Meta's first Oklo payment reached Centrus on November 2, but the fuel ships no earlier than 2029
A hyperscaler's cash has reached the only US company producing commercial HALEU, as credit against fuel that ships no earlier than 2029. The clock it starts runs on a federal lease in Ohio, and Centrus shareholders are the ones holding it.
Richard Tangthree-minute read
Meta's+0.55% — Meta, up 0.55 percent today money has reached a fuel plant. On November 2, an initial amount of Meta's money came out of escrow and was paid directly to Centrus−6.37% — Centrus, down 6.37 percent today, the American uranium-enrichment supplier, as a credit toward fuel orders for Oklo−5.89% — Oklo, down 5.89 percent today, the reactor developer 1. No amount, volume or price is public, and Centrus's own 10-Q, signed November 5, never mentions the payment 2. The first disclosed slice of a hyperscaler's nuclear prepayment has arrived at an enrichment plant while the reactors it is meant to feed are still a plan on paper.
The payment runs the whole chain at once
Meta needs firm power for AI data centers, and a prepayment agreement signed in January lets it fund Oklo's planned 1.2 GW campus in Pike County, Ohio 1. Oklo's Aurora powerhouses burn HALEU, high-assay low-enriched uranium, which no American plant sold commercially until this year 3. At the end of September, Oklo signed Centrus to supply enough of it for up to five powerhouses from its plant in Piketon, the same county 12.
Centrus is enriching that fuel now on a demonstration cascade while it manufactures new centrifuges, and it runs the Piketon expansion's project controls on Palantir's+0.23% — Palantir, up 0.23 percent today AI software 452. The builder converting a capability into a working fuel plant is the right recipient, and the money has found it.
Capex is up more than a hundredfold in two years as Centrus builds Piketon
Data
| Capex | |
|---|---|
| Q4 '23 | $0.5M |
| Q1 '24 | $1.5M |
| Q2 '24 | $0.9M |
| Q3 '24 | $1M |
| Q4 '24 | $0.7M |
| Q1 '25 | $2.1M |
| Q2 '25 | $3.6M |
| Q3 '25 | $4.4M |
| Q4 '25 | $9.6M |
| Q1 '26 | $23.2M |
| Q2 '26 | $71.6M |
| Q3 '26 | $131.6M |
The receipt is dated 2029
A credit toward orders is not fuel. Deliveries begin in 2029 at the earliest, into a campus that is planned but not licensed: the Nuclear Regulatory Commission's Oklo docket shows pre-application work only, no license application for Ohio 3. The plant that would make the fuel sits on government land, and a lease amendment signed in October fixed its expiry at October 1, 2027 2.
The Department of Energy says it will work toward a long-term extension before the end of this year but is under no obligation, and it has told Centrus it does not intend to exercise further production options on the government HALEU contract 2. Capital is no longer the constraint on this chain; a federal signature is.
Shareholders hold the clock
Strip out the loss-making quarter and the two upgrades that lifted the shares late last week 6, and the bull case rests on a $7.0 billion backlog that management itself says is mostly conventional fuel for existing utilities 4. Hyperscaler cash is joining a queue rather than standing alone: X-energy$1B — X-energy, private, latest valuation $1B, Radiant and Antares all signed agreements in the quarter that include prepayments to Centrus 2. Two dates now do the pricing, the Department of Energy's lease decision aimed at year-end and Centrus's investor day at Piketon on December 7 24.
Third quarters are Centrus's trough; this one was the lowest in three years
Quarterly revenue swings on delivery timing while the backlog stretches to 2040
Data
| Revenue | |
|---|---|
| Q4 '23 | $103.6M |
| Q1 '24 | $43.7M |
| Q2 '24 | $189M |
| Q3 '24 | $57.7M |
| Q4 '24 | $151.6M |
| Q1 '25 | $73.1M |
| Q2 '25 | $154.5M |
| Q3 '25 | $74.9M |
| Q4 '25 | $146.2M |
| Q1 '26 | $76.7M |
| Q2 '26 | $176.1M |
| Q3 '26 | $55.5M |
The AI boom has financed American nuclear fuel faster than the government can lease the ground it sits on. The money is in the right hands, with the builder closing the gap between a capability and a working plant. The signature it now waits on sits in Washington, and until it comes, the wait belongs to Centrus shareholders.