Power

BMO upgrades Bloom Energy and cuts its target to $230 as its record quarter burned $181 million of cash

A long-time skeptic turned bull on Bloom's fuel cells and their milestone-based payments. Those same milestones are why record revenue still burned cash, and the fourth-quarter report, with 2027 guidance, decides which reading holds.

Richard TangRichard Tangthree-minute read
Share
KR Sridhar, founder and chief executive of Bloom Energy, in a company headshot
KR Sridhar, Bloom Energy's founder and chief executive. BMO upgraded the fuel-cell maker to Outperform on November 19 and cut its price target to $230 from $260.

BMO Capital Markets, the investment bank whose analysts rate stocks, upgraded Bloom Energy−2.48% — Bloom Energy, down 2.48 percent today to Outperform on November 19, its rating for shares it expects to beat the market, and cut its price target to $230 from $260; the fuel-cell maker's shares still jumped 6%. 12

The day did part of the work: Anthropic$350B — Anthropic, private, latest valuation $350B, the AI lab, went public on Nasdaq in an offering read as a test of investor appetite for AI, which pulled attention back to everything the buildout needs, power included. 1 Analyst Ameet Thakkar, long a skeptic of the stock, now points to execution and contract protections. 12

The technology is the strong half of the call. The open question is who finances the speed, and this quarter the answer was Bloom's own balance sheet.

Fuel cells cut the power wait to months

Bloom's fuel cells turn natural gas into electricity through a chemical reaction rather than by burning it, sitting on site at the data center. 3 Bala Naidu, the company's vice president of energy transition, says a grid connection can take five to seven years where power is scarce, while Bloom delivers in months. 3 That gap is why every major US hyperscaler, the giant cloud companies, has approved its systems. 6 Clearing the wait for power does not finish a project; it moves the bottleneck.

At the showcase site, power finished first

At the New Jersey data center of Nebius−10.06% — Nebius, down 10.06 percent today, an AI-cloud builder supplying Microsoft−1.88% — Microsoft, down 1.88 percent today, Bloom won approval within three months of signing and had its first units feeding electricity two months later. 3 Nebius still pushed the rest of Microsoft's ordered compute to the second quarter of 2027, blaming site developer DataOne for retiring temporary generators early; Microsoft helped plan the revised timetable and the contracts stand. 35 Power was the first constraint solved. The opening date now rests on construction and generators, none of it Bloom's, the same slow conversion we traced last week in Bloom's order book 35.

Milestone billing puts the wait on Bloom's books

Third-quarter revenue set a record at $1.24 billion and 2026 guidance rose for the third time, 46 yet the quarter used $181 million of cash, as we reported on October 23. 26 The cause is milestone-based billing: revenue booked but not yet billed more than tripled this year, to $859 million from $241 million at the end of 2025. 26 CFO Simon Edwards calls the cash use "not the beginning of a trend". 6 With two customers making up 69% of revenue, one late milestone moves the quarter. 2

Revenue has more than tripled since 2023, and the record quarter still burned cash

$0B$0.5B$1B$1.5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26free cash flow: -$181M
Data
Revenue
Q4 '23$0.36B
Q1 '24$0.24B
Q2 '24$0.34B
Q3 '24$0.33B
Q4 '24$0.57B
Q1 '25$0.33B
Q2 '25$0.4B
Q3 '25$0.52B
Q4 '25$0.78B
Q1 '26$0.75B
Q2 '26$1.07B
Q3 '26$1.24B
Quarterly revenue, $ billions, by calendar quarter, from Bloom Energy's SEC filings (retrieved November 19, 2026). The Q3 2026 quarter set a record $1.236 billion of revenue and still used $181 million of cash.4,8

The fourth quarter settles the argument

BMO expects $7.88 billion of 2027 revenue, above the $7.09 billion consensus, on a number Bloom has not yet guided. 12 Oracle−3.13% — Oracle, down 3.13 percent today, the software company building AI data centers and the customer behind Bloom's 2.8-gigawatt order, burned $5 billion of cash in its August quarter; it reports on December 10, and its own CFO has promised the data-center spending peaks this year. 267 Bloom follows early next year, needing fourth-quarter revenue of $1.35 billion to $1.55 billion and cash flow back above zero. 6

Bloom's fuel cells can put power on a site in months. Payment arrives by milestone and can lag by quarters; until billing catches up, Bloom's shareholders fund the gap.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BE

Reader comments

0 comments

    Power

    Southern's Georgia Power and Alabama Power hold $26.5 billion of federal energy loans, the most in DOE history

    The first published ranking of the Energy Department's loan book puts Georgia Power and Alabama Power first, and the November 18 tally shows the whole $73.2 billion book now finances reactors and wires rather than wind, solar or electric vehicles.

    Power

    Vistra registered 5 million Cogentrix shares, about $624 million, for resale as its buyback grows

    Vistra funded its Cogentrix gas-fleet purchase partly in its own stock, registered for resale Nov 9 with a lock-up ending Jan 30, just as the board added $1.5 billion to the buyback. Shareholders who bought the buyback story face roughly $624 million of incoming supply while only 78% of 2028 output is hedged.

    Power

    Louisiana defers Entergy's private grid hearing for Meta to Dec. 16 as a $12.9 billion gas-plant vote nears

    The same December docket now holds a consultant's verdict on Entergy's next rate increase, a hearing on the private grid serving Meta, and the vote on $12.9 billion of gas plants. Whose money carries it moves ETR shareholders and Louisiana ratepayers alike.

    Power

    PG&E signs 20-year Avantus contracts for 800 MW of solar and storage, pending CPUC approval

    The contracts still need approval from the California Public Utilities Commission, and PG&E's third-quarter filing shows the utility's operating cash running $3.4 billion behind its capital spending over the first nine months of 2026. Avantus's backers at KKR and EIG take the construction risk; the 20-year payment obligation lands on PG&E, its lenders and California ratepayers.

    Power

    NRG Energy sells six gas plants to LS Power for $4 billion, pricing one Texas plant at $1,400 per kilowatt

    The 8x cash offer implies about 40% more for the running Texas plant than NRG says new build costs. Neither the deal filing nor the 2027 guidance, which still counts the six plants, values the 20 GW NRG keeps.

    Power

    Dominion Energy sells $1.2 billion of bonds at 5.25% and 5.95% as Virginia weighs NextEra's $67 billion deal

    The pricing was disclosed the day before Virginia opened hearings on NextEra's $67 billion takeover, where the companies refused a rate freeze and promised a credit upgrade. The coupons are what the AI build-out costs without the merger, and a January ruling decides who pays them.

    Subscribe to TheInference for free