A day after beating estimates and lifting its five-year capital plan to $70 billion, Xcel Energy filed to sell up to $6 billion of stock, taking potential share supply to roughly $12 billion against $8 billion of planned equity. Shareholders are the AI buildout's first funders.

Vincent JiangVincent Jiang · 3 min read
Share
Transmission lines and wind turbines along a rural road in southwest Minnesota
1 / 6Slide 1 of 6
Transmission lines and wind turbines in southwest Minnesota. Xcel's $70 billion 2027-2031 capital plan is weighted toward renewables and grid work, funded by $8 billion of new equity and $26 billion of debt.

A $70 billion plan, then a $6 billion stock filing

On Friday, October 30, Xcel Energy+0.96% — Xcel Energy, up 0.96 percent today signed an agreement letting Barclays−3.55% — Barclays, down 3.55 percent today, Goldman Sachs−3.64% — Goldman Sachs, down 3.64 percent today, J.P 1. Morgan and 19 other banks sell up to $6 billion of its common stock at market prices, at commissions up to 1%, live from Monday's session 1. The filing came a day after the Minneapolis utility reported third-quarter ongoing earnings of $1.52 a share, ahead of the $1.39 FactSet+2.98% — FactSet, up 2.98 percent today estimate and up from $1.24 a year earlier, on net income of $960 million against $524 million 23.

It narrowed 2026 guidance to $4.10 to $4.16, began 2027 guidance at $4.48 to $4.62, and lifted its capital plan for 2027 through 2031 to $70 billion, 17% above the prior plan, including about $7 billion for data centers already under contract 24.

About $12 billion of share supply against $8 billion of equity

The 8-K also retires the May 2026 program with $448.6 million unsold, and leaves $3.8 billion of shares promised under forward sale agreements from that program plus $2.2 billion more from an August 2025 predecessor 1. With the fresh capacity, Xcel holds roughly $12 billion of potential share sales: one and a half times the $8 billion of equity in a financing plan that also adds $26 billion of debt 2.

About $12 billion of share supply now stands against $8 billion of planned equity

$0B$2B$4B$6B$8BNew ATM program (Oct 30, 2026)$6BForwards from May 2026 program$3.8BForwards from Aug 2025 program$2.2BEquity planned for 2027-31
Data
Value
New ATM program (Oct 30, 2026)$6B
Forwards from May 2026 program$3.8B
Forwards from Aug 2025 program$2.2B
Gross capacity under the equity distribution agreement plus shares under outstanding forward sale agreements, against the equity component of the 2027-2031 financing plan. Sources: Xcel Energy 8-K, October 30, 2026; Q3 2026 earnings release.1,2

The dilution is running. Diluted shares reached 632 million against 595 million a year earlier; 10.5 million shares settled in the third quarter for $819 million; equity financing subtracted $0.10 from quarterly earnings per share 2. Capital spending has exceeded operating cash flow in all of the last 12 quarters 5.

Capex has outrun operating cash flow in all of the last 12 quarters

  • Capital expenditures
  • Operating cash flow
$0B$1B$2B$3B$4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$3.29BCapex passes $3B a quarter
Data
Capital expendituresOperating cash flow
Q4 '23$1.61B$0.97B
Q1 '24$1.54B$1.05B
Q2 '24$1.83B$1.19B
Q3 '24$1.78B$1.74B
Q4 '24$2.22B$0.66B
Q1 '25$1.99B$1.03B
Q2 '25$2.43B$1.08B
Q3 '25$3.06B$1.77B
Q4 '25$3.44B$0.21B
Q1 '26$3.02B$1.7B
Q2 '26$2.95B$1.1B
Q3 '26$3.29B$2.07B
Quarterly, USD billions, Q4 2023 through Q3 2026. Source: Xcel Energy SEC filings, compiled by The Inference.5

Bulls raised targets; the demand forecast is the soft spot

Barclays lifted its target to $94 from $85 on October 30; the 20-analyst mean is $88.58 against a $79.82 close 3. Chief Financial Officer Brian Van Abel says more than 40% of the equity is already contracted, with rate base growing about 11% a year and EPS growth above 10% on average from 2027 to 2030 6.

Chief Executive Bob Frenzel has pledged that "existing customers should not subsidize new large loads" 4; his proposed Minnesota rate freeze for 2027 and 2028 awaits a state decision requested by January 2. Midwest peer Alliant Energy+1.09% — Alliant Energy, up 1.09 percent today lifted its own capex 19% to $15.9 billion the same week, on 3.4 GW of contracted data-center demand 9.

In PJM, 42% of forecast data-center growth is already gone

The soft spot is the forecast itself: PJM's market monitor counted 4,016.9 MW of data-center load canceled or delayed by September 21, 42% of the growth that grid had projected 8.

Watch the 79.4 million unsettled forward shares, worth at least $5.8 billion 2, and whether the 4 GW data-center target closes on schedule 7. The AI buildout has already collected its first payment, and it came from the shareholder register.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading XEL

Reader comments

0 comments

    Power

    NextEra's $67 billion Dominion buy gets a Virginia ruling January 11 on who pays AI's power bill

    Rebuttal testimony is due Monday, hearings open November 17 and the State Corporation Commission's final order lands January 11. The record points to approval with conditions, and those conditions will decide whether data centers or households carry the cost of AI's load.

    Power

    Entergy says Google's $550.6 million battery build costs ratepayers zero, and the Arkansas PSC tests it

    Entergy filed Thursday to build $550.6 million of batteries for Google's West Memphis campus and told regulators other customers will pay nothing. The record so far, including a regulator-found $308 million cost shift on the solar deal, gets its first public test next week.

    Power

    DOE offers Constellation up to $5 billion to add nearly 1.1 gigawatts at running reactors for Google, Amazon

    The Department of Energy has offered Constellation up to $5 billion in conditional loans to add nearly 1.1 gigawatts at plants already running, underwritten by 20-year deals with Google and Amazon. The stock is down a quarter this year anyway, and the November 9 report is where contracted megawatts have to start showing up as earnings.

    Power

    WEC Energy's $47.5 billion grid plan bets on AI data centers, and Wisconsin's regulator holds the key

    A record $47.5 billion five-year plan, nearly half for data centers, puts Wisconsin's ratepayer protection regime and its regulators in the path of the AI buildout.

    Power

    Missouri votes Tuesday on half of Ameren's power buildout

    MISO just awarded an Ameren and NextEra consortium a $1.23 billion Iowa transmission line that no Missouri regulator votes on. The generation half of Ameren's buildout still runs through Jefferson City, where utilities are giving to campaigns five to one ahead of the November 3 midterms.

    Power

    X-energy trades near $11 as AEP says its 12-reactor Indiana project has no final decision before 2030

    On its October 28 earnings call, AEP chairman Bill Fehrman said the Amazon-backed twelve-reactor Indiana project needs only minimal AEP money now and cannot reach a final investment decision before 2030. X-energy trades near $11 against analyst targets that run from $8 to $57.