Entergy says Google's $550.6 million battery build costs ratepayers zero, and the Arkansas PSC tests it

Entergy filed Thursday to build $550.6 million of batteries for Google's West Memphis campus and told regulators other customers will pay nothing. The record so far, including a regulator-found $308 million cost shift on the solar deal, gets its first public test next week.

Richard TangRichard Tangthree-minute read
Share
Entergy Chair and Chief Executive Officer Drew Marsh in a company headshot
1 / 6Slide 1 of 6
Entergy Chair and Chief Executive Officer Drew Marsh, whose company filed Thursday to build $550.6 million of batteries for Google's West Memphis campus

On Thursday, Entergy−0.84% — Entergy, down 0.84 percent today Arkansas, the utility that will supply Google's new data center campus at West Memphis, asked the state's Public Service Commission to approve two battery storage systems for the site's expansion: a 250-megawatt unit near Osceola and a smaller 100-megawatt unit in Hot Spring County 1. The combined construction cost is $550.6 million. 1 Google−3.94% — Google, down 3.94 percent today, building a $4 billion campus there, has committed in Entergy's filings to cover the construction costs, and the utility calculates the bill impact at "zero dollars across all customer classes." 1

Next Wednesday and Thursday, the commission holds public evidence hearings in Entergy's pending rate case, the first forum where that arithmetic is tested under oath. 1

The zero-dollar figure is an Entergy projection

The promise rests on the utility's calculation that Google's expected payments will exceed the projects' revenue requirement. 1 Entergy also chose to fold the battery costs into its formula rate plan, the mechanism that lets it raise rates up to 4% a year without a formal case, rather than a Google-specific rider that would put the project's costs on a line of their own. 1

The same structure has already produced one shortfall: state regulators have found that customers will pay $308 million more for Cypress Solar than if Google's money had gone to construction. 6 Cypress is the $1.6 billion solar-and-battery field feeding Google's campus. 1

Thursday's battery build is a third the size of Cypress Solar, whose costs shifted $308 million

00.511.52Cypress Solar build$1.6BBattery build filed Thursday$550.6MRegulator-found cost shift$308M
Data
Value
Cypress Solar build$1.6B
Battery build filed Thursday$550.6M
Regulator-found cost shift$308M
Project costs and the regulator-found cost shift, USD billions. Cypress and the battery build are figures from Entergy's filings; the $308 million is the cost shift Arkansas regulators found on Cypress Solar. Sources: Arkansas Democrat-Gazette, 22 and 30 October 2026.1,6

The record so far: ratepayers pay first

Residential bills already carry an extra $5.77 a month on average, charged since June under a state law that lets Entergy bill customers while three projects are still under construction. 1 A February rate filing could add another $1.16 a month, and the commission hears it next week. 1 The same week's news shows both ends of the pattern. Entergy Louisiana began a $2 million shareholder-funded bill-credit program for customers below the cost of living. 3 Entergy Mississippi announced a gas plant costing more than $2 billion, which it says serves existing customers. 4

Capex has more than doubled while cash flow lagged

For investors, the weight of this build-out shows in Entergy's filings: capital spending has more than doubled in two years while operating cash flow has not, and free cash flow has been negative in most recent quarters.

Entergy's capital spending has outrun its operating cash flow

  • Capital spending
  • Operating cash flow
$0B$1B$2B$3BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '26$2.83B$1.89B
Data
Capital spendingOperating cash flow
Q1 '24$1.27B$0.52B
Q2 '24$1.19B$1.03B
Q3 '24$1.56B$1.56B
Q4 '24$1.95B$1.38B
Q1 '25$1.75B$0.54B
Q2 '25$2.05B$1.26B
Q3 '25$1.93B$2.14B
Q4 '25$2.22B$1.22B
Q1 '26$2.4B$0.83B
Q2 '26$2.83B$1.89B
Quarterly capital expenditure and operating cash flow, USD billions, Q1 2024 to Q2 2026. Source: Entergy quarterly figures from SEC filings.5

The board raised its quarterly dividend 6.3% the same day the battery filing went in. 2 The stock trades near 28 times trailing earnings, well above its five-year median, and insiders have been net sellers to the tune of about $13 million over the past year. 2

Whether Google pays gets decided in public next week

I am firmly pro-AI, and Arkansas is right to court these data centers. But the deal only works for everyone else if the AI customer actually pays, and Entergy's structure sends ratepayer bills out first and Google's payments later, which is how the Cypress gap opened. Next week's hearings will test the battery deal's math in public for the first time. Judge ETR on one question: do the bills go out before Google's payments arrive?

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading ETR

Reader comments

0 comments

    Power

    Bloom Energy's newest billion-dollar NTT DATA and Google power deals ship nothing until 2027

    The stock trades at 39.2x forward earnings, above GE Vernova and Enphase, yet the NTT DATA 900 MW order and the AEP plant for Google ship nothing until 2027 and 2028 while Q3 cash flow ran negative. The de-rating is a bet on when signed megawatts become invoiced ones.

    Power

    Pinnacle West files 25-year deal making TSMC fund its own power ahead of a December rate decision

    The 25-year contract is the template for every data-center deal that follows it, and it lands before two Arizona regulators elected three days earlier on bill anger. Pinnacle West's growth story now rides on convincing them.

    Power

    Energy Department paid BWXT $68 million for uranium work as its first US new-build order slips to 2027

    The payment has sat unremarked in federal data for eleven days, and the one tracker that noticed coded the award to L3Harris. It is the funded half of BWXT's growth paying out in cash, while the commercial half, the AI-power half, waits on an order that slipped to 2027.

    Power

    CPUC proposal would cut PG&E's 5,000-mile undergrounding plan to about 1,100 miles

    A judge has moved $1.7 billion of wildfire costs onto California ratepayers, and on November 19 the commission votes on a cost test PG&E says would strike 3,900 miles from the capital it earns on. The utility has already cut $2 billion from its own 2027 plan.

    Power

    AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize

    AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.

    Power

    Southern Company prices $1.75B of equity units at 8.625%, forcing stock buys by 2029

    The units pay 8.625% a year and force buyers to take Southern stock by December 2029, funding a data-center build that Georgia's newly Democratic regulators were elected to police.

    Subscribe to TheInference for free