TSMC contracts every kilowatt-hour of Taiwan's largest offshore wind farm, 73 turbines, for 30 years
The 73-turbine Hai Long project finished construction on November 17 with its full gigawatt contracted to the chipmaker from 2027, days after TSMC agreed to fund its own grid in Arizona. Electricity is now the AI buildout's binding input, and TSMC is buying certainty on both sides of the Pacific.
Richard Tangtwo-minute read
All 73 turbines of Hai Long, Asia's largest single offshore wind development, are now connected to the grid off Taiwan's central coast 1. Every kilowatt-hour of the project's more than a gigawatt of capacity is contracted to TSMC+0.55% — TSMC, up 0.55 percent today from full commercial operation in 2027 1. I think this is the clearest sign yet of where the AI buildout's real constraint sits: not lithography, not packaging, but electricity and the terms on which anyone will build it. In one week, TSMC locked dedicated green power at home and agreed in Arizona to fund its own grid 2.
The demand the power has to feed
The load is not a forecast. TSMC's October revenue rose nearly 60% year over year on AI and advanced-process demand 3. The foundry expects to spend $60 billion to $64 billion this year while ramping 2nm production 3. Hai Long's annual output is at least four billion kilowatt-hours 1. That is about what a million Taiwanese households use in a year, and it all flows to one customer 1. This is what securing the bottom of the supply chain looks like when the bottleneck moves downstream to the wall socket.
TSMC's revenue has more than doubled since late 2023, and the power load follows it
Third-quarter revenue was up 44 percent from a year earlier
Data
| Revenue | |
|---|---|
| Q4 '23 | $20.36B |
| Q1 '24 | $18.53B |
| Q2 '24 | $20.7B |
| Q3 '24 | $24.05B |
| Q4 '24 | $26.73B |
| Q1 '25 | $25.42B |
| Q2 '25 | $31.95B |
| Q3 '25 | $32.48B |
| Q4 '25 | $33.45B |
| Q1 '26 | $35.43B |
| Q2 '26 | $39.85B |
| Q3 '26 | $46.89B |
The 30-year contract is what made Hai Long buildable
Mitsui, Northland Power and Gentari, the project's owners, put together a record NT$117 billion in project financing in 2023 and added NT$55 billion this year, from 35 lenders 1. The reason a bank will fund a wind farm on that scale is a single investment-grade buyer taking the volume risk off the table under a 30-year offtake agreement 14. For the developers, Hai Long is now a contracted revenue line rather than a merchant bet 4. They did the decade of work between a windy strait and a chip fab's substation, and they deserve the return they contracted for.
Taiwan's next buildout will need the same answer
Taiwan wants nearly 30 GW of offshore wind by 2039, with the next capacity allocations opening from 2027 1. Each round will have to answer the same question Arizona regulators settle in December, when they rule on a 25-year filing that makes TSMC pay for every new plant and wire behind its Phoenix fabs 2.
On one side of the Pacific the chipmaker funds its own grid; at home its contracted wind farm gives it a dedicated line while the island's grid and financing carry the rest. TSMC has now answered the power question on both sides of the Pacific, and the builders who make that answer bankable are the ones to watch.
Hai Long's 1 GW joins about 5 GW installed, against a 30 GW goal for 2039
Hai Long's gigawatt is in; the 2039 target still needs far more
- Estimate
Data
| Value | |
|---|---|
| Hai Long, completed | 1 GW |
| Installed today | 5 GW |
| 2039 target (estimate) | 30 GW |