Vertiv jumped 16% on an order number with no dollar value

Vertiv said organic orders more than doubled, then said it will stop publishing the figures that would show whether that growth is real megawatts or price inflation in the queue. February's annual report is the check.

Richard TangRichard Tangtwo-minute read
Share
Vertiv chief executive Giordano Albertazzi
1 / 6Slide 1 of 6
Vertiv chief executive Giordano Albertazzi, whose company doubled its organic orders in dollars and then retired the orders disclosure.

On October 28 Vertiv+6.53% — Vertiv, up 6.53 percent today, the data center power and cooling equipment maker, reported third-quarter sales of $4.31 billion, up 61%, and said organic orders more than doubled from a year earlier 1234. The shares jumped 16% 1234. But the order figure carried no dollar value, no book-to-bill ratio and no delivery schedule, and management said on the call it will not publish orders data going forward 1234. The next hard number is the year-end backlog in the annual report, due around February, last disclosed at $15.0 billion 23.

Vertiv rose on a percentage, then retired the yardstick.

Vertiv's sales accelerated from 19% growth in Q3 2024 to 61% in Q3 2026

2B3B4B5BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '2661% yoy
Data
Net sales
Q3 '242.07B
Q4 '242.35B
Q1 '252.04B
Q2 '252.64B
Q3 '252.68B
Q4 '252.88B
Q1 '262.65B
Q2 '263.27B
Q3 '264.31B
Quarterly net sales, $ billions. Q3 2026 reported October 28, 2026. Source: Vertiv quarterly figures from its SEC filings [5].5

A doubling of dollars is not a doubling of megawatts

The figure being rewarded is a percentage in a rising-price market. Cushman & Wakefield puts the all-in cost of a modern US or Canadian data center at $17.6 million per megawatt, up 21% since late 2024, with switchgear up 60% since December 2021 and transformer lead times running as long as 113 weeks 3.

An order book that doubled in dollars could therefore be flat in megawatts of shipped equipment, and Vertiv has removed the quarterly data that would settle the question. The company's own reporting calendar now makes February the only date with evidence.

Data center electrical gear has risen far faster than general inflation since 2021

0204060Switchgear60Copper46Generators, motors33Cooling equipment32Transformers29
Data
Value
Switchgear60
Copper46
Generators, motors33
Cooling equipment32
Transformers29
Percent increase in data center equipment costs from December 2021 to early 2026. Source: Cushman & Wakefield data via DC Market Insights [3].3

What the cash and the customers say

Two other disclosures cut both ways. Customer prepayments reached $4.12 billion at September 30, more than double the end-2025 level, which is hard to square with buyers hedging on cancellations; but the quarterly inflow slowed to $490 million against $652 million of adjusted free cash flow 2. And the largest buyers are constrained by delivery, not budget: Microsoft+0.09% — Microsoft, up 0.09 percent today said the same evening that its $45.2 billion capex quarter came in below plan because third-party capacity arrived late 3. Vertiv's backlog coverage runs 12 to 18 months 24.

Customer prepayments have more than doubled since the end of 2025

$0B$1B$2B$3B$4B$5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$4.12B, more than double end-2025
Data
Customer prepayments
Q4 '23$0.64B
Q1 '24$0.74B
Q2 '24$0.89B
Q3 '24$1.02B
Q4 '24$1.06B
Q1 '25$1.1B
Q2 '25$1.26B
Q3 '25$1.13B
Q4 '25$1.82B
Q1 '26$2.46B
Q2 '26$3.63B
Q3 '26$4.12B
Customer prepayments, $ billions, by calendar quarter. Source: Vertiv quarterly figures from its SEC filings [5].5

February is the check

Vertiv raised its 2026 guidance to $14.45 billion to $14.85 billion in sales and closed at $232.50 on October 30, near 30 times forward earnings 12. The trade turns on one unresolved question: whether the doubled order dollars are doubled megawatts or a record-priced queue with a two-year delivery tail.

The $15.0 billion end-2025 backlog and its roughly 2.9 book-to-bill set the baseline 3; the February annual report will show whether orders kept pace. Until then the only order number investors can verify is the one management stopped publishing.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading VRT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CoreWeave's Q4 interest bill of up to $1.15 billion closes in on its full-year adjusted operating income

    Third-quarter revenue of $3.66 billion beat the company's own guidance and lifted the backlog to $132.5 billion, which answers the demand question for now. The same filing names who funds the next stretch of the build: customers, convertible holders and new shareholders.

    Data Center

    TeraWulf sues its host town of Lansing over public records

    The petition lands a week before Lansing votes on a local law that would prohibit data centers outright, the use TeraWulf's unleased 320 MW Lake Hawkeye campus depends on. Roughly 2.1 GW of the company's controlled capacity has no tenant, and WULF holders own that risk at around $12.

    Data Center

    Rackspace triples capex to $104 million with $92 million of fresh stock while AMD commits to buy nothing yet

    The filing will not say how much of the quarter's $104 million of capital spending went to the AMD GPU build, and the AMD agreement commits the chipmaker to nothing up front: for an agreed deployment it would buy only residual unsold capacity, capped per deployment. Rackspace bridged the quarter with $92 million of newly issued stock while the cloud business that must pay for it shrank 17.2%.

    Data Center

    Fermi bets its stalled campus on three refurbished New Jersey turbines

    The Amarillo developer has $62.5 million of cash, a going-concern note and an unsigned tenant lease, and it is buying cheap used megawatts to fill the gap. Earnings on November 12 will show whether the construction lender exists.

    Data Center

    Sanmina pushed $3.5 billion of loan maturities to 2031

    The same filing that guided fiscal 2027 revenue to $17.5 billion to $19.5 billion lifted the stock about 20 percent after hours. Its other page shows the bank line under the ramp: a term loan topped back to $1.4 billion, $600 million still drawable into 2027, and a profit guide stated only in adjusted earnings.

    Data Center

    MARA rose 11% on a $3 billion AI pipeline its own filing calls not yet contracted; $79 million is signed

    MARA's Q3 letter names more than $3 billion of AI demand and has signed $79 million of it. Investors bidding the shares 11% higher on Tuesday are paying for a four-gigawatt story whose only contracted AI revenue is one take-or-pay GPU deal.