An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan
AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.
Vincent Jiangthree-minute read
A county board asks AEP to stop advancing the line
On Nov. 17 the Steuben County Board of Commissioners asked AEP Transmission+0.02% — AEP Transmission, up 0.02 percent today to suspend the Lulu-Sorenson project until independent research covers public health, the environment, property values and quality of life 1. The line would run about 75 miles between the Sorenson substation and the Indiana-Michigan state line, on towers up to 175 feet tall; no route is picked, and one is due by late February 2027 12.
Becca Leider, a registered nurse whose land sits in the path, calls the fight "all encompassing" 2. DeKalb County's board voted unanimously on Nov. 9 to oppose it, after more than 1,000 people attended the September open houses 67.

The line carries a $100 billion promise
American Electric Power, the Columbus utility that runs the country's largest transmission network, told investors on Oct. 28 it will spend $100 billion from 2027 through 2031, lifting rate base, the pool of regulated assets it earns on, to $162 billion 3.
AEP's capital spending has outrun operating cash flow in 10 of the last 12 quarters
- Capital spending
- Operating cash flow
Data
| Capital spending | Operating cash flow | |
|---|---|---|
| Q4 '23 | $1.61B | $1.34B |
| Q1 '24 | $1.76B | $1.44B |
| Q2 '24 | $1.56B | $1.46B |
| Q3 '24 | $1.85B | $2.17B |
| Q4 '24 | $2.86B | $1.73B |
| Q1 '25 | $2.1B | $1.45B |
| Q2 '25 | $3.28B | $1.22B |
| Q3 '25 | $2.28B | $2.46B |
| Q4 '25 | $4.25B | $1.81B |
| Q1 '26 | $3.8B | $1.52B |
| Q2 '26 | $3.13B | $1.9B |
| Q3 '26 | $4.58B | $2.35B |
The plan rests on 84 gigawatts of incremental contracted load by 2031, 15 gigawatts of it signed in the third quarter alone, and carries guidance for 9% to 11% annual operating-earnings growth with up to $21 billion of bill offsets for residential customers 3. Evercore−4.80% — Evercore, down 4.80 percent today ISI kept its Outperform rating on Nov. 13 with a $154 target, 19% above the $129.18 close 4.
AEP's $100 billion plan averages $20 billion a year after capex jumped 48% in 2025
The plan averages roughly 1.7 times AEP's 2025 spend, every year
- Capital spending
- Estimate
Data
| Capital spending | |
|---|---|
| FY2020 | $6.25B |
| FY2021 | $6.43B |
| FY2022 | $7.88B |
| FY2023 | $7.53B |
| FY2024 | $8.03B |
| FY2025 | $11.91B |
| 2027-31 avg (plan) (estimate) | $20B |
The megawatt queue is thinning
The permission problem shows up first in AEP Ohio's own numbers. Developers requested more than 30,000 megawatts of capacity; once the utility began charging for engineering studies and requiring binding commitments, 13,023 megawatts went to study, and by February 2026 only 5,642 megawatts had signed contracts 58. Another 12,219 megawatts were contracted before the data-center tariff took effect in July 2025 58. On Nov. 3, voters favored data-center restrictions in 40 of 41 local ballot contests, five of them outright bans 59. In Oklahoma, opponents of AEP's Branson 345-kilovolt overlay handed state regulators a petition with more than 1,400 signatures 10.
AEP Ohio's data-center queue: 30,000-plus MW asked, 5,642 MW signed by February 2026
Fewer than one in five requested megawatts reached a signed contract
Data
| Value | |
|---|---|
| Capacity requested | 30,000 MW |
| Went to paid studies | 13,023 MW |
| Signed under tariff | 5,642 MW |
| Contracted pre-tariff | 12,219 MW |
The contracts, not the county votes, decide who pays
AEP's Ohio tariff pushes the risk back onto developers: minimum monthly bills, full reimbursement of buildout costs on cancellation or a year's delay, and exit fees worth three years of minimum charges 8. Federal regulators are weighing the same protections for the regional grid, with filings due Dec. 16 8. AEP says it has "invested time engaging with property owners, local officials and community members" 10. County boards, DeKalb's president conceded, have no authority to stop a line 6. The question of who funds the plan was traced in The Inference's October reporting 6.
The route and the signed megawatts are the checkpoints
The route is named by late February 2027, and AEP Ohio's next signed-megawatt count is the other checkpoint 15. At the February 2026 pace of conversion, AEP either spends $100 billion against less load than planned, or slows the build and the growth promise slips 15. Wall Street underwrote the megawatts; the townships are underwriting the right of way.