Power

National Grid wires five London data centres while its delivery record takes the hits

Reported contracts would wire five London data centres and 1 GW of demand into the grid days after a trade report found National Grid significantly under-delivered boundary capacity in the T2 period. Ofgem is rewriting who pays to connect, and from London to Albany the money is being asked to wait.

Vincent JiangVincent Jiangthree-minute read
Share
National Grid's Creyke Beck high-voltage substation, with transmission towers and lines under a clear sky
1 / 6Slide 1 of 6
National Grid's Creyke Beck substation. The company is contracting the high-voltage cable and substation work meant to wire five London data centres into the grid.

The London hook-up is being contracted

The AI power wave in London is turning into cable and concrete. Key construction contracts on National Grid's−1.29% — National Grid, down 1.29 percent today North West London Upgrade have gone to Laing O'Rourke and to a Hochtief-Murphy joint venture, with the JV installing high-voltage cable and upgrading tunnels 12. The reinforcement exists to connect five data centres with a combined 1 GW of demand 1. No contract value has been disclosed, and the awards rest on syndicated reports citing unnamed media rather than a company announcement 1.

High-voltage power cables racked inside a concrete utility tunnel
High-voltage cable in a utility tunnel, photographed on a US Bureau of Reclamation project. The London contracts cover the same kind of work: high-voltage cable installation and tunnel upgrades in north-west London.Bernie Marine, US Bureau of Reclamation

The hook-up sits inside a near-£5bn build

Behind it sit the £600m substation civils framework National Grid signed with 31 suppliers this month 3 and the £4.3bn, 2 GW Eastern Green Link 2 between Scotland and England, due in 2029 1. Group capex ran to $13.2bn in the year to March 2026, up 16 percent, against revenue that slipped about 1 percent to $23.6bn 4. The spend is contracted. The earnings depend on delivery.

Capex jumped 16 percent in FY2026 while revenue slipped

  • Revenue
  • Capex
$0B$10B$20B$30BFY2025FY2026
Data
RevenueCapex
FY2025$23.9B$11.4B
FY2026$23.6B$13.2B
Fiscal years ended March, as reported to the SEC, in US dollars, rounded to one decimal. Capex rose 16.4 percent year on year while revenue slipped 1.2 percent. Source: Sharadar annual fundamentals from National Grid's SEC filings, retrieved 4 October 2026.10

The delivery record is being scored

On 2 October a trade report found National Grid "significantly under delivered" new boundary capacity in the T2 price-control period 5. Ofgem's assessment of the connections queue, run by the system operator the British state bought from National Grid in 2024, found the reform missed deadlines and sent developers inaccurate offers 6. The regulator is consulting on a refundable connection fee of £237,500 to £712,500 per megawatt for data-centre applicants, after queue demand jumped from 41 GW to 125 GW in seven months, at least 80 GW of it data centres 7. Who pays is being rewritten while the pipes are being laid.

America dangles its own money

The US side softens the picture. The Department of Energy picked National Grid's DREAM dynamic-rating project for about $49m under its SPARK programme, a four-year effort from next year and still subject to a final agreement, a size the company's own statement left out 18. Vice president of engineering Andrew Schneller pitched it as "getting more value from the infrastructure we already have" 8. In New York, the company proposes holding gas delivery rates steady to spring 2028 for nearly 2 million customers, while advocates warn the plan defers charges tied to more than $1.7bn of proposed pipe spending; regulators have no deadline to act 9.

Three dates will score the build-out

Bernstein resumed coverage on 15 September at outperform, 1,310 pence, and the shares sit 18 percent below their 52-week high 1. Watch three dates: distribution flexibility awards in January 2027, from a tender spanning more than 800 zones 1; Albany's ruling whenever it comes 9; and the next price control, which will score the build-out the AI queue is already funding. The hook-up is sold in megawatts and judged in delivery years.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NGG

Reader comments

0 comments

    Power

    An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

    AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Subscribe to TheInference for free