 5 6. Retiring near-dated paper is housekeeping. But it extends the maturity wall while the commercial program, reactor equipment and advanced-reactor fuel, waits on orders: the first US new-build equipment order has slipped toward 2027, and Q3 commercial bookings of $215 million are thin against a $2.07 billion commercial backlog and a 25% jump in commercial revenue to $314.2 million 4.

New orders collapsed in Q3 as government bookings fell to $323M from $2,086M

Government bookings fell $1.76B year over year

0M500M1,000M1,500M2,000M2,500MGov Q3 '252,086.1MGov Q3 '26323MCommercial Q3 '25159.3MCommercial Q3 '26215.2M
Data
Value
Gov Q3 '252,086.1M
Gov Q3 '26323M
Commercial Q3 '25159.3M
Commercial Q3 '26215.2M
Segment bookings, three months ended September 30, in millions of dollars, from BWXT's Q3 2026 earnings release. Q3 2026 compared with Q3 2025.4

Performance is not the problem; funding is

The quarter itself was strong. Revenue rose 10% to $953.0 million, non-GAAP EPS of $1.26 beat estimates, and management tightened FY26 EPS guidance to $4.72-$4.77 with free cash flow of $350-$360 million 4 7. The tension is not performance; it is who funds the build-out. If NNSA and Tennessee carry Jonesborough, the $500 million of 2034 notes is the bet on the commercial half, where orders shrank 4 7. If BWXT must fund part of the $714.5 million itself, the notes are bigger than they look 4 7.

Revenue has grown year over year in every quarter for two years

Revenue grew year over year in all ten quarters

$600M$700M$800M$900M$1,000MQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26$952.97M
Data
Revenue
Q2 '24$681.47M
Q3 '24$671.96M
Q4 '24$746.27M
Q1 '25$682.26M
Q2 '25$764.04M
Q3 '25$866.29M
Q4 '25$885.84M
Q1 '26$860.22M
Q2 '26$901.63M
Q3 '26$952.97M
Quarterly revenue in millions of dollars, Q2 2024 to Q3 2026, from BWX Technologies' quarterly figures in its SEC filings, retrieved 10 November 2026. Revenue was up 10% year over year in Q3 2026.9

The grant's price, the air permit and January's guidance are ahead

Jonesborough neighbors also showed up to the wrong meeting. At a November 5 air-permit session, residents said they had not been properly notified; the state cap on the site's emissions sits at 94 pounds a year, and TDEC must still approve the permit 8. Watch two dated readings: the grant's dollar value on the Nuclear Energy Fund transparency site, due within 30 days of November 6, and the air permit decision 8.

The next proof arrives with the 2027 guidance in January: whether the robust bid pipeline CEO Rex Geveden described converts to firm awards, or the notes keep funding a customer that has not signed 4.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BWXT

Reader comments

0 comments

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.

    Power

    PPL's Blackstone venture signs first 2GW data-center power deal