Power

Williams Reports Q3 With Its $1 Billion Northeast Pipeline Stuck in Court

The gas pipeline giant moves a third of US natural gas and pays a $2.10 dividend. Its courts keep erasing its Northeast expansions, while the money migrates to data-center country; Tuesday's call decides what replaces them.

Vincent JiangVincent Jiang · 3 min read
Share
Official portrait of Alan Armstrong, whose Williams Companies reports third-quarter results with its $1 billion Northeast pipeline stuck in court
1 / 7Slide 1 of 7
Alan Armstrong leads Williams Companies, which reports third-quarter results on November 2, 2026, eleven days after a federal appeals court denied rehearing on the permit that erased Northeast Supply Enhancement.

Williams reports Q3 with its biggest Northeast bet missing a permit

Williams−2.97% — Williams, down 2.97 percent today, the Tulsa energy company whose Transco network moves about a third of America's natural gas, reports third-quarter results after the market closes today, November 2 1. The report lands eleven days after the U.S. Court of Appeals for the Third Circuit denied the company's bid to reconsider the ruling that erased the New Jersey water-quality certification for Northeast Supply Enhancement, an expansion equal to about 0.4 billion cubic feet of gas a day into New York Harbor 23.

A $2.10 dividend rides on projects courts keep erasing

More than $1 billion of capital sits under that project, and Transco's own rehearing petition told the court that losing the certification "will delay construction" and could jeopardize the November 1, 2027, in-service date and deliveries to utility National Grid+0.57% — National Grid, up 0.57 percent today for the 2027-28 heating season 3.

The board has since approved a quarterly dividend of $0.525 a share, $2.10 annualized, payable December 28 4, on top of second-quarter net income of $827 million 4. The dividend story leans on growth capital, so the courts are now squeezing the payout's funding logic, not just the projects.

The project page promises 2027; the court filing says maybe not

Williams' project page still promises fourth-quarter 2027 service 2. The company's own petition to the court is less certain 3. Meanwhile Washington is trying to force the second Northeast project through: the Energy Department said on October 19 it would direct up to $42 million, under Title III of the Defense Production Act, toward permitting and pre-construction work on Constitution, a 125-mile line from Pennsylvania that would carry up to 650,000 dekatherms a day, targeting service by the winter of 2028 5.

New York denied that project's water permit in 2016 and developers abandoned it in 2020 5; Williams has since asked the Federal Energy Regulatory Commission to reinstate the 2014 federal approval and waive the New York permit requirement 6.

The money is moving to data centers and LNG

While the Northeast litigates, the capital goes where permits are not the story. Williams closed the $5.5 billion Momentum Midstream acquisition on September 3 to connect Haynesville gas to Gulf Coast LNG and power demand 4.

Last week it filed at FERC for Silver Spur, an 88-mile line in Idaho and Nevada adding up to 275 million cubic feet a day by 2030, part of a Northwest plan approaching 1 billion cubic feet a day, where the demand argument is data centers 7. Quarterly capital spending has more than tripled since early 2024 and is closing on operating cash flow 8.

The projects chasing Williams' next billion cubic feet a day, ranked by capacity

  • Estimate
00.20.40.60.81Northwest plan, total1Constitution0.65Northeast Supply Enhancement0.4Silver Spur0.28
Data
Value
Northwest plan, total (estimate)1
Constitution (estimate)0.65
Northeast Supply Enhancement0.4
Silver Spur (estimate)0.28
Announced or filed daily capacities, in billions of cubic feet of gas a day. Northeast Supply Enhancement from the Third Circuit record; Constitution as announced by the Energy Department; Silver Spur and the Northwest plan from Williams' FERC filings.3,5,7

Quarterly capital spending has more than tripled since early 2024, closing on operating cash flow

  • Capital spending
  • Operating cash flow
$0.5B$1B$1.5B$2BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '26$1.86B
Data
Capital spendingOperating cash flow
Q1 '24$0.54B$1.23B
Q2 '24$0.61B$1.28B
Q3 '24$0.73B$1.24B
Q4 '24$0.8B$1.22B
Q1 '25$1.01B$1.43B
Q2 '25$1.01B$1.45B
Q3 '25$0.99B$1.44B
Q4 '25$1.98B$1.58B
Q1 '26$0.99B$1.6B
Q2 '26$1.86B$1.38B
Williams' quarterly capital expenditure against operating cash flow, in billions of US dollars, from its SEC filings, first quarter 2024 through second quarter 2026. Third-quarter 2026 figures are due after the market close on November 2, 2026.8

The other side: New York's approval stands and the state regulator holds the pen

The bull case is intact on paper. A federal appeals court upheld NESE's New York certification in August, Pennsylvania approved its share, and the New Jersey Department of Environmental Protection may now reissue, revise or reach a different result 3. Williams says the projects deliver reliable, affordable energy "while supporting economic growth and emissions reductions" 6. And winter makes the demand case: in January, oil briefly passed natural gas as New England's leading source of electricity during Winter Storm Fern 5.

What to listen for on Tuesday's call

Management speaks at 9:30 a.m 1. ET on Tuesday 1. Listen for a moved service date, deferred Northeast capex, and pace on the Northwest filings. Politics hang over it: Governor Hochul leads Republican Bruce Blakeman by 14 points in the latest Quinnipiac poll, and even her administration has approved a previously rejected pipeline and delayed a climate target 6. The project page promises gas by the winter of 2027; the company's own court filing is not so sure 6.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NGG

Reader comments

0 comments

    Power

    NextEra's three federally backed hubs: 16.5 GW of AI power funded with $5.7 billion of other people's money

    Three federally backed hubs hand NextEra about 16.5 GW of AI-serving generation funded with $5.7 billion of other people's money, for fees worth at least half of outright ownership. The $66.8 billion Dominion takeover is the claim that still needs Virginia's blessing, and the state's own staff says deny.

    Power

    Xcel adds $2 billion of 2027 converts to a $70 billion AI grid plan that runs to 2031

    Today's 8-K puts $2.0 billion of convertible notes due 2027 on the stack, earmarked for commercial paper, not the build. Whether existing customers or new data centers repay the $70 billion plan is a ruling Minnesota and New Mexico regulators have yet to make.

    Power

    Baker Hughes banked $1.45 billion from Hexagon's Waygate buy as its $46.4 billion backlog waits for 2027

    Baker Hughes closed the $1.45 billion Waygate sale to Hexagon on November 2, days after raising its AI-era order target past $50 billion. But GAAP net income fell 33% and its own CFO says the record backlog converts to revenue only slowly in 2027.

    Power

    Vistra's 5,500 megawatts of new gas skipped Texas. Friday's report prices them.

    The Cogentrix plants Vistra closed on October 30 landed almost entirely in PJM and New England, not ERCOT. Friday's guidance is the first test of whether the $4 billion deal still pays what it promised.

    Power

    Entergy earned $1.98, beat by 31 cents; Arkansas regulators get Google's battery terms November 9

    Entergy's Q3 beat looks like the AI-load story investors are paying for, but a third of it is weather. The real test of whether data-center growth compounds or triggers bill shock lands in Arkansas by noon on November 9.

    Power

    Dominion Energy's offshore wind fell from $83 to $62 per megawatt-hour, and certificates did it

    The largest offshore wind farm in the United States is 85% built, but the cost-per-megawatt-hour drop in Dominion's third-quarter disclosure came from certificate prices, not construction, and the schedule has already spent part of its contingency.