Power

X-energy wins NRC permit for four reactors at Dow's Texas plant, first US nuclear build at an industrial site

The NRC's first high-temperature gas-cooled permit in over 50 years proves the Xe-100 can be built at a chemical plant. The money gate now sits with Dow in 2027, while X-energy burns $123 million a quarter and the whole nuclear sector de-rates.

Richard TangRichard Tangtwo-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Richard Tang. How we work

Share
NRC Chairman Ho K. Nieh speaking in a blue suit and red tie on a lit stage at the American Nuclear Society annual conference
NRC Chairman Ho K. Nieh keynoting the American Nuclear Society annual conference in Denver. The commission's construction permit for X-energy's four Xe-100 reactors at Dow's Seadrift plant is the first advanced reactor cleared to build at a US industrial site.

The Nuclear Regulatory Commission has approved a construction permit for four X-energy$1B — X-energy, private, latest valuation $1B Xe-100 reactors at Dow's+2.85% — Dow, up 2.85 percent today Seadrift, Texas chemical plant, the first advanced reactor authorized to build at a US industrial site and the first high-temperature gas-cooled reactor permit in more than 50 years 17. That is the technology clearing its hardest early test. It is not the start of construction, and it is not the money: Dow weighs a preliminary investment decision only in 2027, with first power in the early 2030s 17.

The regulator was the bottleneck, and it cleared

The permit proves the Xe-100 can be safely sited inside a working chemical complex, and NRC Chairman Ho K 7. Nieh called the review proof that advanced designs can move on predictable 18-month timelines 7. Four reactors, 80 megawatts each, up to 320 megawatts plus high-temperature steam for 60 years 1. This is the link that was stuck: for decades, the regulator was the bottleneck for any design outside the light-water fleet. It is no longer. The limiting link is now capital, and it sits with Dow.

The permit does not pay for the plant

X-energy's third quarter shows why that gate matters. Sales, mostly Xe-100 design work, nearly doubled year over year to $51.6 million, but the company still burned $123 million of cash 3. It holds $1.56 billion, roughly 13 quarters of runway, with no debt, and the Department of Energy's Advanced Reactor Demonstration Program reimburses about half the work, $618 million so far 3. The design is de-risked; the financing clock is running.

The market is pricing the wait, not the design

Guggenheim cut its XE target to $42 on valuation on November 20; the stock sits 72% below its 52-week high 34. Rival NuScale, holding $1.9 billion of cash against $281,000 of quarterly revenue, fell 40% in a month to a new low 5, and the slide hit fuel names too: Centrus's−0.65% — Centrus, down 0.65 percent today $7 billion backlog is roughly 77% contingent on construction milestones like this one 6. The whole sector is repricing the distance between a permit and a financed plant.

Two nuclear developers hold billions in cash against revenue close to zero

  • Cash on hand
  • Most recent quarter's revenue
$0M$500M$1,000M$1,500M$2,000MX-energyNuScale Power$1,900M$1,560M
Data
Cash on handMost recent quarter's revenue
X-energy$1,560M$51.6M
NuScale Power$1,900M$0.28M
Cash on hand and most recent reported quarterly revenue, in $ millions. X-energy holds $1.56 billion against $51.6 million of third-quarter revenue; NuScale Power holds $1.9 billion against $281,000 of quarterly revenue, which rounds to zero on this scale. Sources: Trefis (3), TIKR (5).3,5

X-energy is standardizing before it scales

X-energy answered on November 22 with a second nuclear-island engineering contract with Fluor, this time for Energy Northwest's Cascade project near Richland, Washington, carrying first-project learnings into a second-of-a-kind plant 28. That is the right work: standardizing before scale is how a first-of-a-kind build ever becomes cheap. The permit moved the regulatory link. The next decisive move is Dow's 2027 decision, and the people building project readiness in between, Fluor, the supply chain, the fuel plant, are the ones earning the right to be paid for it 28.

Sources

  1. 1ConstructConnect News, NRC Approves Construction Permit for Dow, X-Energy Texas Reactor Project, November 2026
  2. 2Energies Media, X-energy taps Fluor for engineering work on proposed Washington advanced nuclear project, 22 November 2026
  3. 3Trefis, Who Is Paying For X-Energy's Cash Burn?, 18 November 2026
  4. 4Investing.com, Guggenheim cuts X-Energy stock price target to $42 on valuation, 20 November 2026
  5. 5TIKR, NuScale Is Down 40% in a Month and Just Hit a New 52-Week Low, 21 November 2026
  6. 6AInvest, Centrus Energy: The $180 Fair Value Is a 2029 Bet, Not a Margin of Safety, November 2026
  7. 7Power Engineering, X-energy receives first approval for advanced nuclear at an industrial site, 10 November 2026
  8. 8World Nuclear News, X-energy selects Fluor for second Xe-100 project, 6 November 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading LEU

Reader comments

0 comments

    Power

    Investors sue NuScale as quarterly revenue falls to $281,000 and the stock trades below its cash pile

    Quarterly revenue has fallen to $281,000, the equity now trades below its own $1.86 billion cash pile, and the January 11, 2027, lead-plaintiff deadline puts class-period holders on the clock.

    Power

    Bloom Energy locks $123 million of outsourced fuel-cell supply through 2027 in a Korean filing

    A Korean regulatory filing disclosed November 25, for a purchase order dated November 24, shows Bloom locking outsourced fuel-cell production at Seojin System's Vietnam plant on 45-day payment terms, while the stock trades below half its $351.28 peak and bulls and bears fight over the same $181 million of quarterly cash burn.

    Power

    Pennsylvania's consumer advocate asks regulators to bill data centers, not PPL customers, $157 million

    The complaint against PPL Electric would move a $157 million power-line bill onto the data center that caused it, and this week Gov. Shapiro's office, environmental groups, residents, Amazon and the industry coalition all formally picked sides. The commission's ruling, due July 2027, will set the price of connecting every future Pennsylvania data center.

    Power

    Vistra CEO calls data-center power queues overstated as Texas logs 194 GW of requests against a 91 GW peak

    James Burke says the queues behind America's data-center load forecasts are inflated by developer speculation, and wants higher collateral and take-or-pay transmission contracts. The filings behind the words show a company split in two: contracted nuclear megawatts that need no queue, and a merchant 2028 with a fifth of its output unsold.

    Power

    PG&E customers prepay for wildfire costs, but the $18 billion fund for new fires is empty

    Ratepayers prepay wildfire costs today while shareholders' $300 million a year into the new $18 billion account does not start until 2029, and the account sunsets if never activated. That leaves PG&E's equity, already rated below investment grade, as the first loss on any major new fire.

    Power

    Google offers to pay American Electric Power $10.8 million to speed power to its Columbus data center

    The first voluntary, corporate-funded transmission upgrade on a US regulated grid now sits before Ohio regulators. How they rule decides whether hyperscalers can buy speed on the grid, and whose bills fund the rest of AEP's $100 billion buildout.