Jacobs lands AEP's $37 billion transmission program, and seven states' ratepayers fund the wires

One day after AEP expanded its capital plan to $100 billion, the utility named Jacobs to deliver the $37 billion transmission program across seven states, the first named contractor on the new plan. Jacobs collects delivery fees either way; the wires are paid for through the rates of the states they cross.

Vincent JiangVincent Jiangfour-minute read
Share
A high-voltage transmission line on wooden H-frame structures crossing Wisconsin farmland
1 / 6Slide 1 of 6
High-voltage wires are what the $37 billion program buys: AEP, the owner of the nation's largest transmission system, will fund most of the buildout through the rates of the seven states its lines cross.

One day after American Electric Power−0.45% — American Electric Power, down 0.45 percent as of its last quote lifted its five-year capital plan to $100 billion, the Columbus, Ohio utility that owns the nation's largest electric transmission system gave the plan's biggest piece a name. Jacobs+0.46% — Jacobs, up 0.46 percent as of its last quote, a Dallas-based engineering firm with about $12 billion of annual revenue and roughly 47,000 employees, was selected on October 29 to provide end-to-end delivery of AEP's $37 billion transmission portfolio across Indiana, Michigan, Ohio, Kentucky, Tennessee, West Virginia and Virginia: project management, project controls, engineering and design, siting, right-of-way acquisition and environmental services 12.

Jacobs leads a team that includes ORC, GFT and RC Commonwealth, and its PA Consulting unit will support AEP's innovation work 1. WSP USA takes the four-state western portfolio, and neither firm has disclosed what its contract is worth 3. New since this site's October 29 article on the $22 billion spending add and the $5.2 billion of stock behind it: the plan's full shape, and the first named delivery partner on it 3.

Transmission drives the rate base to $162 billion

Transmission is the largest line in the plan, ahead of $36 billion for generation and $22 billion for distribution 24. AEP expects its rate base, the asset pool on which regulators let it earn a return, to grow from $87 billion this year to $162 billion by 2031, and transmission rate base to nearly double from about $37 billion to roughly $69 billion 345.

Transmission rate base nearly doubles by 2031

  • Total rate base
  • Transmission rate base
  • Estimate
$0B$50B$100B$150B$200B20262031$37B
Data
Total rate baseTransmission rate base
2026$87B$37B
2031 (estimate)$162B$69B
AEP total and transmission rate base, in billions of US dollars; 2031 figures are the company's projection, not reported results. Sources: AEP third-quarter 2026 earnings release [4]; Seeking Alpha [5]; Securities.io [2]; Utility Dive [8].4,5,2,8

On that doubling rests the guide management raised the same week: 9% to 11% operating earnings growth through 2031, up from 7% to 9%, with $22 billion of capital added and only $5.2 billion of new equity funding it 5.

Transmission is the largest slice of AEP's $100 billion five-year capital plan

$0B$10B$20B$30B$40BTransmission$37BGeneration$36BDistribution$22B
Data
Value
Transmission$37B
Generation$36B
Distribution$22B
AEP five-year capital plan for 2027 through 2031, in billions of US dollars, announced October 28, 2026. Source: AEP third-quarter 2026 earnings release [4]; Securities.io [2].4,2

The wires land on customers' bills

Transmission earns through rates, and rates land on customers. The Ohio Consumers' Counsel, the state's residential utility advocate, puts generation at about half of a typical residential bill, with transmission and distribution making up the other half 6. In March, Ohio regulators approved higher AEP Ohio transmission charges, about $7.90 a month for a household using 1,000 kilowatt-hours 6.

In September, ratepayers rallied in Ironton, Ohio, over data-center-driven grid costs: "If you don't provide extra capacity on the grid, that's going to drive up electricity rates for everybody," resident Bob McCollister told WCHS 7. Jacobs sits between the two sides, paid to deliver the program regardless of whose return the wires earn 12.

Data centers are signing up to pay for the grid

AEP signed 15 gigawatts of new load commitments in the third quarter and expects 84 gigawatts of contracted load by 2031, up 22% in one quarter 48. Of that total, 92% is tied to data centers, cryptocurrency customers included 3.

Management says fully executed take-or-pay contracts, in which large customers pay fixed costs whether or not they draw the power, are now expected to offset up to $21 billion for existing residential customers, up from $16 billion 4. And one of the largest projects in the plan, roughly $5 billion of 765-kilovolt lines serving SB Energy's 10.4-gigawatt Piketon data-center campus in Ohio, is contracted to be paid by that customer over 20 years, at an 11.35% base return on equity 38.

Two tickers, two bets

For Jacobs holders, the award is a multi-year revenue anchor landing on a business already accelerating: quarterly revenue growth ran at 5.1% in mid-2025, then 27% and 34.5% in the two quarters since 9. For AEP holders, the selection is execution cover. The plan's risk has shifted from winning demand to building wires on schedule.

Jacobs revenue accelerated into the AEP award, from 5% to 34.5% growth

$2.5B$3B$3.5B$4B$4.5BQ2 '24Q3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$4.08B
Data
Revenue
Q2 '24$2.88B
Q3 '24$2.96B
Q4 '24$2.93B
Q1 '25$2.91B
Q2 '25$3.03B
Q3 '25$3.16B
Q4 '25$3.29B
Q1 '26$3.7B
Q2 '26$4.08B
Jacobs Solutions quarterly revenue in billions of US dollars, fiscal quarters ended June 28, 2024, through June 26, 2026, per SEC filings. Year-over-year growth was 5.1% in the June 2025 quarter, 27.0% in the March 2026 quarter and 34.5% in the June 2026 quarter.9

Most of the $37 billion still rides on rates

The strongest rebuttal comes from AEP itself. "AEP is committed to having new large-load customers bear the incremental system costs they create and fund the investments required to serve them," chief executive Bill Fehrman said with the results 4. SB Energy has committed $4.2 billion toward the Piketon transmission work, money AEP says is meant to shield other customers from rate increases 6.

But that covers one campus: the remaining $28 billion of the $37 billion is regional-planning and reliability spend that rides on rates 3. AEP's own release flags the concentration risk, noting that projected data-center demand "may not materialize as expected" 4.

Permits and rate cases set the schedule

Construction on the Piketon lines is expected to begin in early 2027, pending approvals from PJM, Ohio regulators and FERC 38. Jacobs's fiscal first-quarter report, covering the December quarter and due in February, will show the backlog these fees build in.

Then watch the rate cases across the seven states: Jacobs books its fees over five years, and the customers who fund the wires will pay for them for decades.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

    Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.