Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted
Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.
Vincent Jiangthree-minute read
A hearing, and still no price tag
Ameren+0.35% — Ameren, up 0.35 percent today Missouri took its West Alton Energy Center, 2,100 megawatts of combined-cycle gas in three units beside the Sioux coal plant in St 1. Charles County, to a public hearing at St. Charles Community College on November 18, with construction planned from June 2027 and the units finished one by one through 2031. 1 There the utility pressed its request to bill customers for the plant while it is being built, and the project's cost is still redacted in its state filings 2, the gap The Inference flagged in previewing the hearing on November 10.
Ameren wants to bill financing costs while it builds
The mechanism, legalized in Missouri in 2025, collects financing costs from customer bills during construction rather than after the plant opens. 3 Ameren says waiting until completion means more borrowing over a longer period, and it has asked the Missouri Public Service Commission for an order by May 2027. 3 The statute, as quoted from the Missouri Revisor of Statutes, withholds the financing from any resource the commission has not approved and sets the allowable amount only in a separate rate proceeding. 2 Liberty, a smaller Missouri utility, has already received it for a gas plant of its own. 2
The consumer advocate says the load is not committed
John Kleiser of the Office of Public Counsel, Missouri's consumer advocate, told the hearing the plant primarily serves "high-demand customers" such as data centers, and the office disputes that the state needs it. 12 Its chief economist, Geoff Marke, testified that absent firm data-center commitments covering entire project costs, he does "not believe it is prudent for Ameren Missouri to move forward," warning against "overbuilding for a wildly unpopular industry that is seemingly bleeding money." 4
Ameren counts 2.8 gigawatts as signed
Rob Dixon, Ameren Missouri's vice president of regulatory and legislative affairs, answered that Missouri must provide power "to everyone who participates in the economy... and that includes data centers." 1 The utility points to 2.8 gigawatts of signed contracts, Google and Amazon−2.75% — Amazon, down 2.75 percent today among them, 5 which The Inference reported in September, and $21 million of projected base-rate savings for customers over two years. 2
West Alton is sized against load that is mostly not yet under contract
The plant nearly matches Ameren's signed book; twice that load sits behind it unsigned.
Data
| Value | |
|---|---|
| Completed interconnection studies | 4.4 GW |
| Signed electric service agreements | 2.8 GW |
| Projects with construction agreements | 1.2 GW |
The financing ruling moves a $38.1 billion plan
West Alton sits inside a $38.1 billion capital plan for 2027 through 2031, more than 20 percent above its predecessor, 67 one Ameren says will grow rate base, the asset base on which a regulated utility earns its allowed return, about 13.3 percent a year against 8 to 10 percent annual growth in earnings per share. 6 About $5 billion of new equity backs it, $1.7 billion already sold forward, 7 part of the buildout The Inference traced with the September signed-demand story. Nine-month capital expenditure ran $4.09 billion against $3.12 billion a year earlier. 6
Ameren's capex has outrun its operating cash flow in all 12 quarters
Spending beat cash from operations in every one of the last 12 quarters.
- Capital expenditure
- Operating cash flow
Data
| Capital expenditure | Operating cash flow | |
|---|---|---|
| Q4 '23 | $1.14 B | $0.53 B |
| Q1 '24 | $0.9 B | $0.49 B |
| Q2 '24 | $1.03 B | $0.56 B |
| Q3 '24 | $1.16 B | $0.9 B |
| Q4 '24 | $1.32 B | $0.82 B |
| Q1 '25 | $1.08 B | $0.43 B |
| Q2 '25 | $1.07 B | $0.86 B |
| Q3 '25 | $0.99 B | $1.1 B |
| Q4 '25 | $1.04 B | $0.96 B |
| Q1 '26 | $1.6 B | $0.42 B |
| Q2 '26 | $1.08 B | $0.77 B |
| Q3 '26 | $1.44 B | $1 B |
Either way the plant gets built, the ruling decides who pays
On the statute's requirement of a separate rate proceeding to set any amount, the commission could approve the plant and still refuse the financing; that is a reading of the text Hoodline quotes, not a settled ruling. 2 A grant puts construction on bills from the first shovel.
A refusal leaves Ameren carrying the plant on its balance sheet and its equity plan until a rate case prices it. Ameren asked for its order by May 2027, 3 the month its Missouri rate-case decision is expected. 7 If Missouri approves the plant, either financing outcome still builds it; the ruling decides who pays while it does.