Chile's power tribunal sides with Enel over Engie, ordering a count of the desert's stability needs
The tribunal upheld Enel's demand for a quantified voltage-control requirement and rejected Engie's push to declare a deficit now. A number would become tenders and tariffs, and Enel already has grid-forming batteries rising in the desert.
Vincent Jiangthree-minute read
A number, ordered
Chile's Panel de Expertos, the tribunal that settles the country's power disputes, has ordered the grid operator to count. In rulings reported earlier this month it rejected Engie's−0.37% — Engie, down 0.37 percent today demand that the Coordinador Eléctrico Nacional (CEN) weigh the north's weakness now and define new infrastructure on it, and upheld Enel's−0.39% — Enel, down 0.39 percent today narrower claim: CEN must rewrite its 2027 complementary-services report, which sets the grid's voltage and stability needs, and state in figures the resources the zone requires and how they are paid for 1.
The strength the desert lost
The north, home to Chile's copper mines and, increasingly, its data centers, swapped coal and gas plants for solar and wind, and lost the inertia and short-circuit power those machines gave free. CEN's 2022 and 2023 studies set a floor of 1,600 MVAr of synchronous condensers, spinning machines that hold voltage without generating power, by 2030; five offers went to Alupar, Engie and Transelec in May 2024 1. A study for the generators' association still found the system weak in daytime hours through 2031, closable with about 2.8 GVA more 1.
Why CEN will not count yet
CEN's defense is method: the 2023 tools cannot model inverter-based resources, batteries that form the grid or follow it, and the robustness study due February 2027 digs deeper 1. Its filing names "a possible massification of large loads, among them the data centers" among what the new method must weigh 1, and on November 17 it published its own study on integrating data centers into the system 2.
Colbún, backing Engie, cited Spain's blackout of April 28, 2025, when inverter-based plants failed to hold stability, and South Australia's eight dark hours in 2016 1. The operator is building regardless: on November 16 the energy ministry heralded 19 transmission awards worth more than US$500 million 3.
Enel's inventory, already standing
Enel Green Power, the Italian group's renewables arm, has four battery plants rising in the Atacama, all of them grid-forming, the inverter mode that mimics a synchronous machine: Azabache at 94 MW and 372 MWh, Finis Terrae at 100 MW, Valle del Sol at 186 MW, with Las Salinas first to break ground, in November 2025 4.
Enel's Atacama battery build-out already tops 380 MW in the weak north
Three rated projects give Enel 380 MW of grid-forming capacity in the weak zone
Data
| Value | |
|---|---|
| Valle del Sol | 186 MW |
| Finis Terrae | 100 MW |
| Azabache | 94 MW |
For the group this is small money: nine-month revenue of €65.0 billion, ordinary Ebitda of €17.95 billion, Green Power flat at €5.11 billion, interim dividend up 7% 5, with 2026 Ebitda guided at €23.1 billion to €23.6 billion 6. The Inference covered Enel's October files, from phantom meters to São Paulo.
What lands next
CEN says the rewritten report, ordered by the panel, will be published in the coming days 1; it had not surfaced in the operator's newsroom by November 23 3. February's robustness study then decides what gets tendered, and whether grid-forming batteries are paid as infrastructure. If the number lands, the Atacama's batteries stop being storage and start being the grid.