Benson keeps a DTE Energy director on her council as a $474 million rate ruling nears

A DTE Energy director co-chairs Michigan's governor-elect transition while the utility sues to keep its political money, and in February the commission the new administration will help shape rules on DTE Electric's $474 million rate request. That single order carries the next two years of the company's regulated revenue.

Richard TangRichard Tangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Richard Tang. How we work

Share
Jocelyn Benson, Michigan's governor-elect, holding a microphone and smiling at an event in June 2025
Jocelyn Benson, now Michigan's governor-elect, at an event in June 2025. She takes office January 1 and will appoint the commissioners who rule in February on DTE Electric's $474 million rate request.

Michigan governor-elect Jocelyn Benson has kept a DTE Energy−0.06% — DTE Energy, down 0.06 percent today director on her transition leadership council, and in February the state commission she will help shape rules on DTE Electric's $474 million rate request, the decision that sets the utility's revenue into 2028 2. For DTE shareholders, the February order is a priced event; who sits around the incoming governor is an input to it that has not been priced.

A DTE director, a lawsuit and a February order on one calendar

Voters approved Proposal 2 on November 3 with 81 percent support, banning the state's monopoly utilities and their executives from political contributions 4. DTE and Consumers Energy sued in federal court on November 5 to block it, represented by the law firm Miller Johnson 4.

On November 4, Benson named Gary Torgow, chairman of Huntington Bank and a DTE board director, as one of four chairs of her transition leadership council, alongside two Miller Johnson staff 5. State Representative Betsy Coffia called on November 19 for all three to be removed, calling their ties a conflict of interest 1. On November 24 the transition said safeguards exist to guard against conflicts but would not describe them, and it did not say whether Torgow advises on energy policy or whether the three will join the administration 1. The council's work ends Monday 1.

The February order is the number to price

DTE Electric filed on April 28 for a $474 million base-rate increase and a higher allowed return on equity; the Michigan Public Service Commission's final order is expected in February 2. The commission cuts. Last year it approved $242 million of DTE Electric's $574 million request 2.

The commission granted DTE Electric 42% of its last request; $474 million is now pending

  • Requested
  • Approved
  • Estimate
$0M$200M$400M$600M2025 orderFebruary 2027 order
Data
RequestedApproved
2025 order$574M$242M
February 2027 order (estimate)$474M—
Base-rate requests and the amounts approved, $ millions. February 2027 bars show what DTE Electric asked for; the commission has not ruled. Source: DTE Energy Form 10-Q for the quarter ended September 30, 2026.2

DTE Gas, meanwhile, withdrew its notice of intent in October and does not plan to file another rate request until late 2027 6. That makes the February electric order the one near-term chance to reset DTE's regulated revenue. The order also underwrites the buildout: a 1-gigawatt data-center agreement signed in March adds roughly $5 billion of capital spending through 2032, and the November 1 agreement to sell the Vantage segment's renewables and gas businesses for about $3 billion, with DTE retaining its coke operations, leaves the company's earnings increasingly concentrated in the regulated Michigan utilities that ruling covers 2.

DTE's capital spending has outrun its operating cash in 11 of the last 12 quarters

  • Capital spending
  • Operating cash flow
$0.5B$1B$1.5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1.39B
Data
Capital spendingOperating cash flow
Q4 '23$1.12B$0.85B
Q1 '24$1.05B$1.04B
Q2 '24$1B$0.76B
Q3 '24$1.13B$0.76B
Q4 '24$1.25B$1.08B
Q1 '25$0.87B$1.02B
Q2 '25$0.97B$0.71B
Q3 '25$1.22B$0.63B
Q4 '25$1.34B$1.05B
Q1 '26$1.23B$0.91B
Q2 '26$1.49B$0.77B
Q3 '26$1.39B$0.77B
Capital spending and cash from operations, $ billions, by calendar quarter. The gap widens through 2026 as the utility builds for data-center load. Source: DTE Energy quarterly SEC filings.7

The commission's composition is the lever

The Michigan Public Service Commission has three members appointed by the governor to staggered six-year terms, with one designated chair 3. Benson takes office January 1 holding those appointments as a lever on the company's earnings, while a DTE director sat at her transition table and the utility fights in court, through Miller Johnson, to keep its political money 1.

The conflict may be fully managed; the transition declined to say how.

Investors do not need proof of influence to see the structure: the record shows the appointment, the lawsuit and the February ruling sharing one calendar, under a governor who campaigned on lowering utility bills 5. The nearer-term driver of DTE's regulated earnings next year is who Benson names to the commission.

Sources

  1. 1Mid Michigan Now (WSMH), Benson transition responds amid criticism of members connected to anti-Proposal 2 lawsuit, 24 November 2026
  2. 2DTE Energy and DTE Electric, Form 10-Q for the quarter ended 30 September 2026, filed 5 November 2026
  3. 3Michigan Public Service Commission, About the MPSC, accessed 27 November 2026
  4. 4ClickOnDetroit (WDIV), DTE, Consumers Energy sue Michigan over new campaign finance restrictions, 5 November 2026
  5. 5The Daily Caller via MSN, Michigan Democrat who wanted utilities out of politics picks power company director for transition, 11 November 2026
  6. 6WZZM 13 via MSN, DTE Gas commits to not request a rate change until late 2027, 19 November 2026
  7. 7DTE Energy, quarterly figures from its SEC filings, retrieved 27 November 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading DTE

Reader comments

0 comments

    Power

    Malaysia moved its 21% data-center forecast from 2030 to 2050; TNB meters show 850 MW of 4.5 GW drawn

    The same ministry told Parliament on November 4 that data centers would reach 21% of demand by 2030, and on November 26 that the same share arrives by 2050, while TNB's meters show 4.5 gigawatts connected and only 850 megawatts drawn. The gap lands on the merchants who built ahead of the load, YTL Power first.

    Power

    PPL Electric's residential power price rises 10.3% Dec. 1; Amazon's $157 million share waits until July 2027

    The increase reflects wholesale power costs, but it lands while the commission still has not ruled on whether Amazon's data center or PPL's customers pay $157 million of the grid built for it. For PPL shareholders, the July 2027 ruling decides whose money funds the AI grid.

    Power

    Kinder Morgan pipelines blew up twice in three days, testing its record $14.4 billion AI gas backlog

    Kinder Morgan operates the Alabama line that blew up on November 21 and a second line that failed in Iowa on November 23, and its record $14.4 billion backlog is pitched on gas for AI data centers. Two fresh failures and a live court challenge now put the safety record, not the demand case, at the center of the stock.

    Power

    CPUC lets PG&E bill customers $456 million early as $8.6 billion of rate requests wait

    The commission granted the first slice on November 19 while 11 more requests worth about $8.6 billion through 2030 wait behind it, and the same day's undergrounding rules shrank the capital program meant to justify the spending.

    Power

    Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million

    Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027.

    Power

    Entergy CEO Drew Marsh says data centers will spare existing customers $7.5 billion

    The figure, given to investors on November 24, appears nowhere in Entergy's latest quarterly filing. Louisiana's utility commission is expected to vote in December on $12.9 billion of gas plants for Meta, and holders of ETR are underwriting that the contract delivers what the forecast assumes.