Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

Richard TangRichard Tangthree-minute read
Share
Constellation Energy Chairman, President and CEO Joe Dominguez speaks during a conversation at CERAWeek 2026
1 / 6Slide 1 of 6
Constellation Chairman, President and CEO Joe Dominguez, right, in conversation at CERAWeek 2026. On the company's third-quarter earnings call on Monday he said utilities and grid operators massively overestimated data-center demand.

Constellation Energy's−2.93% — Constellation Energy, down 2.93 percent as of its last quote CEO said on Monday's third-quarter call that utilities and grid operators "did not do a good job estimating the real number of data centers," and that the error "resulted in a massive overestimation" 1. On the same call the company raised its 2026 adjusted operating earnings guidance for a second time this year, to $12.50 to $12.80 per share 1.

Vistra's−1.53% — Vistra, down 1.53 percent today chief executive gave the same diagnosis on Friday, blaming speculative developers for overstated grid-queue numbers, especially in ERCOT 1. The AI power complex repriced on Tuesday: Constellation fell 3.87%, Vistra 3.06%, and GE Vernova−3.53% — GE Vernova, down 3.53 percent today 7.4% after SoftBank revised equipment procurement for its US data center projects and booked a $3.7 billion charge 12.

GE Vernova took the worst of Tuesday's repricing, down 7.4%

-8%-6%-4%-2%0%Constellation-3.87%Vistra-3.06%GE Vernova-7.4%
Data
Value
Constellation-3.87%
Vistra-3.06%
GE Vernova-7.4%
One-day share-price moves, Tuesday, November 10, 2026. Constellation and Vistra fell after their chief executives called grid-queue data-center demand overstated; GE Vernova fell after SoftBank revised equipment procurement for its US data center projects and booked a $3.7 billion charge. Sources: Yahoo Finance [1]; Reuters [2].1,2

If the queues are padded, who pays

If Dominguez is right, the losses should land on whoever sized plants, debt and rate plans against those queue numbers: the developers holding placeholder projects, the equipment makers counting on their orders, and possibly the ratepayers behind the biggest utility buildout plans. GE Vernova, which sells the turbines, is the clearest named exposure so far 2.

Constellation's multiple has already come down from 38x to 23x, with room to a 16x floor

010203040October 2025 peakToday (Nov 2026)3-year averageDec 2023 low1623
Data
Forward P/E
October 2025 peak38
Today (Nov 2026)23
3-year average26
Dec 2023 low16
Constellation Energy (CEG) forward (next-twelve-month) price-to-earnings ratio, in multiples, as reported via TIKR; three-year average and December 2023 low shown for context. Source: TIKR data via Yahoo Finance [1].1

The incumbents with power already sold

Both CEOs can afford the diagnosis because their output is contracted. Constellation signed about 4,560 megawatts of new long-term agreements since its last report, more than 8,500 megawatts this year running into the 2040s, and expects about 45% of its clean baseload fleet hedged by 2032 1. Vistra has signed over 4 gigawatts of long-term power purchase agreements and lifted its 2027 adjusted EBITDA guidance to $7.7 to $8.5 billion 1. A padded queue hurts projects waiting for demand; it does not change what a signed contract pays.

The challenger betting the queues were right

Venture Global, the LNG exporter, is going the other way. It reported frame agreements with GE Vernova and Baker Hughes for up to 16 power islands on its Louisiana sites, expects to begin delivering compute capacity in late 2028 and to scale to about 5 gigawatts by the end of 2031, and describes itself as a potential vertically integrated AI utility 3. Those are equipment frame agreements, not data center customer contracts; that is a bet the demand Dominguez calls overstated shows up anyway.

What would settle it

Watch two tests. FERC is expected to rule in the first half of 2027 on large loads sited next to power plants, which could make the next deals easier or harder to sign 1. And watch whether Venture Global converts any of those 16 power islands into signed compute customers before the turbines ship 3. Capital should follow signed buyers, not queue positions; the FERC ruling and Venture Global's first contract will tell us which side the market has to believe.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading CEG

Reader comments

0 comments

    Power

    Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

    Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.

    Power

    PPL's Blackstone venture signs first 2GW data-center power deal

    The first proof PPL can turn a 35GW request queue into contracts. The case for the stock now rests on that funnel converting, and on large-load tariffs holding as voters turn on data centers.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.