Power

Evergy hit a record $89.69 as Missouri ratepayers packed hearings against its $4.5 billion gas plant

Residents' testimony is now part of the official record at the Missouri Public Service Commission, the same regulator holding Evergy's pending $229.5 million rate increase. The shares closed at a record $89.69 on November 16, the day the hearings began.

Richard TangRichard Tangthree-minute read
Share
Two gas turbine units, a step-up substation and a transmission tower at a gas-fired generating plant
Two gas turbines at a gas-fired generating plant of the kind Evergy proposes to build in Buchanan County, Missouri. Evergy's project would be 1,400 megawatts.

Two nights of packed Missouri Public Service Commission hearings this week put Evergy's+0.11% — Evergy, up 0.11 percent today proposed $4.5 billion gas plant in Buchanan County before the state board that approves new plants and sets electric rates 1. The constraint on the Kansas City region's AI power buildout is now regulatory approval, not demand or equipment, and residents asked the board to deny the 1,400-megawatt project 1.

"We should not be asked to pay the bills for these massive data centers," Cody Boston of the KC Data Center Watch Dog group told the hearing 1. Evergy's shares closed at an all-time high of $89.69 on November 16, the day the first hearing filled 2. A record close and two full rooms are opposite bets on the same regulator.

Evergy says the plant clears without the data centers

Evergy's defense is on the record. Chief customer officer Chuck Caisley said the plant "would be built even without the data centers," and that data centers already pay 20% more than regular customers and fund their infrastructure upgrades upfront 1. His benchmark for future bills is inflation, about 3.5% this year 1.

The News-Press account of the same hearing has him citing 2.5% a year, and Marke told the room he does not see how even that holds 3. The Missouri Office of Public Counsel, the state's ratepayer advocate, counts differently: its Geoff Marke called the plant "an additional investment to serve five customers," two of them the Google and Meta−0.64% — Meta, down 0.64 percent today data centers rising near Smithville 3. That testimony is now part of the official case record 4.

Aerial view of a data center roof with rows of cooling towers, chillers and backup generators
The load behind the ask: rows of cooling towers and backup generators on a data center roof. Geoff Marke of the Missouri Office of Public Counsel told the hearing the Buchanan County plant would be "an additional investment to serve five customers," two of them the Google and Meta data centers rising near Smithville.Rsparks3

The build already outruns the cash it generates

The filings show what is at stake. Capital spending exceeded operating cash flow from the fourth quarter of 2025 through the second quarter of 2026, and the third quarter's recurring cash spike is the only period in which cash catches up 5.

The recovery machinery sits with the same commission: Evergy Missouri West, Evergy's Missouri-regulated arm serving St. Joseph and western Missouri, filed on November 3 for $229.5 million in annual revenue 6. That comes on top of the customer construction cash we reported November 16 6.

Expected data-center revenue trims the request by $61 million 6. Ratepayer dollars fund the build, contracted data-center revenue offsets part of the ask, and the growth that remains accrues to shareholders.

Evergy's capex outran operating cash in three of the last four quarters

Only the recurring third-quarter cash spike lets operating cash catch up

  • Capital spending
  • Operating cash flow
$0.2$0.4$0.6$0.8$1Q1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26Recurring seasonal cash spike
Data
Capital spendingOperating cash flow
Q4 '23$0.68$0.43
Q1 '24$0.62$0.32
Q2 '24$0.68$0.32
Q3 '24$0.53$0.95
Q4 '24$0.51$0.4
Q1 '25$0.59$0.45
Q2 '25$0.63$0.32
Q3 '25$0.71$0.94
Q4 '25$0.87$0.33
Q1 '26$0.85$0.36
Q2 '26$0.96$0.35
Q3 '26$0.9$0.99
Evergy quarterly figures from its SEC filings, US dollars in billions.5

North Carolina just showed what harder terms look like

On the day Evergy set its record, the North Carolina Utilities Commission approved a rate plan for Duke Energy+0.26% — Duke Energy, up 0.26 percent today, the utility serving the Carolinas 7. Its allowed return on equity, the profit margin the regulator permits, came in at 9.8%, below what Duke sought 7. Large customers who leave early now pay a stranded-generation charge of about $67,000 per megawatt-year, and data centers are 92% of the large load Duke has signed there 7.

If Missouri approves the plant as filed, the load is real and the region gets its megawatts on Evergy's terms. The durable version is North Carolina's, where whoever signs for the gigawatts carries the cost of leaving 7. Interventions in the rate case close November 25 6, and Evergy expects new rates in October 2027 6. A record price is a bet that Missouri writes easier terms, and two rooms of ratepayers just testified on the other side of that bet.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading EVRG

Reader comments

0 comments

    Power

    PG&E signs 20-year Avantus contracts for 800 MW of solar and storage, pending CPUC approval

    The contracts still need approval from the California Public Utilities Commission, and PG&E's third-quarter filing shows the utility's operating cash running $3.4 billion behind its capital spending over the first nine months of 2026. Avantus's backers at KKR and EIG take the construction risk; the 20-year payment obligation lands on PG&E, its lenders and California ratepayers.

    Power

    NRG Energy sells six gas plants to LS Power for $4 billion, pricing one Texas plant at $1,400 per kilowatt

    The 8x cash offer implies about 40% more for the running Texas plant than NRG says new build costs. Neither the deal filing nor the 2027 guidance, which still counts the six plants, values the 20 GW NRG keeps.

    Power

    Dominion Energy sells $1.2 billion of bonds at 5.25% and 5.95% as Virginia weighs NextEra's $67 billion deal

    The pricing was disclosed the day before Virginia opened hearings on NextEra's $67 billion takeover, where the companies refused a rate freeze and promised a credit upgrade. The coupons are what the AI build-out costs without the merger, and a January ruling decides who pays them.

    Power

    TSMC contracts every kilowatt-hour of Taiwan's largest offshore wind farm, 73 turbines, for 30 years

    The 73-turbine Hai Long project finished construction on November 17 with its full gigawatt contracted to the chipmaker from 2027, days after TSMC agreed to fund its own grid in Arizona. Electricity is now the AI buildout's binding input, and TSMC is buying certainty on both sides of the Pacific.

    Power

    Global X funds now hold 5.08% of Oklo and 5.61% of NuScale, a bid that moves with ETF flows

    The Street's average Oklo target has collapsed from $117 to $56 while the ETF house behind the sector's theme funds quietly crossed the 5% line in both reactor names. The bid under this theme is turning mechanical, and the same channel can reverse it.

    Power

    PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill

    A 143-acre Pequea Township purchase anchors 16.4 miles of new wires feeding the Lancaster AI Hub East project. Who pays for the shared parts, the data center's owners or the utility's 1.5 million customers, now sits with Pennsylvania regulators, and the governor has asked to join the case.

    Subscribe to TheInference for free