Malaysia moved its 21% data-center forecast from 2030 to 2050; TNB meters show 850 MW of 4.5 GW drawn

The same ministry told Parliament on November 4 that data centers would reach 21% of demand by 2030, and on November 26 that the same share arrives by 2050, while TNB's meters show 4.5 gigawatts connected and only 850 megawatts drawn. The gap lands on the merchants who built ahead of the load, YTL Power first.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
Francis Yeoh, who heads Malaysia's YTL group, in a dark suit and glasses
Francis Yeoh, who leads Malaysia's YTL group, the parent of YTL Power International. YTL Power has invested RM13.5 billion in data centers and plans a 1,200-megawatt park at Kulai in Johor, of which 298 megawatts is contracted.

On November 26, Malaysia's Ministry of Energy Transition and Water Transformation told Parliament that Peninsular electricity demand will rise from 22.6 gigawatts in 2027 to 49.8 gigawatts by 2050, about 3.5% a year, with data centers climbing from 11% to 21% of total consumption 1. Three weeks earlier, on November 4, the same ministry told Parliament data centers would reach 21% of demand by 2030, a tripling from 7% in 2026 3. Two official 21%s, two decades apart, and the ministry has not reconciled them 3.

The meters run smaller than the contracts

TNB's 2025 annual report says 35 data-center projects with about 4.5 gigawatts were connected to its grid by December 2025 while those customers drew 850 megawatts, a 19% utilization rate 1. By August 2026, contracted capacity was 2,346 megawatts and active facilities drew 1,374, or 58.6% 1. The government's answer is rationing: operators seeking grid access must file ten-year staggered projections, sign binding Electricity Supply Agreements, and take access in phases, rules aimed at what the ministry calls "phantom demand" 1.

Data centers took 4.5 GW of TNB grid in 2025 and drew 850 MW of it

  • Capacity connected or contracted
  • Capacity actually drawn
0 MW2,000 MW4,000 MW6,000 MWDec 2025Aug 2026
Data
Capacity connected or contractedCapacity actually drawn
Dec 20254,500 MW850 MW
Aug 20262,346 MW1,374 MW
Data-center capacity connected to, or contracted with, TNB's grid, against the load those customers actually drew. Utilization ran 19% in December 2025 and 58.6% in August 2026. Source: TNB 2025 annual report via AInvest, November 26, 2026.1

YTL Power is where the gap becomes an investment case

The company has invested RM13.5 billion in data centers and plans a 1,200-megawatt park at Kulai in Johor, of which 298 megawatts is contracted 1. Its data-center segment earned RM139.5 million before tax in the September quarter, against RM1.05 million a year earlier; annualized, that is roughly a 4.1% pre-tax yield on the RM13.5 billion of invested capital 1. Group results show the strain: first-quarter revenue rose 41% to RM7.54 billion, but pre-tax profit fell 3% to RM640.0 million and after-tax profit fell 7% 5.

The tape has already repriced the chain

After news of a US shipment freeze, YTL Power fell 10.4% on November 26 9. Between November 13 and 24, Sunway Construction, a campus builder, fell 18.2%, YTL Power 4.4% and TNB 2.5%, against 1.3% for the FBM KLCI 1. Builders who get paid once were marked down hardest; the regulated utility, paid every year on its asset base, moved with the index 1.

After the chip rule, builders fell seven times more than the utility

The builders fell hardest; the regulated utility moved with the index

-20%-15%-10%-5%0%Sunway Construction-18.2%Paid once, on constructionYTL Power-4.4%TNB-2.5%Paid every year, on the asset baseGamuda-1.8%FBM KLCI-1.3%
Data
Value
Sunway Construction-18.2%
YTL Power-4.4%
TNB-2.5%
Gamuda-1.8%
FBM KLCI-1.3%
Share-price change, November 13-24, 2026, after the US chip export rule of mid-November took effect; negative bars are declines. Source: AInvest, November 26, 2026.1

Lenders are splitting the market the same way

A $480 million loan to buy Nvidia−0.01% — Nvidia, down 0.01 percent today processors for a Malaysian data center serving ByteDance has halted, a $488 million syndication for a Johor campus slipped, and Dubai's Damac Digital forfeited deposits on a MYR200.9 million Johor site 1. Capacity leased to US cloud groups remains bankable; China-linked capacity now carries a compliance cost banks price or refuse 1.

The bulls count 298 firm megawatts and a February deadline

CIMB calls YTL's 298 contracted megawatts secure under firm leases, and Kenanga counts 700 megawatts coming online this year 712. The tests are dated: licenses under the new rules fall due by February 17, 2027, and YTL's next contracted-megawatt disclosure follows 710. The contracted megawatts are the only number investors get paid on today; the 2050 forecast is a projection with no revenue behind it yet 710. Track the next contracted-MW disclosure and the February license date.

Sources

  1. 1AInvest, Malaysia's Power Demand Will Double. Data Centres Account for About a Third of the Increase, 26 November 2026
  2. 3Malay Mail, As data centre power share heads for 21pc, Putrajaya moves to avoid 'phantom demand' hogging Malaysia's grid, 4 November 2026
  3. 5MarketScreener (Publicnow), YTL Power: 1st Quarter Revenue Grows 41% to RM7.5 Billion, with Profit After Tax of RM452 Million, 19 November 2026
  4. 7The Star, YTL Power growth prospects remain intact, 19 November 2026
  5. 9The Rakyat Post, No permit, no chips: US trade rule puts Malaysia's data centres on ice, 26 November 2026
  6. 1024/7 Wall St., New U.S. Chip Rule Is Now Hitting AI Data-Center Loans, Not Just Nvidia Chips, 26 November 2026
  7. 12Sinar Daily (Bernama), Data centres to drive TNB growth despite fuel surcharge impact, Kenanga IB, 20 September 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NVDA

Reader comments

0 comments

    Power

    Benson keeps a DTE Energy director on her council as a $474 million rate ruling nears

    A DTE Energy director co-chairs Michigan's governor-elect transition while the utility sues to keep its political money, and in February the commission the new administration will help shape rules on DTE Electric's $474 million rate request. That single order carries the next two years of the company's regulated revenue.

    Power

    PPL Electric's residential power price rises 10.3% Dec. 1; Amazon's $157 million share waits until July 2027

    The increase reflects wholesale power costs, but it lands while the commission still has not ruled on whether Amazon's data center or PPL's customers pay $157 million of the grid built for it. For PPL shareholders, the July 2027 ruling decides whose money funds the AI grid.

    Power

    Kinder Morgan pipelines blew up twice in three days, testing its record $14.4 billion AI gas backlog

    Kinder Morgan operates the Alabama line that blew up on November 21 and a second line that failed in Iowa on November 23, and its record $14.4 billion backlog is pitched on gas for AI data centers. Two fresh failures and a live court challenge now put the safety record, not the demand case, at the center of the stock.

    Power

    CPUC lets PG&E bill customers $456 million early as $8.6 billion of rate requests wait

    The commission granted the first slice on November 19 while 11 more requests worth about $8.6 billion through 2030 wait behind it, and the same day's undergrounding rules shrank the capital program meant to justify the spending.

    Power

    Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million

    Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027.

    Power

    Entergy CEO Drew Marsh says data centers will spare existing customers $7.5 billion

    The figure, given to investors on November 24, appears nowhere in Entergy's latest quarterly filing. Louisiana's utility commission is expected to vote in December on $12.9 billion of gas plants for Meta, and holders of ETR are underwriting that the contract delivers what the forecast assumes.

    Subscribe to TheInference for free