Power

Marsh's $7.5 billion data center promise has no filing behind it

· 73 sec

The figure, given to investors on November 24, appears nowhere in Entergy's latest quarterly filing. Louisiana's utility commission is expected to vote in December on $12.9 billion of gas plants for Meta, and holders of ETR are underwriting that the contract delivers what the forecast assumes.

  1. 0:00Entergy · the Fair Share pledge
  2. 0:07The pledge
  3. 0:16What is filed
  4. 0:26Entergy's own number
  5. 0:34What is not settled
  6. 0:47One against
  7. 0:52December is where the numbers are tested
  8. 1:01How the stock answered