Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million

Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
Barry Lam, Quanta Computer's founder and chairman, right, beside then Taiwanese vice president Lai Ching-te as Lai gestures over a server chassis
Barry Lam, right, Quanta Computer's founder and chairman, with then vice president Lai Ching-te examining server hardware at a March 2024 ICT industry briefing in Taipei. Quanta's AI-server assembly now includes buying its own on-site power.

A third order, a week after a Tennessee lease

On November 25, 2026 Quanta Manufacturing Nashville, the US subsidiary of Quanta Computer+7.66% — Quanta Computer, up 7.66 percent today (2382.TW), a Taiwanese contract manufacturer 3, disclosed a $367 million purchase of fuel-cell microgrid systems, which generate electricity on site, from Bloom Energy+0.38% — Bloom Energy, up 0.38 percent today, a fuel-cell maker 12. About $249.9 million covers its California operations and $117.1 million Tennessee, technical services included 1. Quanta's investor page lists the filing as a machinery acquisition on behalf of a subsidiary 4. On November 18 the same unit leased a 252,072-square-foot building in La Vergne, Tennessee, for 62 months at about $14.9 million 5.

Three orders now equal three-quarters of the 2027 budget

Two earlier purchases sit behind this one: $79.75 million in October 2024, and $502 million on December 30, 2025, for the B16, B18 and B19 buildings in California 12. Together the three orders come to about $950 million 1.

Quanta's three Bloom Energy fuel-cell orders total about $950 million in 25 months

Three orders in 25 months took Quanta's own-power commitments to about $950 million

$0M$200M$400M$600MOct 2024Dec 2025Nov 2026Third order in 25 months
Data
Disclosed purchase value
Oct 2024$79.75M
Dec 2025$502M
Nov 2026$367M
Disclosed purchase values in US$ millions by Quanta Manufacturing Nashville, as reported November 26, 2026 (sum $948.75 million); the December 2025 order covered the B16, B18 and B19 buildings in California. Sources [1], [2].1,2

At the November 26, 2026, rate of 32.9 New Taiwan dollars to the US dollar 6, that is roughly NT$31 billion. Quanta's 2027 capital budget is NT$40 to 45 billion, after NT$34.6 billion spent in the first nine months of 2026, nearly 80 percent of it in California and Thailand 1. The purchases are disclosed; no filing says how the systems are booked, whether that budget already holds them, or when payment falls due.

Record revenue, a gross margin down to 4.75 percent

Quanta's November 11 results showed third-quarter revenue of NT$1.12 trillion, up 125.2 percent from a year earlier, and net profit of NT$28.42 billion, up 73 percent 7. Gross margin fell to 4.75 percent from 5.02 percent in the second quarter and 6.85 percent a year earlier 3, a slide Quanta attributed to product mix and more customer-specified components 7. Servers were over 80 percent of revenue and are guided to 85 to 90 percent in 2027 73. Operating profit still rose 75.3 percent to NT$32.2 billion 3. The Inference covered that quarter on November 12 8.

Denser racks mean more power inside the factory

At its November 11 earnings call Quanta said denser AI racks draw more power and need more testing inside the plant, and that customers' AI road maps run two years out 2. DigiTimes reported the next day that Quanta is steering its 2027 capital budget toward power, "the new battleground for AI server ODMs" 9. A reason like that suggests the power constraint that data centers have been meeting with on-site generation 10 has reached the factory that builds their racks. Quanta's shareholders carry that cost from a 4.75 percent gross margin 3.

Quanta's cost is 30 percent of Bloom's record quarter

For Bloom Energy (NYSE: BE), the San Jose fuel-cell maker, the order is about 30 percent of its record $1.24 billion third-quarter revenue 1011. It follows a 900 megawatt agreement with the data-center operator NTT DATA, signed on November 5 1012, and Bloom raised its 2026 revenue guidance to $4.4 to 4.6 billion on October 22 11. Morgan Stanley+0.40% — Morgan Stanley, up 0.40 percent today kept an Overweight rating and a $335 target on Bloom on November 24, counting more than 2.8 gigawatts of deployment opportunities since late September 1314, a note The Inference covered on November 25 15.

Four black Bloom Energy Server cabinets in a blue-lit display room
Bloom Energy servers, the on-site generators Quanta Manufacturing Nashville ordered for its California and Tennessee sites. Bloom's third-quarter revenue of $1.24 billion was a record.Bloom Energy

Bloom's revenue has more than doubled in a year, to a record $1.24 billion

$0B$0.5B$1B$1.5BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26Record quarter, 2.4x a yearearlier
Data
Bloom Energy revenue
Q2 '24$0.34B
Q3 '24$0.33B
Q4 '24$0.57B
Q1 '25$0.33B
Q2 '25$0.4B
Q3 '25$0.52B
Q4 '25$0.78B
Q1 '26$0.75B
Q2 '26$1.07B
Q3 '26$1.24B
Bloom Energy revenue by quarter, in US$ billions, from its SEC filings. The third quarter of 2026, at $1.236 billion, is the record against which Quanta's $367 million order is measured. Source [16].16

Capex against margin decides 2027

Watch whether Foxconn, Wistron and Inventec, which compete with Quanta for the same AI-server design wins 8, file their own power purchases, and how fast Bloom's fourth-quarter report, expected in February 12, turns the $367 million into revenue. The test for Quanta is whether 2027 capital spending overshoots NT$45 billion while gross margin holds above 4.75 percent as Nvidia's−2.52% — Nvidia, down 2.52 percent today next-generation Vera Rubin racks ramp in the first quarter of 2027 8.

Sources

  1. 1EconoTimes, "Quanta Announces About $367 Million in U.S. Fuel-Cell Microgrid Purchases", 26 November 2026
  2. 2TokenPost, "Quanta Announces $367 Million Fuel-Cell Microgrid Purchases", 26 November 2026
  3. 3Crypto Briefing, "Quanta Computer posts record revenue as AI servers squeeze gross margin to 4.75%", 11 November 2026
  4. 4Quanta Computer investor site, News list: "2026.11.25 Announcing Machinery and Equipment Acquisition on Behalf of Subsidiary"; "2026.11.18 Announcing the Acquisition of Right-of-Use Assets", accessed 26 November 2026
  5. 5ad-hoc-news, "Quanta Computer stock: Tennessee lease adds US$14.9 million commitment", 25 November 2026
  6. 6Yahoo Finance, USD/TWD (TWD=X) quote, 32.945 as of 26 November 2026
  7. 7ad-hoc-news, "Quanta-Aktie: Umsatz springt im dritten Quartal um 125,2 Prozent", 25 November 2026
  8. 8The Inference, "Quanta Computer revenue rose 125% to NT$1.12 trillion as it seeks to shift inventory to AI customers", 12 November 2026
  9. 9DigiTimes, "Quanta shifts 2027 capex toward power, the new battleground for AI server ODMs", 12 November 2026 (headline and lede only; remainder paywalled)
  10. 10ad-hoc-news, "Bloom Energy stock: Quanta unit orders $367 million of microgrids", 25 November 2026
  11. 11Bloom Energy, SEC Form 8-K Exhibit 99.1, "Bloom Energy Reports Record Third Quarter 2026 Financial Results and Raises Full Year 2026 Guidance", filed 22 October 2026
  12. 12Yahoo Finance (TIKR), "Bloom Energy Signs Its Largest Deal Abroad: 900 MW for NTT Data Starting in 2027", 24 November 2026
  13. 13TradingView, "Key facts: Quanta Unit's $367M Deal; Morgan Stanley Keeps $335 Target", 26 November 2026
  14. 14Stocktwits, "BE Stock Slumps After AI-Driven Gains: This Analyst Sees 'An Attractive Entry Point'" (Morgan Stanley note of 24 November 2026), 24 November 2026
  15. 15The Inference, "Bloom Energy locks $123 million of outsourced fuel-cell supply through 2027 in a Korean filing", 25 November 2026
  16. 16Bloom Energy, quarterly figures from its SEC filings, retrieved 26 November 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BE

Reader comments

0 comments

    Power

    CPUC lets PG&E bill customers $456 million early as $8.6 billion of rate requests wait

    The commission granted the first slice on November 19 while 11 more requests worth about $8.6 billion through 2030 wait behind it, and the same day's undergrounding rules shrank the capital program meant to justify the spending.

    Power

    Entergy CEO Drew Marsh says data centers will spare existing customers $7.5 billion

    The figure, given to investors on November 24, appears nowhere in Entergy's latest quarterly filing. Louisiana's utility commission is expected to vote in December on $12.9 billion of gas plants for Meta, and holders of ETR are underwriting that the contract delivers what the forecast assumes.

    Power

    ENGIE adds 330 km of heat networks fed partly by data centers, and France's left wants to freeze them

    ENGIE's newest French heat networks draw part of their heat from data centers, the same build-out one presidential campaign wants to freeze and the same campaign wants to nationalize ENGIE itself. Investors in the cooling pipeline have to price a political answer, not just a construction schedule.

    Power

    Westinghouse ordered AP1000 demonstration pieces from BWXT, with no price and no named reactor

    A 6.7% jump priced BWXT into the AP1000 supply chain, but the purchase orders cover only demonstration pieces, with no disclosed value, no delivery date and no commitment to buy components for any reactor build. The paying customer is still Washington.

    Power

    Investors sue NuScale as quarterly revenue falls to $281,000 and the stock trades below its cash pile

    Quarterly revenue has fallen to $281,000, the equity now trades below its own $1.86 billion cash pile, and the January 11, 2027, lead-plaintiff deadline puts class-period holders on the clock.

    Power

    X-energy wins NRC permit for four reactors at Dow's Texas plant, first US nuclear build at an industrial site

    The NRC's first high-temperature gas-cooled permit in over 50 years proves the Xe-100 can be built at a chemical plant. The money gate now sits with Dow in 2027, while X-energy burns $123 million a quarter and the whole nuclear sector de-rates.

    Subscribe to TheInference for free