Power

NRG Energy targets a year-end signature on a $3.2 billion Texas data-center plant; the customer is unnamed

CEO Robert Gaudette says terms are agreed on the 1.2-gigawatt Bring Your Own Power deal even as Texas' governor-elect presses a data-center moratorium; NRG is funding buybacks by selling 4.9 gigawatts of operating plants at eight times earnings while the growth project waits on ink.

Vincent JiangVincent Jiangthree-minute read
Share
Gas-fired turbines at the Sand Hill Energy Center in Austin, Texas
1 / 6Slide 1 of 6
A gas-fired power plant in Texas, the kind of generation NRG plans to build for data-center customers under its Bring Your Own Power program. Photo of the Sand Hill Energy Center, Austin Energy.

Terms are agreed, the signature is the target

On Monday's third-quarter call, NRG Energy−0.31% — NRG Energy, down 0.31 percent today chief executive Robert Gaudette answered the question investors have asked since August: when does the unnamed hyperscaler sign? "This project is going to happen," he said. Management has agreed on terms with the customer and is targeting a definitive agreement by year-end, and it is negotiating with the same customer to expand the Texas site to up to 2.4 gigawatts 12.

The economics carry the argument. The 1.2-gigawatt gas plant, part of NRG's Bring Your Own Power program, is expected to cost $3.2 billion and produce about $500 million of annual adjusted EBITDA and $375 million of free cash flow at full operation 2. Capacity payments cover roughly 95% of that free cash flow whether or not the data center draws power, putting the demand risk on the customer, not NRG 2.

The contract runs at least 15 years with an investment-grade guarantee, operations are targeted for late 2029, and the project won conditional inclusion in ERCOT's Batch Zero interconnection process on September 8 2.

NRG sold 4.9 GW of operating plants while holding a 5.4 GW new-build pipeline

The 1.2 GW deal under negotiation sits inside a 5.4 GW secured pipeline

  • Estimate
0 GW2 GW4 GW6 GW2026 contracting target1 GWInitial Texas project1.2 GWExpansion talks, same site2.4 GWSold to LS Power4.9 GWUnsolicited offer, 8.0x 2027 EBITDASecured turbine + EPC pipeline5.4 GW
Data
Value
2026 contracting target (estimate)1 GW
Initial Texas project1.2 GW
Expansion talks, same site (estimate)2.4 GW
Sold to LS Power4.9 GW
Secured turbine + EPC pipeline5.4 GW
Generation capacity in gigawatts. Targets and in-negotiation expansion shown as estimates; sale and secured pipeline as reported. Sources: Crypto Briefing, November 9, 2026; NRG Energy press release, November 9, 2026.2,3

Selling megawatts while the growth case waits

The same day, NRG agreed to sell six gas plants, just under 4.9 gigawatts, back to LS Power for $4 billion, an implied 8.0 times expected 2027 adjusted EBITDA 34. Gaudette called the offer unsolicited and put Jack County's implied value at about $1,400 per kilowatt, against roughly $1,000 per kilowatt to build new Texas capacity 34. Proceeds go to $2 billion of debt reduction, $1 billion of added buybacks within a $3 billion repurchase plan across 2026 and 2027, and $1 billion for growth or further paydown 3.

Half the $4 billion goes to debt, a quarter to buybacks

  • Debt reduction250%
  • Added buybacks125%
  • Growth or further paydown125%
Data
SliceValueShare
Debt reduction250%
Added buybacks125%
Growth or further paydown125%
Planned uses of the $4 billion in proceeds from the LS Power sale, as stated by NRG. Source: NRG Energy press release, November 9, 2026 [3].3

The quarter was strong: adjusted EPS of $4.68 beat estimates by $1.65, revenue rose 24% to $9.47 billion, and adjusted EBITDA reached $2.01 billion 5. But 2027 guidance, midpoints of $9.05 EPS and $5.75 billion EBITDA, excludes the sale 5, and the project's $721 million slice of the 2026 capital plan still awaits a financing partner, ideally by year-end, with equity ruled out 1. Shares rose more than 6% pre-market on the news 6.

Revenue jumped 24% year over year in the quarter the deal news broke

$6B$7B$8B$9B$10B$11BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26$9.47B
Data
Revenue
Q2 '24$6.66B
Q3 '24$7.22B
Q4 '24$6.82B
Q1 '25$8.59B
Q2 '25$6.74B
Q3 '25$7.64B
Q4 '25$7.75B
Q1 '26$10.26B
Q2 '26$7.48B
Q3 '26$9.47B
Revenue in billions of US dollars by calendar quarter, from NRG's SEC filings. Q3 2026's $9.47 billion is up 24% year over year. Source: NRG Energy SEC filings [9].9

The politics Gaudette is betting against

Analysts at Barclays+0.34% — Barclays, up 0.34 percent today, BNP Paribas and Morgan Stanley+0.48% — Morgan Stanley, up 0.48 percent today have trimmed targets on data-center opposition and policy risk 8. Texas governor-elect Gina Hinojosa has called for a moratorium on data-center approvals until the Legislature passes protections, and Governor Abbott froze grid connections and environmental permitting in August pending an audit 7. Gaudette argues turnover helps: incoming officials want community say, protected water supplies and lower bills, and NRG will build where it is welcome 1. The year-end signature, the financing partner and final ERCOT approval are the tells to watch 12.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading NRG

Reader comments

0 comments

    Power

    Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

    Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities