Applied Digital put $97 million into ChronoScale on a note that matures December 31

The Schedule 13D/A filed November 20 shows the funding behind ChronoScale's $200 million Super Micro GPU order: a $97 million no-interest note from majority owner Applied Digital, fully funded and maturing December 31. Conversion needs a stockholder consent still in the mail, so one balance sheet carries the timing risk.

Richard TangRichard Tangthree-minute read
Share
Wes Cummins, Applied Digital chairman and chief executive, being interviewed on CNBC, his name and title on the chyron below him
Wes Cummins, Applied Digital's chairman and chief executive, on CNBC's Squawk on the Street on November 2, 2026, discussing the company's AI infrastructure business.

Applied Digital's−14.02% — Applied Digital, down 14.02 percent today Schedule 13D/A, filed November 20, names the money behind ChronoScale's $200 million Super Micro−7.13% — Super Micro, down 7.13 percent today order: the parent itself 12. Applied Digital, a Nasdaq-listed data-center builder, already owns 85.6% of ChronoScale, the AI cloud it majority-owns 1. Its latest contribution is a $97 million unsecured convertible note, funded in full, paying no interest, and due back on the last day of the year 1. The raise works only if paperwork outruns a six-week clock, and that clock has not started.

A shell, a Texas venture and a GPU bill

ChronoScale began as a Nasdaq shell: Applied Digital folded its GPU-cloud unit into Ekso Bionics, an exoskeleton maker, and renamed it; it is run by Cenly Chen, a former Super Micro chief growth officer 2. The round funds a 50/50 Odessa, Texas venture with developer STN, serving an unnamed frontier AI lab under contracts worth up to $7.5 billion over six years 3. A ChronoScale subsidiary lends that venture $220 million, with the GPU portion paid straight to Super Micro 2. ChronoScale's existing contracts point to $1 billion of annualized revenue by late 2027 4.

The clock sits in the mailing, not the vote

The note converts at $8.00 a share 1. That is about 18% below where ChronoScale closed before the deal 5, and conversion happens only when stockholder approval becomes effective 1. The consent, signed November 18 by holders who are mostly Applied Digital, takes effect on the 20th calendar day after ChronoScale mails its information statement, and the amendment names no mailing date 1.

The vote is a formality; the mailbox is the risk.

If effectiveness slips past December 31, the note stays what it says it is: interest-free, unsecured debt of a company that has just sent its cash to Super Micro 1.

One balance sheet, two bets

Applied Digital consolidates ChronoScale, so the note is a seam inside a single balance sheet rather than a transfer of risk outside it 6. That sheet now backs both trades at once: campuses tied up in long leases, with CoreWeave−9.31% — CoreWeave, down 9.31 percent today about 30% of contracted revenue, and the GPU venture stacked on top 7. The quarterly interest bill, $77 million, now roughly matches rent, and hundreds of megawatts of the buildout still lack committed financing 67.

Capex has topped revenue in each of Applied Digital's last eight quarters

  • Revenue
  • Capex
$0B$1B$2B$3BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$2.08B
Data
RevenueCapex
Q4 '24$0.04B$0.17B
Q1 '25$0.05B$0.26B
Q2 '25$0.05B$0.17B
Q3 '25$0.08B$0.25B
Q4 '25$0.13B$0.55B
Q1 '26$0.13B$0.78B
Q2 '26$0.26B$1.29B
Q3 '26$0.34B$2.08B
Quarterly revenue and capital spending, USD billions, from Applied Digital's SEC filings. Q3 '26 is the quarter ended August 31, 2026, when capex ran 6.1 times revenue.9

Applied Digital's debt climbed from under $1 billion to $6.5 billion in eight quarters

Two AI-cloud bets now sit on one balance sheet

$0B$2B$4B$6B$8BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$6.48BCloud unit became ChronoScale;still consolidated
Data
Total debt
Q4 '24$0.8B
Q1 '25$0.99B
Q2 '25$0.91B
Q3 '25$0.7B
Q4 '25$2.61B
Q1 '26$2.83B
Q2 '26$5.1B
Q3 '26$6.48B
Quarter-end total debt, USD billions, from Applied Digital's SEC filings. Q3 '26 is the quarter ended August 31, 2026. The GPU cloud unit that became ChronoScale sits inside these consolidated figures from May 2026.8

December 31 turns the note into equity or a receivable

Closing the gap between GPUs and compute people can actually use deserves reward, and ChronoScale's contract book suggests it may earn one 4. What deserves scrutiny is the financing seam: a frontier-lab deal funded partly with the parent's own paper, on a clock set by a mailing. Twenty days after the information statement goes out, this is either equity or a year-end receivable from Applied Digital's own subsidiary.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading APLD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    SpaceX's 10-Q shows $48.1 billion of capex against $13.1 billion of cash before its December 8 lock-up

    SpaceX's Q3 10-Q puts the build at $48.1 billion of nine-month capex against $13.1 billion of operating cash, with the gap filled by $43 billion of chip-lease debt near 8.3%. That is the case against the equity 17 days before its lock-up expires, with Anthropic holding a 90-day exit.

    Data Center

    Trump threatens 'tremendous tax' on US companies that build data centers abroad

    No rate, timetable or legal authority accompanied the threat, which landed on Alphabet, Amazon, Microsoft, Meta and Oracle, the companies already building abroad, on a day the Nasdaq 100 fell 5.7%.

    Data Center

    Oracle slid to about $103, under Bernstein's $133 floor if its AI data-center business fails

    Bernstein's stress case says Oracle's databases, software and conventional cloud are worth $133 a share even if its AI data-center business fails. At $110.57 and falling, the slide suggests investors are pricing what that floor leaves out: years of negative cash flow between building the capacity and getting paid for it.

    Data Center

    Fermi falls 16% as a court lets its board rewrite bylaws by majority while shareholders need 70% to act

    The ruling leaves Fermi shareholders needing 70% of all outstanding shares to touch the board while directors can rewrite the same rules by simple majority. The co-founder who sued sold $21 million of stock the week before, and the five-day rally on Amazon's name rests on a lease that is not signed.

    Data Center

    Cameron County rejects SpaceX tax break on $24 billion Starbase campus

    The nonbinding rejection opens a fight over property taxes on a $24 billion campus, and it arrives in a week when SpaceX priced $76 billion of GPU debt.

    Data Center

    YTL Power denies its data centers moved Nvidia chips to China as data-center profit jumps nearly 133-fold

    The Malaysian utility filed its denial hours after quarterly results showed data-center profit up nearly 133-fold, the group's only growth engine. Investors marking the stock down about 20% in two weeks must weigh the company's word against a five-source account of Alibaba's chips running inside its Johor park.

    Subscribe to TheInference for free