Power

Entergy CEO Drew Marsh says data centers will spare existing customers $7.5 billion

The figure, given to investors on November 24, appears nowhere in Entergy's latest quarterly filing. Louisiana's utility commission is expected to vote in December on $12.9 billion of gas plants for Meta, and holders of ETR are underwriting that the contract delivers what the forecast assumes.

Richard TangRichard Tangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Richard Tang. How we work

Share
Drew Marsh, Entergy's chairman and chief executive, in a dark suit and blue tie
Drew Marsh, Entergy's chairman and chief executive, told investors at the Edison Electric Institute's conference on November 24 that data centers paying their fair share spares existing customers $7.5 billion.

Entergy's+1.29% — Entergy, up 1.29 percent today chairman and chief executive, Drew Marsh, told investors at the Edison Electric Institute's conference on November 24 that data centers paying their "fair share" of generation, transmission and grid costs adds up to $7.5 billion that existing customers will not have to pay 1. He calls the policy Fair Share Plus 1. The figure appears nowhere in the quarterly report Entergy (NYSE: ETR) filed with the Securities and Exchange Commission on November 2, and Marsh did not break it down by state 12. Take it as a forecast.

Fair Share Plus has filed terms behind it; the $7.5 billion is a forecast

The filing carries the mechanism behind the pledge. Entergy Louisiana's March application for Meta's+3.93% — Meta, up 3.93 percent today second campus, seven combined-cycle gas units (gas burned in one turbine, the exhaust heat driving a second) costing about $12.9 billion, rests on a contract with Evest, a Meta subsidiary 2. Evest pays Entergy's incremental costs through contributions in aid of construction, payments that fund the build before it enters rates, plus advance payments and minimum monthly bills; if it leaves early, it owes Entergy's unrecovered costs, backed by a guaranty from Meta 2.

Those terms are filed. The $7.5 billion is what Marsh says they spare other customers over time; the contract terms Entergy has described carry no such total 12.

Three gaps sit between the pledge and what customers pay

The first is time. Under the settlement Entergy Louisiana reached with the staff of the Louisiana Public Service Commission, the state's elected utility regulator, three of the plants depreciate over 32 years 34. Meta's contract runs 20, so Louisiana customers could still owe on them long after Meta's payments stop 3.

The second is cost. Waterford 5, the first plant for Meta's existing campus, came in 63% over its estimate this month, and the filing does not say who pays the difference, as we reported on November 20 5.

Google's solar plant already has Arkansas households paying

The third is sharing. Marsh said in September that Arkansas households pay part of a solar plant serving Google, because the plant also serves the grid: "that power plant is for the grid overall. So our existing customers are paying for part of it" 6. In October, Entergy's witnesses put the saving for Louisiana customers at $4 billion over the life of the contract and declined to guarantee it, as we reported on November 11 7.

December is where the numbers are tested

The commission is expected to vote in December on the settlement, which lets Entergy skip the usual search for the lowest-cost option 38. Four of the five commissioners have backed Entergy's Meta plans before 3. Davante Lewis, the one who has not, said on November 23 that he is leaning against the proposal and wants proof of financial efficiency before any cost reaches customers 89.

Consumer groups rallied in Baton Rouge last week, saying Meta should pay for everything it needs 10. Entergy called any suggestion of higher customer costs false and said Meta will pay its full and fair share, and then some 10.

Revenue has grown for eight straight quarters; the 17% is a forecast on top of it

Quarterly revenue has risen year on year for eight straight quarters, and the third quarter's 14.5% gain is what ETR holders are buying 11. Volume is growing more slowly: weather-adjusted retail sales rose 4.5% in the quarter, against the 17% annual sales growth Marsh now forecasts 14. On the terms Entergy has filed, that forecast depends on the plants being approved, built near budget and Meta staying 2.

Entergy's revenue has grown year on year for eight straight quarters, reaching 14.5% in Q3 2026

0%5%10%15%20%Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26Marsh's forecast: 17% sales growth14.5%
Data
Revenue growth from a year earlier
Q4 '240.6%
Q1 '251.9%
Q2 '2512.7%
Q3 '2512.5%
Q4 '257.9%
Q1 '2612%
Q2 '265.9%
Q3 '2614.5%
Year-on-year change in quarterly operating revenue, from Entergy's SEC filings; Q3 2026 measured against Q3 2025. The 17% line is Marsh's forecast for annual sales growth, not a reported figure.11

What is missing is an order that says who pays when a plant costs more than Entergy promised. ETR holders learn in December whether Louisiana writes one.

Sources

  1. 1EnergyPressWire, 'EEI 2026: Entergy CEO Drew Marsh Talks Economic Impact of Data Centers' (interview transcript), 24 November 2026
  2. 2Entergy Corporation, Form 10-Q for the quarter ended 30 September 2026, filed with the SEC 2 November 2026
  3. 3NOLA.com / The Advocate, 'Entergy makes case for expanding Meta data center in hearing while opponents question costs', 8 October 2026
  4. 4Entergy Corporation, 'Entergy reports third quarter 2026 financial results', earnings release (Exhibit 99.1 to Form 8-K), 2 November 2026
  5. 5WWNO / Gulf States Newsroom, 'Entergy's Meta gas plant costs soar as utility seeks approval for seven more', 19 November 2026
  6. 6Washington Examiner, 'Entergy says Google covering full costs for data center power project, as consumers pay for part of it', 30 September 2026
  7. 7WWL-TV, 'Entergy ratepayers could shoulder part of $20B buildout tied to Meta data center', 23 October 2026
  8. 8WBRZ, 'Public Service Commission reviews Entergy request for seven gas facilities for Meta data center', 23 November 2026
  9. 9Business Report (Baton Rouge), 'Davante Lewis leaning against Entergy's $12.9B Meta power proposal, considering run for governor', 23 November 2026
  10. 10Louisiana Radio Network, 'Entergy Louisiana coming under fire for proposal to construct multiple gas plants for Meta', 19 November 2026
  11. 11Entergy (ETR), quarterly operating revenue and year-on-year growth from its SEC filings, retrieved 26 November 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading ETR

Reader comments

0 comments

    Power

    CPUC lets PG&E bill customers $456 million early as $8.6 billion of rate requests wait

    The commission granted the first slice on November 19 while 11 more requests worth about $8.6 billion through 2030 wait behind it, and the same day's undergrounding rules shrank the capital program meant to justify the spending.

    Power

    Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million

    Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027.

    Power

    ENGIE adds 330 km of heat networks fed partly by data centers, and France's left wants to freeze them

    ENGIE's newest French heat networks draw part of their heat from data centers, the same build-out one presidential campaign wants to freeze and the same campaign wants to nationalize ENGIE itself. Investors in the cooling pipeline have to price a political answer, not just a construction schedule.

    Power

    Westinghouse ordered AP1000 demonstration pieces from BWXT, with no price and no named reactor

    A 6.7% jump priced BWXT into the AP1000 supply chain, but the purchase orders cover only demonstration pieces, with no disclosed value, no delivery date and no commitment to buy components for any reactor build. The paying customer is still Washington.

    Power

    Investors sue NuScale as quarterly revenue falls to $281,000 and the stock trades below its cash pile

    Quarterly revenue has fallen to $281,000, the equity now trades below its own $1.86 billion cash pile, and the January 11, 2027, lead-plaintiff deadline puts class-period holders on the clock.

    Power

    X-energy wins NRC permit for four reactors at Dow's Texas plant, first US nuclear build at an industrial site

    The NRC's first high-temperature gas-cooled permit in over 50 years proves the Xe-100 can be built at a chemical plant. The money gate now sits with Dow in 2027, while X-energy burns $123 million a quarter and the whole nuclear sector de-rates.

    Subscribe to TheInference for free