Oklo sends Meta's prepayments to Centrus for fuel due in 2029, with no binding Meta power contract
Oklo signed definitive HALEU contracts with Centrus on November 12, with Meta's prepayment funding fuel that arrives in 2029. The cash flows to the enrichment plant, not the reactor maker, and the numbers that decide Oklo, a plant cost and a binding power contract, are still missing.
Richard Tangtwo-minute read
Oklo−4.23% — Oklo, down 4.23 percent today turned Meta's−0.87% — Meta, down 0.87 percent today money into a fuel contract on November 12, and the money did not stay with Oklo 12. The advanced-nuclear developer signed definitive, multi-year contracts with Centrus Energy−6.67% — Centrus Energy, down 6.67 percent today for high-assay low-enriched uranium, the fuel its Aurora fast reactors need, with prepayments from Oklo funding new enrichment capacity at Centrus' Pike County, Ohio plant and first deliveries only in 2029 12. Read this as supply-chain progress, not demand: nothing in the filings says a binding power contract with Meta now exists, and that is the link that still decides whether Oklo gets built.
Meta's prepayment stops at the enrichment plant
Trace the cash. Meta agreed in January to prepay for electricity from Oklo's planned 1.2 GW Ohio campus, with the payment tied to project progress 5. That cash sits in Oklo, which held $3.13 billion of cash and securities at the end of September, a balance that grew only because Oklo sold $2.3 billion of stock in nine months 3. Now part of it moves out again, as prepayments to a centrifuge plant, for fuel Oklo cannot burn before 2029 1. The volume covers up to five Auroras; the disclosed scope is fuel, not customers 1.
Oklo's cash jumped on a share sale in early 2026 and has not grown since
Data
| Cash and cash equivalents | |
|---|---|
| Q2 '24 | $0.11B |
| Q3 '24 | $0.09B |
| Q4 '24 | $0.1B |
| Q1 '25 | $0.09B |
| Q2 '25 | $0.23B |
| Q3 '25 | $0.41B |
| Q4 '25 | $0.79B |
| Q1 '26 | $1.59B |
| Q2 '26 | $1.65B |
| Q3 '26 | $1.62B |
Centrus books the demand, Oklo carries the risk
Centrus is the clearer beneficiary. It now counts $5.4 billion of customer contracts and commitments against the new capacity, and Oklo's prepayments help fund a buildout whose risk now sits partly on Oklo's balance sheet 12. For a supplier, prepaid demand is the best kind.
The plant cost and the prepayment amount are still undisclosed
How much Oklo prepaid is not in the release. Neither is the cost of a single Aurora plant, which Oklo has never given, with the fiscal-year report expected in March the next chance to get one 34. Analysts model about $6.3 billion of free-cash burn from 2026 through 2030, roughly twice the cash on hand, and at $5.1 billion of market value investors are paying about $2 billion above net cash for a company with 2028 consensus revenue of $39 million 34. Craig-Hallum halved its target to $27 on November 9 for exactly this reason 3. The stock fell on the news 1.
Oklo's cash use has moved from overhead to capital spending: $154M in one quarter
- Capex
- Operating cash used
Data
| Capex | Operating cash used | |
|---|---|---|
| Q4 '24 | $0M | $13M |
| Q1 '25 | $0M | $12M |
| Q2 '25 | $1M | $18M |
| Q3 '25 | $5M | $18M |
| Q4 '25 | $27M | $33M |
| Q1 '26 | $33M | $18M |
| Q2 '26 | $94M | $48M |
| Q3 '26 | $154M | $45M |
The judgment: fuel in 2029 is a real, necessary hop, and the builders funding enrichment capacity today deserve the work. But until a binding Meta contract or an Idaho plant cost appears, every announcement moves cash out of a pile that already covers only half the projected burn.