Meta's Ohio data center faces Tuesday's vote with 90.5% of 10,202 hearing comments against

A database logged one day before the midterms counts 10,202 public comments at US local hearings: 90.5% negative, water the top complaint, AI mentioned in a fifth. More than 40 ballot measures on Tuesday put the bill on builders' permits, pipes and wires.

Vincent JiangVincent Jiang · 3 min read
Share
A long windowless Meta data center building stretching behind dry grassland, juniper trees and a fence on the edge of Prineville, Oregon.
1 / 6Slide 1 of 6
Meta's data center west of Prineville, Oregon. On Tuesday, voters in Piqua, Ohio, decide whether the company can build one in their city, alongside a recall of the mayor and two commissioners who backed it.

A recall vote rides on Meta's data center

In Piqua, Ohio, a city of about 20,000, Tuesday's ballot asks two questions at once: should Meta−1.03% — Meta, down 1.03 percent today build its data center here, and should the mayor and two city commissioners who backed it keep their jobs? 1 The recall is the sharp edge of a revolt that now has a ledger. A site called American Sentiment, run by Prophecy Gov, a San Francisco startup whose day job is selling AI assistants to city staff, has counted 10,202 public comments from 417 local government meetings across the country this year. 234

The cost of the mood is already booked. Forty-five projects worth $68 billion were delayed or blocked by local opposition in the second quarter alone, according to the researcher Data Center Watch, and more than 40 data-center measures sit on November 3 ballots, from bans in about a dozen Ohio communities to a rezoning vote on a proposed Amazon+2.75% — Amazon, up 2.75 percent today site in Wilmington, Ohio. 1

The complaints are water, secrecy and quality of life

The record is blunt. Of the 10,202 comments, 90.5% were negative and 7% positive; 73% of the meetings heard no supporter at all, and the supporters who came were outnumbered six to one. 2 Water use led the complaints, followed by quality of life and a lack of transparency about the projects. Just 21% of commenters mentioned AI in any way. 2

One group held the line. Some 79% of self-described union workers spoke in favor of data centers, against 3% of property owners and 3% of residents; even among people who work in data centers, only 40% did. 2

In the hearing room, only union workers speak for data centers

%0%20%40%60%80Union workers%79Data center workers%40Property owners%3Residents%3
Data
Value
Union workers%79
Data center workers%40
Property owners%3
Residents%3
Share of 2026 public comments at US local-government meetings that favored data centers, by commenter type. American Sentiment database of 10,202 comments across 417 local governments, as reported by Tom's Hardware, November 2, 2026.2

The ad market flipped against the buildings

Campaign money matches the hearing room. Pew Research Center coded 20,751 Facebook and Instagram political ads that mentioned data centers: in January, supportive ads outnumbered critical ones, 42% to 31%; by October, 57% opposed and 3% supported. 5

The spending is one-sided in cash as well as tone. AdImpact, an ad-tracking firm, counts $173 million spent on almost entirely negative data-center commercials this general election, $140 million of it from Democrats, and when Axios asked it to name one overtly positive spot, it could not find one. 6

Data-center political ads flipped from net supportive in January to 19-to-1 against by October

  • Anti-data center
  • Pro-data center
%0%20%40%60%80FebAprJunAugOct%57
Data
Anti-data centerPro-data center
Jan%31%42
Feb%52%14
Mar%42%30
Apr%57%19
May%57%6
Jun%64%6
Jul%60%6
Aug%62%8
Sep%61%8
Oct%57%3
Share of Facebook and Instagram political ads mentioning data centers that opposed or supported them, by month, 2026. Pew Research Center coding of 20,751 ads, published October 29, 2026.5

Builders answer with a billion dollars

The industry's case is on the table. Amazon Web Services chief Matt Garman, in a 3,000-word post on October 2, called the water fears a myth, pledged more than $1 billion of community investment over five years, and warned that the roughly 100 moratoriums then pending could cost the United States the AI race. 8

Hearing comments also self-select for the angry. Yet a September Quinnipiac poll found 72% of voters opposed to a data center in their own community, up from 65% in March, and local vetoes bend only so far: after Boulder City, Nevada residents stopped a $3 billion project on a city-owned tortoise preserve, the developer won approval on neighboring federal land. 1

So far, opponents are four for four

Tuesday counts the rooms anyway, and the pattern so far is four-for-four: every data-center measure decided earlier this year went for tighter controls. 7 December brings a $55 billion bond vote on a ServerFarm project in Clarksville, Arkansas, and January could bring a referendum in Coweta County, Georgia, forced by 14,000 signatures against a $17 billion campus, if a judge allows it. 1

The scarcest input in the AI buildout is no longer power or water; it is a room willing to say yes.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading META

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Nidec's 3.2MW AI cooler is on schedule; its audit is not

    Nidec announced a 3.2MW in-row cooler for 800-volt AI racks the same week its auditor declined to sign its accounts and Tokyo's exchange began a listing review. The product ramp and the accounting clearance now run on different clocks, and the second one prices the stock.

    Data Center

    Hedge funds sold IREN as AI exposure; $4 billion of contracts must convert on November 5

    The funds that bought bitcoin miners as AI exposure sold them as AI exposure in October, Goldman Sachs prime-brokerage data show. IREN reports fiscal first-quarter results on November 5, with consensus at $221.71 million of revenue and a $0.76 loss per share, and the print decides whether $4 billion of contracted capacity is converting or stalling.

    Data Center

    American Tower owns Dish's abandoned 5G radios; SpaceX may be the buyer as US property revenue falls 3%

    A bankruptcy abandonment order gave the tower operator its dead customer's radios the same week it guided US property revenue down 3%. About 400 basis points of that hole is one company, and the likeliest buyer of the gear is the company building a network to replace its remaining tenants.

    Data Center

    Equinix's record quarter ran on $3.8 billion of new debt and a $2 billion stock shelf

    Record bookings and a third guidance raise, but the build ran on $3.8 billion of new debt and a $2 billion share-sale shelf filed an hour after results. Who pays if the build outruns the bookings.

    Data Center

    Sterlite's record quarter met two limit-downs: the ₹35,274 crore order book is the question

    Sterlite Technologies printed its best quarter ever, ₹2,529 crore of revenue, up 145%, and fell two 5% lower circuits anyway. The disagreement is not demand: it is whether a ₹35,274 crore order book built on two unnamed US hyperscalers converts into cash.

    Data Center

    Vertiv jumped 16% on an order number with no dollar value

    Vertiv said organic orders more than doubled, then said it will stop publishing the figures that would show whether that growth is real megawatts or price inflation in the queue. February's annual report is the check.