Oklo sends Meta's prepayments to Centrus for fuel due in 2029, with no binding Meta power contract

Oklo signed definitive HALEU contracts with Centrus on November 12, with Meta's prepayment funding fuel that arrives in 2029. The cash flows to the enrichment plant, not the reactor maker, and the numbers that decide Oklo, a plant cost and a binding power contract, are still missing.

Richard TangRichard Tangtwo-minute read
Share
Portrait of Oklo co-founder and chief executive Jacob DeWitte
1 / 6Slide 1 of 6
Jacob DeWitte, co-founder and chief executive of Oklo, which signed definitive fuel contracts with Centrus on November 12 and is still without a binding power contract with Meta.

Oklo−4.23% — Oklo, down 4.23 percent today turned Meta's−0.87% — Meta, down 0.87 percent today money into a fuel contract on November 12, and the money did not stay with Oklo 12. The advanced-nuclear developer signed definitive, multi-year contracts with Centrus Energy−6.67% — Centrus Energy, down 6.67 percent today for high-assay low-enriched uranium, the fuel its Aurora fast reactors need, with prepayments from Oklo funding new enrichment capacity at Centrus' Pike County, Ohio plant and first deliveries only in 2029 12. Read this as supply-chain progress, not demand: nothing in the filings says a binding power contract with Meta now exists, and that is the link that still decides whether Oklo gets built.

Meta's prepayment stops at the enrichment plant

Trace the cash. Meta agreed in January to prepay for electricity from Oklo's planned 1.2 GW Ohio campus, with the payment tied to project progress 5. That cash sits in Oklo, which held $3.13 billion of cash and securities at the end of September, a balance that grew only because Oklo sold $2.3 billion of stock in nine months 3. Now part of it moves out again, as prepayments to a centrifuge plant, for fuel Oklo cannot burn before 2029 1. The volume covers up to five Auroras; the disclosed scope is fuel, not customers 1.

Oklo's cash jumped on a share sale in early 2026 and has not grown since

$0B$0.5B$1B$1.5B$2BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1.62B
Data
Cash and cash equivalents
Q2 '24$0.11B
Q3 '24$0.09B
Q4 '24$0.1B
Q1 '25$0.09B
Q2 '25$0.23B
Q3 '25$0.41B
Q4 '25$0.79B
Q1 '26$1.59B
Q2 '26$1.65B
Q3 '26$1.62B
Cash and cash equivalents at quarter end, which exclude marketable securities; the $3.13 billion Oklo reported at the end of September counts both. The balance rose as Oklo sold shares, not from operations, and has been flat near $1.6 billion since March. Source: Oklo quarterly SEC filings [7].6

Centrus books the demand, Oklo carries the risk

Centrus is the clearer beneficiary. It now counts $5.4 billion of customer contracts and commitments against the new capacity, and Oklo's prepayments help fund a buildout whose risk now sits partly on Oklo's balance sheet 12. For a supplier, prepaid demand is the best kind.

The plant cost and the prepayment amount are still undisclosed

How much Oklo prepaid is not in the release. Neither is the cost of a single Aurora plant, which Oklo has never given, with the fiscal-year report expected in March the next chance to get one 34. Analysts model about $6.3 billion of free-cash burn from 2026 through 2030, roughly twice the cash on hand, and at $5.1 billion of market value investors are paying about $2 billion above net cash for a company with 2028 consensus revenue of $39 million 34. Craig-Hallum halved its target to $27 on November 9 for exactly this reason 3. The stock fell on the news 1.

Oklo's cash use has moved from overhead to capital spending: $154M in one quarter

  • Capex
  • Operating cash used
$0M$50M$100M$150M$200MQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$154M
Data
CapexOperating cash used
Q4 '24$0M$13M
Q1 '25$0M$12M
Q2 '25$1M$18M
Q3 '25$5M$18M
Q4 '25$27M$33M
Q1 '26$33M$18M
Q2 '26$94M$48M
Q3 '26$154M$45M
Capital spending and operating cash used, by quarter, in millions of dollars; cash outflows are shown as positive. Oklo has never disclosed the cost of one Aurora plant, which is what this spending is building. Source: Oklo quarterly SEC filings [7].6

The judgment: fuel in 2029 is a real, necessary hop, and the builders funding enrichment capacity today deserve the work. But until a binding Meta contract or an Idaho plant cost appears, every announcement moves cash out of a pile that already covers only half the projected burn.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading META

Reader comments

0 comments

    Power

    NRG sells six gas plants back to LS Power for $4 billion, nine months after buying them

    Nine months after buying the fleet from LS Power, NRG sells six plants back for $4.0 billion at 8.0x forward EBITDA, routing the cash to $3 billion of buybacks and debt paydown while the buyer bets scarcity keeps repricing gas upward.

    Power

    NuScale reported $281,000 of revenue last quarter

    NuScale is spending shareholder cash to build a reactor whose buyer, through ENTRA1 and the Tennessee Valley Authority, has signed nothing. A securities class action filed November 11 says the gap between that story and those bills was concealed.

    Power

    Energy Department clears Oklo's Groves-1 reactor for unrestricted operations

    The November 11 clearance is the regulatory proof the $5.1 billion developer's fast-fission design works. The money question is untouched: analysts project roughly $6.3 billion of free cash flow burned by 2030 against $3.13 billion of cash on hand, and the gap so far has been paid for in stock.

    Power

    Exelon asks FERC to delay PJM's 2030/31 capacity auction to 2030 as load forecasts hit 21.7%

    Exelon, whose utilities buy power for about 10.7 million PJM customers, says the region's capacity market can no longer price AI-era demand three years ahead. Its own third-quarter filing shows the affordability squeeze that follows.

    Power

    Fluence Energy reports Nov. 23 under interim CEOs from Siemens and AES, stock down 73%

    Results on November 23, the first under interim chiefs on loan from Siemens and AES, land four days before the lead-plaintiff deadline in a suit claiming Fluence called a hand-welding plant fully automated. The shares have lost 73% since February; the backlog sits at a record $6.4 billion.

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.