BMO upgrades Bloom Energy and cuts its target to $230 as its record quarter burned $181 million of cash
A long-time skeptic turned bull on Bloom's fuel cells and their milestone-based payments. Those same milestones are why record revenue still burned cash, and the fourth-quarter report, with 2027 guidance, decides which reading holds.
Richard Tangthree-minute read
BMO Capital Markets, the investment bank whose analysts rate stocks, upgraded Bloom Energy−2.48% — Bloom Energy, down 2.48 percent today to Outperform on November 19, its rating for shares it expects to beat the market, and cut its price target to $230 from $260; the fuel-cell maker's shares still jumped 6%. 12
The day did part of the work: Anthropic$350B — Anthropic, private, latest valuation $350B, the AI lab, went public on Nasdaq in an offering read as a test of investor appetite for AI, which pulled attention back to everything the buildout needs, power included. 1 Analyst Ameet Thakkar, long a skeptic of the stock, now points to execution and contract protections. 12
The technology is the strong half of the call. The open question is who finances the speed, and this quarter the answer was Bloom's own balance sheet.
Fuel cells cut the power wait to months
Bloom's fuel cells turn natural gas into electricity through a chemical reaction rather than by burning it, sitting on site at the data center. 3 Bala Naidu, the company's vice president of energy transition, says a grid connection can take five to seven years where power is scarce, while Bloom delivers in months. 3 That gap is why every major US hyperscaler, the giant cloud companies, has approved its systems. 6 Clearing the wait for power does not finish a project; it moves the bottleneck.
At the showcase site, power finished first
At the New Jersey data center of Nebius−10.06% — Nebius, down 10.06 percent today, an AI-cloud builder supplying Microsoft−1.88% — Microsoft, down 1.88 percent today, Bloom won approval within three months of signing and had its first units feeding electricity two months later. 3 Nebius still pushed the rest of Microsoft's ordered compute to the second quarter of 2027, blaming site developer DataOne for retiring temporary generators early; Microsoft helped plan the revised timetable and the contracts stand. 35 Power was the first constraint solved. The opening date now rests on construction and generators, none of it Bloom's, the same slow conversion we traced last week in Bloom's order book 35.
Milestone billing puts the wait on Bloom's books
Third-quarter revenue set a record at $1.24 billion and 2026 guidance rose for the third time, 46 yet the quarter used $181 million of cash, as we reported on October 23. 26 The cause is milestone-based billing: revenue booked but not yet billed more than tripled this year, to $859 million from $241 million at the end of 2025. 26 CFO Simon Edwards calls the cash use "not the beginning of a trend". 6 With two customers making up 69% of revenue, one late milestone moves the quarter. 2
Revenue has more than tripled since 2023, and the record quarter still burned cash
Data
| Revenue | |
|---|---|
| Q4 '23 | $0.36B |
| Q1 '24 | $0.24B |
| Q2 '24 | $0.34B |
| Q3 '24 | $0.33B |
| Q4 '24 | $0.57B |
| Q1 '25 | $0.33B |
| Q2 '25 | $0.4B |
| Q3 '25 | $0.52B |
| Q4 '25 | $0.78B |
| Q1 '26 | $0.75B |
| Q2 '26 | $1.07B |
| Q3 '26 | $1.24B |
The fourth quarter settles the argument
BMO expects $7.88 billion of 2027 revenue, above the $7.09 billion consensus, on a number Bloom has not yet guided. 12 Oracle−3.13% — Oracle, down 3.13 percent today, the software company building AI data centers and the customer behind Bloom's 2.8-gigawatt order, burned $5 billion of cash in its August quarter; it reports on December 10, and its own CFO has promised the data-center spending peaks this year. 267 Bloom follows early next year, needing fourth-quarter revenue of $1.35 billion to $1.55 billion and cash flow back above zero. 6
Bloom's fuel cells can put power on a site in months. Payment arrives by milestone and can lag by quarters; until billing catches up, Bloom's shareholders fund the gap.
Get Power by email, free
How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.






Reader comments
0 comments