Google Is Paying to Stretch Georgia's Reactors. Southern's Stock Hit a 52-Week Low Anyway

Georgia Power has filed a tariff that puts Google, not ratepayers, behind nuclear uprates at Plants Vogtle and Hatch: about 96 megawatts and a claimed $900 million in customer benefits. Two days later, Southern's shares touched their lowest price in a year.

Vincent JiangVincent Jiangthree-minute read
Share
Steam rises from the cooling towers at Plant Vogtle, one of two Georgia nuclear plants slated for Google-funded uprates
1 / 6Slide 1 of 6
Plant Vogtle's cooling towers. Google would fund roughly 96 MW of extended power uprates at Vogtle and Hatch through a new tariff, pending Georgia PSC approval.

Stretching reactors instead of building them

Adding 96 megawatts at two nuclear plants does not require pouring concrete, just new turbines, pumps, motors and cooling systems on reactors that already exist 1. Plants Vogtle and Hatch supply about a quarter of Georgia's electricity, with units that entered service between the mid-1970s and 2024 23. On 21 September, Georgia Power said Google will fund the stretch 1.

A tariff, not a power contract

Google will support extended power uprates on Georgia Power's owned share of both plants, adding roughly 96 MW, pending Georgia Public Service Commission approval 14. It subscribes to a new Nuclear Uprate (NU-1) tariff and receives the Zero-Emission Credits on the added output; Georgia Power says the structure shields non-participating customers from the uprate's incremental costs 4. The utility projects about $900 million in customer benefits over the life of the units 14.

The market's verdict arrived in two days

On 23 September, Southern+0.11% — Southern, up 0.11 percent today shares traded as low as $83.73, a 52-week low, after closing at $85.15 the day before 5. The stock sits below both its 50-day and 200-day averages, and second-quarter revenue of $6.98 billion was up 0.1 percent from a year earlier 5. Revenue is flat and the tariff is untested; the market is not paying for either yet.

Street targets run $79 to $104; the shares just bottomed at $83.73

  • Estimate
$0$50$100$150KeyCorp$79Truist$97Barclays$98Street average$99.85BMO$10452-week low, 23 September
Data
Value
KeyCorp (estimate)$79
Truist (estimate)$97
Barclays (estimate)$98
Street average (estimate)$99.85
BMO (estimate)$104
Analyst price targets for Southern Company, in dollars per share, from reports dated 18 June to 13 August 2026; Street average is the MarketBeat consensus. Reference line marks the intraday low struck 23 September 2026. Source: Ticker Report.5

A plan, not capacity

Two regulators stand between the headline and the grid. Dockets 44280 and 56002 at the Georgia PSC carry the tariff and the request to uprate Hatch 1 and 2; Vogtle 1 and 2's uprate was approved in the 2025 Integrated Resource Plan 24. The Nuclear Regulatory Commission must still grant the license amendment any extended power uprate requires 6. Congress is pulling the same direction: the House passed the Ratepayer Protection Act 417-3, which would make data centers above 100 MW of demand cover the grid costs they trigger 7.

Projected benefits, modest megawatts

Georgia Power's Aaron Mitchell called the deal "the latest example of how large-load growth can benefit all electric customers"; Google's Lucia Tian said it keeps data center growth going "hand-in-hand with positive local impact" 4. The $900 million is projected, not booked, and reactor uprates have slipped before 6. Beside gigawatt-scale data center demand, 96 MW is modest, though the precedent is not 68. Google signed a $15.1 billion, 22-year deal for up to half of Finland's Loviisa output earlier in September 3.

The PSC, the NRC and the Senate decide it

Watch the two PSC dockets, the NRC licensing calendar for Hatch, and the Senate, where the Ratepayer Protection Act is waiting 27. Southern reports third-quarter earnings on 5 November, the first reading since the filing 9. The tariff is public, the subscription agreement is redacted in its entirety, and the megawatts are still a plan 2.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading SO

Reader comments

0 comments

    Power

    An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

    AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Subscribe to TheInference for free