Power

An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

Vincent JiangVincent Jiangthree-minute read
Share
A high-voltage transmission line on single poles runs along a cleared right of way between green farm fields and a rural road
A high-voltage transmission line follows a cleared right of way between farm fields and a rural road. AEP's proposed 75-mile Lulu-Sorenson line would cross Steuben County on a similar corridor, on towers up to 175 feet tall.

A county board asks AEP to stop advancing the line

On Nov. 17 the Steuben County Board of Commissioners asked AEP Transmission+0.02% — AEP Transmission, up 0.02 percent today to suspend the Lulu-Sorenson project until independent research covers public health, the environment, property values and quality of life 1. The line would run about 75 miles between the Sorenson substation and the Indiana-Michigan state line, on towers up to 175 feet tall; no route is picked, and one is due by late February 2027 12.

Becca Leider, a registered nurse whose land sits in the path, calls the fight "all encompassing" 2. DeKalb County's board voted unanimously on Nov. 9 to oppose it, after more than 1,000 people attended the September open houses 67.

A high-voltage transmission line on a single steel pole with a wide cleared right of way cut through autumn woodland, looking toward distant fields
A wide cleared right of way cuts through woodland for a high-voltage line. Route selection decides where such corridors go: AEP's Lulu-Sorenson route is due by late February 2027.Wikideas1

The line carries a $100 billion promise

American Electric Power, the Columbus utility that runs the country's largest transmission network, told investors on Oct. 28 it will spend $100 billion from 2027 through 2031, lifting rate base, the pool of regulated assets it earns on, to $162 billion 3.

AEP's capital spending has outrun operating cash flow in 10 of the last 12 quarters

  • Capital spending
  • Operating cash flow
$1B$2B$3B$4B$5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$4.58B
Data
Capital spendingOperating cash flow
Q4 '23$1.61B$1.34B
Q1 '24$1.76B$1.44B
Q2 '24$1.56B$1.46B
Q3 '24$1.85B$2.17B
Q4 '24$2.86B$1.73B
Q1 '25$2.1B$1.45B
Q2 '25$3.28B$1.22B
Q3 '25$2.28B$2.46B
Q4 '25$4.25B$1.81B
Q1 '26$3.8B$1.52B
Q2 '26$3.13B$1.9B
Q3 '26$4.58B$2.35B
American Electric Power capital spending and operating cash flow by quarter, US$ billions, as reported. Capital spending exceeded operating cash flow in 10 of the 12 quarters shown. Source: AEP quarterly figures from its SEC filings, retrieved 21 Nov 2026.12

The plan rests on 84 gigawatts of incremental contracted load by 2031, 15 gigawatts of it signed in the third quarter alone, and carries guidance for 9% to 11% annual operating-earnings growth with up to $21 billion of bill offsets for residential customers 3. Evercore−4.80% — Evercore, down 4.80 percent today ISI kept its Outperform rating on Nov. 13 with a $154 target, 19% above the $129.18 close 4.

AEP's $100 billion plan averages $20 billion a year after capex jumped 48% in 2025

The plan averages roughly 1.7 times AEP's 2025 spend, every year

  • Capital spending
  • Estimate
$0B$5B$10B$15B$20BFY2020FY2021FY2022FY2023FY2024FY20252027-31 avg (plan)$11.91Bderived: $100B over five years
Data
Capital spending
FY2020$6.25B
FY2021$6.43B
FY2022$7.88B
FY2023$7.53B
FY2024$8.03B
FY2025$11.91B
2027-31 avg (plan) (estimate)$20B
AEP capital spending by fiscal year, US$ billions. Final bar divides the $100 billion 2027-2031 plan evenly across five years, a derived average rather than annual guidance. Sources: AEP SEC filings; AEP 8-K, 28 Oct 2026.11,3

The megawatt queue is thinning

The permission problem shows up first in AEP Ohio's own numbers. Developers requested more than 30,000 megawatts of capacity; once the utility began charging for engineering studies and requiring binding commitments, 13,023 megawatts went to study, and by February 2026 only 5,642 megawatts had signed contracts 58. Another 12,219 megawatts were contracted before the data-center tariff took effect in July 2025 58. On Nov. 3, voters favored data-center restrictions in 40 of 41 local ballot contests, five of them outright bans 59. In Oklahoma, opponents of AEP's Branson 345-kilovolt overlay handed state regulators a petition with more than 1,400 signatures 10.

AEP Ohio's data-center queue: 30,000-plus MW asked, 5,642 MW signed by February 2026

Fewer than one in five requested megawatts reached a signed contract

0 MW10,000 MW20,000 MW30,000 MWCapacity requested30,000 MWWent to paid studies13,023 MWfees culled over half the askSigned under tariff5,642 MWContracted pre-tariff12,219 MW
Data
Value
Capacity requested30,000 MW
Went to paid studies13,023 MW
Signed under tariff5,642 MW
Contracted pre-tariff12,219 MW
Stages of AEP Ohio's data-center queue, megawatts. The requested figure is reported as more than 30,000; pre-tariff contracts predate the July 2025 tariff. Sources: Motley Fool via The Globe and Mail, 17 Nov 2026; cleveland.com, 6 Oct 2026.5,8

The contracts, not the county votes, decide who pays

AEP's Ohio tariff pushes the risk back onto developers: minimum monthly bills, full reimbursement of buildout costs on cancellation or a year's delay, and exit fees worth three years of minimum charges 8. Federal regulators are weighing the same protections for the regional grid, with filings due Dec. 16 8. AEP says it has "invested time engaging with property owners, local officials and community members" 10. County boards, DeKalb's president conceded, have no authority to stop a line 6. The question of who funds the plan was traced in The Inference's October reporting 6.

The route and the signed megawatts are the checkpoints

The route is named by late February 2027, and AEP Ohio's next signed-megawatt count is the other checkpoint 15. At the February 2026 pace of conversion, AEP either spends $100 billion against less load than planned, or slows the build and the growth promise slips 15. Wall Street underwrote the megawatts; the townships are underwriting the right of way.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Power

    FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant

    The approval came with a surcharge that bills West Virginia ratepayers while the plant is built, and FirstEnergy answered by lifting its five-year plan to $38 billion, its growth target to 7% to 9%, and its equity ask to $2.8 billion. No large-load customer is named in the filing.