Power

Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

Vincent JiangVincent Jiangthree-minute read
Share
A worker in an Ameren Missouri safety vest watches as a crane lowers a shrouded turbine component at a gas plant construction site
A turbine component is set at Ameren Missouri's Castle Bluff gas plant site in June 2026. The utility is asking Missouri regulators to let it bill customers for financing costs on a larger, 2,100 MW gas plant at West Alton while that one is built.

A hearing, and still no price tag

Ameren+0.35% — Ameren, up 0.35 percent today Missouri took its West Alton Energy Center, 2,100 megawatts of combined-cycle gas in three units beside the Sioux coal plant in St 1. Charles County, to a public hearing at St. Charles Community College on November 18, with construction planned from June 2027 and the units finished one by one through 2031. 1 There the utility pressed its request to bill customers for the plant while it is being built, and the project's cost is still redacted in its state filings 2, the gap The Inference flagged in previewing the hearing on November 10.

Ameren wants to bill financing costs while it builds

The mechanism, legalized in Missouri in 2025, collects financing costs from customer bills during construction rather than after the plant opens. 3 Ameren says waiting until completion means more borrowing over a longer period, and it has asked the Missouri Public Service Commission for an order by May 2027. 3 The statute, as quoted from the Missouri Revisor of Statutes, withholds the financing from any resource the commission has not approved and sets the allowable amount only in a separate rate proceeding. 2 Liberty, a smaller Missouri utility, has already received it for a gas plant of its own. 2

The consumer advocate says the load is not committed

John Kleiser of the Office of Public Counsel, Missouri's consumer advocate, told the hearing the plant primarily serves "high-demand customers" such as data centers, and the office disputes that the state needs it. 12 Its chief economist, Geoff Marke, testified that absent firm data-center commitments covering entire project costs, he does "not believe it is prudent for Ameren Missouri to move forward," warning against "overbuilding for a wildly unpopular industry that is seemingly bleeding money." 4

Ameren counts 2.8 gigawatts as signed

Rob Dixon, Ameren Missouri's vice president of regulatory and legislative affairs, answered that Missouri must provide power "to everyone who participates in the economy... and that includes data centers." 1 The utility points to 2.8 gigawatts of signed contracts, Google and Amazon−2.75% — Amazon, down 2.75 percent today among them, 5 which The Inference reported in September, and $21 million of projected base-rate savings for customers over two years. 2

West Alton is sized against load that is mostly not yet under contract

The plant nearly matches Ameren's signed book; twice that load sits behind it unsigned.

0 GW1 GW2 GW3 GW4 GW5 GWCompleted interconnection studies4.4 GWSigned electric service agreements2.8 GWProjects with construction agreements1.2 GWWest Alton plant capacity, 2.1 GW
Data
Value
Completed interconnection studies4.4 GW
Signed electric service agreements2.8 GW
Projects with construction agreements1.2 GW
Nameplate gigawatts by stage of Ameren Missouri's large-load queue, per Ameren's Q3 2026 call materials as reported by Midwest CRE Advisors; reference line is West Alton's 2.1 GW capacity per Ameren's Missouri filing.2,5

The financing ruling moves a $38.1 billion plan

West Alton sits inside a $38.1 billion capital plan for 2027 through 2031, more than 20 percent above its predecessor, 67 one Ameren says will grow rate base, the asset base on which a regulated utility earns its allowed return, about 13.3 percent a year against 8 to 10 percent annual growth in earnings per share. 6 About $5 billion of new equity backs it, $1.7 billion already sold forward, 7 part of the buildout The Inference traced with the September signed-demand story. Nine-month capital expenditure ran $4.09 billion against $3.12 billion a year earlier. 6

Ameren's capex has outrun its operating cash flow in all 12 quarters

Spending beat cash from operations in every one of the last 12 quarters.

  • Capital expenditure
  • Operating cash flow
$0 B$0.5 B$1 B$1.5 B$2 BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1.44 B
Data
Capital expenditureOperating cash flow
Q4 '23$1.14 B$0.53 B
Q1 '24$0.9 B$0.49 B
Q2 '24$1.03 B$0.56 B
Q3 '24$1.16 B$0.9 B
Q4 '24$1.32 B$0.82 B
Q1 '25$1.08 B$0.43 B
Q2 '25$1.07 B$0.86 B
Q3 '25$0.99 B$1.1 B
Q4 '25$1.04 B$0.96 B
Q1 '26$1.6 B$0.42 B
Q2 '26$1.08 B$0.77 B
Q3 '26$1.44 B$1 B
Quarterly capital expenditure and cash from operations, US$ billions, from Ameren's SEC filings, Q4 2023 through Q3 2026. Capex is shown as positive spending and the two series are not netted.8

Either way the plant gets built, the ruling decides who pays

On the statute's requirement of a separate rate proceeding to set any amount, the commission could approve the plant and still refuse the financing; that is a reading of the text Hoodline quotes, not a settled ruling. 2 A grant puts construction on bills from the first shovel.

A refusal leaves Ameren carrying the plant on its balance sheet and its equity plan until a rate case prices it. Ameren asked for its order by May 2027, 3 the month its Missouri rate-case decision is expected. 7 If Missouri approves the plant, either financing outcome still builds it; the ruling decides who pays while it does.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEE

Reader comments

0 comments

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Power

    FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant

    The approval came with a surcharge that bills West Virginia ratepayers while the plant is built, and FirstEnergy answered by lifting its five-year plan to $38 billion, its growth target to 7% to 9%, and its equity ask to $2.8 billion. No large-load customer is named in the filing.

    Power

    Entergy's gas plant for Meta hits $1.755 billion, 63% over estimate

    A redacted Louisiana filing puts the first hard number on construction inflation in power built for a single AI customer, weeks before regulators vote on seven more Entergy plants under a fast-track that waives lowest-cost rules. December decides whether the bill lands on Meta, on Louisiana ratepayers, or on the growth story behind Entergy's premium multiple.

    Power

    Meta walks back its 2030 net-zero deadline after emissions rose 45% on AI power demand

    Meta is the first of the giant cloud-and-AI data-center operators, the hyperscalers, to reopen a climate deadline, blaming AI power demand that grids cannot feed. The gas plants replacing the pledge face a Louisiana vote in December, and the bill lands on Meta's capex first, then on Entergy ratepayers if the AI tenant walks.

    Subscribe to TheInference for free