Power

NRG Energy sells six gas plants to LS Power for $4 billion, pricing one Texas plant at $1,400 per kilowatt

The 8x cash offer implies about 40% more for the running Texas plant than NRG says new build costs. Neither the deal filing nor the 2027 guidance, which still counts the six plants, values the 20 GW NRG keeps.

Vincent JiangVincent Jiangthree-minute read
Share
Robert Gaudette, chief executive of NRG Energy, in glasses and a navy suit against a white background
Robert Gaudette, chief executive of NRG Energy, which is selling six gas plants to LS Power for $4 billion in cash.

Eight times EBITDA, all cash, and an offer NRG says it did not seek

LS Power approached NRG Energy+1.86% — NRG Energy, up 1.86 percent today, the Houston-based generator listed on the NYSE, with an offer the seller says it was not seeking: $4.0 billion in cash for six gas plants totaling about 4.9 GW across Texas, New York and New England, signed on November 9, 2026, a deal The Inference covered on November 12 12. The price is 8.0 times the plants' expected 2027 adjusted EBITDA (earnings before interest, tax, depreciation and amortization) of about $500 million, with closing set for the second quarter of 2027 pending antitrust, Federal Energy Regulatory Commission and New York state approvals 13.

Jack County prices at $1,400 a kilowatt, 40% over new build

The sharpest number belongs to one plant. Jack County, a 1.2-GW Texas unit that captures exhaust heat to drive a second turbine, carries an implied value of about $1,400 per kilowatt, against the just-above-$1,000-per-kilowatt cost of the 1.5 GW of new Texas gas NRG is developing, in the words of CEO Robert Gaudette 1. Averaged across all six plants, the price is about $820 per kilowatt, below new-build cost; only Jack County carries the premium 4.

Jack County's implied value runs close to 40% above new-build cost

Operating Texas gas prices close to 40% above replacement cost

  • Estimate
$0/kW$500/kW$1,000/kW$1,500/kWJack County, implied$1,400/kWanchor of the $4B saleNew Texas build (NRG est.)$1,000/kWSix-plant sale average$820/kW
Data
Value
Jack County, implied$1,400/kW
New Texas build (NRG est.) (estimate)$1,000/kW
Six-plant sale average$820/kW
Implied values from NRG's November 9, 2026, statements; the average is $4.0B divided by 4.9 GW. Sources: Utility Dive; DatacenterFeed.1,4

Turbine shortages are why an existing plant outprices a new one

The premium has a mechanism, and it is scarcity. Gaudette said NRG's pipeline of data-center projects already exceeds the turbine allocations and construction capacity reserved under its development agreement with GE Vernova−0.80% — GE Vernova, down 0.80 percent today, the turbine maker, and Kiewit, a contractor: 5.4 GW reserved, demand past it 1. GE Vernova told its own investors it is now taking gas-turbine reservations for delivery in 2032, with 122 GW of turbine capacity under contract 5. A buyer that wants capacity this decade cannot order it. It can only buy something that already runs, and that scarcity is what the extra $400 per kilowatt buys 5.

The premium stops at the plants sold

After closing, NRG keeps about 20 GW: 10 GW in ERCOT, the Texas grid, and 10 GW in PJM, the Mid-Atlantic and Midwest market, including the entire PJM fleet and CPower, its demand-response business, from the roughly 13-GW portfolio bought from LS Power in a $12-billion deal that closed in January 367. Neither the sale filing nor the 2027 guidance, $5.5–6.0 billion of adjusted EBITDA, which still counts the six plants, puts a value on what NRG keeps 23. The proceeds are earmarked: $2 billion to debt, $1 billion to buybacks, $1 billion held for growth 1.

Half the $4 billion pays down debt, a quarter funds buybacks

  • Debt repayment$2B50%
  • Share buybacks$1B25%
  • Held for growth$1B25%
Data
SliceValueShare
Debt repayment$2B50%
Share buybacks$1B25%
Held for growth$1B25%
Uses of the cash proceeds as NRG described them when the sale was announced, in $ billions. The sale has not closed, so the proceeds are not yet received. Source: Utility Dive.1

LS Power is assembling an 11.5 GW gas fleet

The buyer is the one paying the scarcity price. LS Power chief executive Paul Segal said facilities "already built, permitted, and interconnected deliver that power today" 7. With a separate 4.4-GW purchase from Constellation also pending, the six NRG plants lift LS Power's gas fleet from 2.2 GW to 11.5 GW 67.

Two pending deals take LS Power's gas fleet from 2.2 to 11.5 GW

NRG and Constellation supply 9.3 of the 11.5 GW

2.2 GW 19.1%Held today4.9 GW 42.6%NRG plants, pending4.4 GW 38.3%Constellationplants, pending
Data
PartGas-fired capacity (GW)Share
Held today2.2 GW19.1%
NRG plants, pending4.9 GW42.6%
Constellation plants, pending4.4 GW38.3%
Gas-fired capacity in GW; both acquisitions are announced but not closed. Sources: Power Engineering; POWER Magazine.6,7

The replacement plant is still unsigned

NRG's replacement earnings are one $3.2 billion, 1.2-GW Texas plant for an unnamed AI hyperscaler: a contract of at least 15 years with an investment-grade guarantee, about $500 million of expected annual adjusted EBITDA, first power in late 2029, and signed agreements promised by year-end, which The Inference covered on November 10 3.

December decides whether the Texas plant can be built

The calendar around that promise is crowded: ERCOT's report on which large loads keep their grid places is due December 10, a December 17 state commission meeting is the earliest the Texas permit pause on data centers could lift, and the connection queue under review runs above 474 GW 38. Gaudette's own words frame the exposure: ERCOT prices are depressed and 2027 looks weak 1.

Watch the year-end signature, the December dates, the second-quarter close, and the post-sale guidance that finally prices the $500 million of EBITDA leaving with the plants 3.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NRG

Reader comments

0 comments

    Power

    PG&E signs 20-year Avantus contracts for 800 MW of solar and storage, pending CPUC approval

    The contracts still need approval from the California Public Utilities Commission, and PG&E's third-quarter filing shows the utility's operating cash running $3.4 billion behind its capital spending over the first nine months of 2026. Avantus's backers at KKR and EIG take the construction risk; the 20-year payment obligation lands on PG&E, its lenders and California ratepayers.

    Power

    Dominion Energy sells $1.2 billion of bonds at 5.25% and 5.95% as Virginia weighs NextEra's $67 billion deal

    The pricing was disclosed the day before Virginia opened hearings on NextEra's $67 billion takeover, where the companies refused a rate freeze and promised a credit upgrade. The coupons are what the AI build-out costs without the merger, and a January ruling decides who pays them.

    Power

    Evergy hit a record $89.69 as Missouri ratepayers packed hearings against its $4.5 billion gas plant

    Residents' testimony is now part of the official record at the Missouri Public Service Commission, the same regulator holding Evergy's pending $229.5 million rate increase. The shares closed at a record $89.69 on November 16, the day the hearings began.

    Power

    TSMC contracts every kilowatt-hour of Taiwan's largest offshore wind farm, 73 turbines, for 30 years

    The 73-turbine Hai Long project finished construction on November 17 with its full gigawatt contracted to the chipmaker from 2027, days after TSMC agreed to fund its own grid in Arizona. Electricity is now the AI buildout's binding input, and TSMC is buying certainty on both sides of the Pacific.

    Power

    Global X funds now hold 5.08% of Oklo and 5.61% of NuScale, a bid that moves with ETF flows

    The Street's average Oklo target has collapsed from $117 to $56 while the ETF house behind the sector's theme funds quietly crossed the 5% line in both reactor names. The bid under this theme is turning mechanical, and the same channel can reverse it.

    Power

    PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill

    A 143-acre Pequea Township purchase anchors 16.4 miles of new wires feeding the Lancaster AI Hub East project. Who pays for the shared parts, the data center's owners or the utility's 1.5 million customers, now sits with Pennsylvania regulators, and the governor has asked to join the case.