The biggest US transmission owner has 84 GW of AI-era demand signed in take-or-pay contracts, and a $100 billion plan that leans on faster ratepayer recovery rather than an equity number. This week, Texas, the US Senate and Oklahoma opened the fight over who pays.

Richard TangRichard Tangthree-minute read
Share
High-voltage transmission lines crossing a field under a cloudy sky
1 / 6Slide 1 of 6
AEP owns the largest transmission system in the United States, and its $100 billion plan depends on building more of it while voters and regulators decide who pays.

American Electric Power−0.45% — American Electric Power, down 0.45 percent as of its last quote, the utility that owns the nation's largest electric transmission system, put the slides behind its $100 billion, 2027-2031 capital plan in front of investors on November 8 12. The plan rests on 84 gigawatts of load contracted to arrive by 2031, in firm take-or-pay agreements where the customer pays whether or not it draws the power 34. Demand is no longer the constraint; financing and political permission are, and both moved this week.

The load is signed, the money is not

Contracted load rose from 69 GW to 84 GW in a single quarter, led by a 10.4-gigawatt campus in Piketon, Ohio, planned by SB Energy, an affiliate of Japan's SoftBank 4. AEP raised the plan from $78 billion to $100 billion to serve it 4.

Rate base, the assets AEP earns a regulated return on, is guided to compound at more than 13 percent a year, and operating earnings to grow 9 to 11 percent 3. The hardware is the scarce part: Tyler Page, chief executive of power-plant developer Cipher Digital−1.91% — Cipher Digital, down 1.91 percent today, said on his earnings call, "There just aren't enough turbines and reciprocating engines in the world" 5.

No equity number covers $78 billion of the plan

The financing is thinner. AEP said it would fund its latest addition, the $22 billion we covered on October 29, with about 24 percent equity 4. No equity number covers the remaining $78 billion of the plan 2.

Peers have sized theirs: Ameren−0.30% — Ameren, down 0.30 percent today, the Missouri and Illinois utility, expects about $5 billion of equity for its $38.1 billion plan, and WEC Energy Group−0.12% — WEC Energy Group, down 0.12 percent today, a utility holding company with its own expanded capital plan, signed banks to sell up to $4 billion of stock 67. AEP's slides instead lean on customer affordability offsets and reduced-lag recovery, collecting from ratepayers with less regulatory delay 2.

AEP's building program has outrun its operating cash

Quarterly capex has pulled away from operating cash just as the $100B plan begins

  • Capex
  • Operating cash flow
$1B$2B$3B$4B$5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26The $100B plan starts in 2027
Data
CapexOperating cash flow
Q4 '23$1.61B$1.34B
Q1 '24$1.76B$1.44B
Q2 '24$1.56B$1.46B
Q3 '24$1.85B$2.17B
Q4 '24$2.86B$1.73B
Q1 '25$2.1B$1.45B
Q2 '25$3.28B$1.22B
Q3 '25$2.28B$2.46B
Q4 '25$4.25B$1.81B
Q1 '26$3.8B$1.52B
Q2 '26$3.13B$1.9B
Q3 '26$4.58B$2.35B
Quarterly capital spending and operating cash flow, USD billions, as reported in AEP's SEC filings; the $100B plan covers 2027-2031.12

The backlash decides who pays

Six days after AEP expanded the plan, voters pushed back. They approved restrictions or moratoriums on 44 of 45 data-center ballot measures where vote counting is complete 8, and Texas Governor-elect Gina Hinojosa, who takes office in January, wants new data centers halted until the legislature writes community protections 9.

The Senate bill and the Oklahoma hearing test who pays

President Trump urged senators on Sunday to make data centers "build and pay for their own electricity," and the Senate voted 73-25 on Monday to open debate on a bill requiring large data centers to cover more of the grid costs they cause 510. The bill still needs House passage before the new Congress convenes on January 3 810.

Oklahoma's Corporation Commission took public comment Monday on the west section of AEP's 100-mile transmission line, with a formal hearing Friday 11.

The model politicians demand is already inside the plan

The model politicians demand already runs inside the plan: AEP expects up to $21 billion of fixed-cost offsets to reach residential customers from those contracts 3, and SoftBank and its affiliates are funding the roughly $5 billion transmission spine for the Ohio campus 4, the customer paying for its own wires.

What to watch: Friday's Oklahoma hearing, whether the Senate bill passes before January 3, and whether AEP puts an equity number on the remaining $78 billion.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

    Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.